9607 N ORION AVE 91343
Certificate Information: 9607 N ORION AVE 91343
- Application / Permit
- 17010-20000-04280
- Plan Check / Job No.
- B17VN16861
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED (N) (29'-1" X 45') DETACHED ACCESSORY DWELLING UNIT PER AB 2299 AND SB 1069 W/ ATTACHED 3' X 8'-6" COVERED PATIO PER WFPP
- Permit Issued
- Issued on 4/6/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2017 | RAPHAEL ROSAS |
| Corrections Issued | 11/28/2017 | RAPHAEL ROSAS |
| Quality Review Completed | 12/6/2017 | STEVEN KIM |
| Building Plans Picked Up | 12/8/2017 | APPLICANT |
| Green Plans Picked Up | 12/8/2017 | APPLICANT |
| Applicant returned to address corrections | 1/23/2018 | RAPHAEL ROSAS |
| Plan Check Approved | 4/6/2018 | RAPHAEL ROSAS |
| Issued | 4/6/2018 | LADBS |
| CofO in Progress | 7/22/2022 | GREGG CUMMINGS |
| CofO Issued | 8/16/2022 | MICHAEL SMITH |
| Permit Finaled | 8/16/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2017 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2017 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 12/12/2017 | JOHN DALLAS |
| Low Impact Development | Cleared | 1/2/2018 | MARTIN FRAGOSO |
| Green Code | Cleared | 1/11/2018 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 1/23/2018 | EDUARDO PEDROZA |
| Private sewage disp. approval | Cleared | 4/6/2018 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 4/27/2021 | Partial Approval | GREGG CUMMINGS |
| Special/Order Compliance | 4/27/2021 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 6/30/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 6/30/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 7/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 7/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 7/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/22/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 7/22/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Rough | 7/22/2021 | Approved | ARTHUR SARGSYAN |
| MERV13>=Rough | 7/22/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 7/22/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Verify Sprinkler Sign Off | 7/22/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Rough | 7/23/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/26/2021 | Partial Approval | ALAN MORELOS |
| Shower Pan | 7/26/2021 | Not Ready for Inspection | ALAN MORELOS |
| BUILDING-Rough-Frame | 7/27/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 7/27/2021 | Approved | GREGG CUMMINGS |
| MERV13>=Rough | 7/27/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 7/27/2021 | Approved | GREGG CUMMINGS |
| Shower Pan | 7/27/2021 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 7/27/2021 | Approved | GREGG CUMMINGS |
| Insulation | 7/30/2021 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 8/3/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 8/18/2021 | Not Ready for Inspection | AMY COLIN |
| Underground Mechanical | 8/18/2021 | Corrections Issued | AMY COLIN |
| Interior/Exterior Lathing | 8/31/2021 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 9/15/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 5/16/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 5/16/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 5/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 5/16/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 5/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 5/16/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 5/16/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 5/16/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 5/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 5/31/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 5/31/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 6/17/2022 | Corrections Issued | GREGG CUMMINGS |
| Service/Power Release | 6/17/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 7/11/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 7/11/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 7/18/2022 | Corrections Issued | GREGG CUMMINGS |
| Service/Power Release | 7/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/21/2022 | Approved | GREGG CUMMINGS |
| Final | 7/21/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 7/21/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 7/21/2022 | Approved | GREGG CUMMINGS |
| Service/Power Release | 7/21/2022 | Approved | GREGG CUMMINGS |