166 S ALVARADO ST 90057

Certificate Information: 166 S ALVARADO ST 90057

Application / Permit
17010-20000-04073
Plan Check / Job No.
B17VN16040
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 84 UNIT, 5 STORY APARTMENT/GARAGE BUILDING. 1ST FLOOR IS TYPE IA AND THE UPPER 4 STORIES ARE TYPE IIB CONSTRUCTION. THE UPPER 4 STORIES ARE FACTORY BUILT HOUSING APPROVED BY THE STATE TO STACK 4 HIGH. TOC, TIER 3 PROJECT: 83 ARE RESTRICTED AFFORDABLE (7 EXTREMELY LOW INCOME, 4 VERY LOW INCOME AND 72 LOW INCOME UNITS) STAIRS, PT SLABS ARE DEFERRED,
Permit Issued
Issued on 12/28/2018
Issuing Office
Metro
Current Status
CofO Issued on 11/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2017 APPLICANT
Assigned to Plan Check Engineer 11/16/2017 JOHN VASQUEZ
Green Plans Picked Up 11/16/2017 APPLICANT
Disabled Access Plans Picked Up 11/22/2017 APPLICANT
Corrections Issued 11/27/2017 JOHN VASQUEZ
Quality Review Completed 11/27/2017 JOHN VASQUEZ
Building Plans Picked Up 11/28/2017 APPLICANT
Applicant returned to address corrections 4/3/2018 JOHN VASQUEZ
Applicant returned to address corrections 6/20/2018 JOHN VASQUEZ
Applicant returned to address corrections 8/16/2018 JOHN VASQUEZ
Applicant returned to address corrections 9/21/2018 JOHN VASQUEZ
Applicant returned to address corrections 9/24/2018 JOHN VASQUEZ
Applicant returned to address corrections 9/25/2018 JOHN VASQUEZ
Applicant returned to address corrections 10/2/2018 JOHN VASQUEZ
Applicant returned to address corrections 11/6/2018 JOHN VASQUEZ
Applicant returned to address corrections 11/29/2018 JOHN VASQUEZ
Applicant returned to address corrections 12/10/2018 JOHN VASQUEZ
Applicant returned to address corrections 12/19/2018 JOHN VASQUEZ
Plan Check Approved 12/28/2018 JOHN VASQUEZ
Issued 12/28/2018 LADBS
TCO Issued (Expire Date: 02-06-2022) 8/10/2021 DAVID TSAU
TCO Issued (Expire Date: 08-27-2022) 2/28/2022 ERNESTO CORRAL
CofO in Progress 11/30/2022 ERNESTO CORRAL
Permit Finaled 11/30/2022 ERNESTO CORRAL
CofO Issued 11/30/2022 ERNESTO CORRAL
Permit Finaled 11/30/2022 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 6/14/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 7/5/2018 GEORGE SUCHAND
DAS Clearance Cleared 8/15/2018 JOHN VASQUEZ
Green Code Cleared 8/15/2018 MICHAEL AYERS
CPC Cleared 8/16/2018 ERIC CLAROS
Eng Process Fee Ord 176,300 Cleared 8/16/2018 MICHAEL CASTILLO
Miscellaneous Cleared 8/16/2018 ERIC CLAROS
Opn space landscape/Water mgmt Cleared 8/16/2018 ERIC CLAROS
Site Plan review Cleared 8/16/2018 ERIC CLAROS
Bicycle Parking Cleared 9/7/2018 KAREN LE
Encroachment in public way Cleared 9/7/2018 KAREN LE
Driveway location Cleared 9/11/2018 MOHAMMAD HASAN
Sewer availability Cleared 9/14/2018 KARAN PATEL
Low Impact Development Cleared 10/2/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/2/2018 SOPHEA EK
Stormwater Pollution Mitigatn Cleared 10/2/2018 MARTIN FRAGOSO
Methane Ordinance Cleared 10/4/2018 WILLIAM JOHNS
Permit Cleared 10/5/2018 SOPHEA EK
Highway dedication Cleared 10/9/2018 ADOLFO GUTIERREZ
Fire Marshall Fire Life Safety Cleared 11/1/2018 OSCAR SALGADO JR
DCP conditions approval Cleared 11/8/2018 DORIS KWOK
Density Bonus 12.22.A.25 Cleared 11/8/2018 DORIS KWOK
Density Bonus 12.22.A.31 Cleared 11/8/2018 DORIS KWOK
Work Adjacent to Public Way Cleared 11/30/2018 HOK CHI CHIU
Building over 3-story or 36-ft Cleared 12/10/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/10/2018 CALOSHA APPROVED

Contact Information

Architect Wong,, Wilbur; Lic. No.: C29795 9142 HYDE PARK DRIVE      HUNTINGTON BEACH, CA 92646
Engineer Fernandez,, Agapito B; Lic. No.: C56546 7400 E SLAUSON AVE STE S      COMMERCE, CA 90040
Engineer Patel,, Sharad T; Lic. No.: S4488 104 LATTICE      IRVINE, CA 92603

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/21/2019 Partial Inspection LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 3/29/2019 Partial Inspection LESLIE TRUJILLO
Piling/Pier/Caisson 3/29/2019 Partial Inspection LESLIE TRUJILLO
Piling/Pier/Caisson 4/2/2019 Partial Approval LESLIE TRUJILLO
Piling/Pier/Caisson 4/5/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/15/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 4/15/2019 Partial Approval LESLIE TRUJILLO
METHANE-Subgrade 4/15/2019 Partial Approval LESLIE TRUJILLO
Masonry Wall/Backfill 4/26/2019 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 5/3/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 5/3/2019 Conditional Approval DANIEL COLLINS
Green Building Rough 5/3/2019 Approved DANIEL COLLINS
METHANE-Rough 5/3/2019 Partial Approval DANIEL COLLINS
Masonry Wall/Backfill 5/3/2019 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 5/3/2019 Partial Approval DANIEL COLLINS
Verify Sprinkler Sign Off 5/3/2019 Partial Inspection DANIEL COLLINS
Deputy Methane Barrier 5/8/2019 Approved DANIEL COLLINS
METHANE-Rough 5/9/2019 Partial Approval DANIEL COLLINS
Masonry Wall/Backfill 5/9/2019 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 5/9/2019 Partial Approval DANIEL COLLINS
Verify Sprinkler Sign Off 5/9/2019 Partial Inspection DANIEL COLLINS
Footing/Foundation/Slab 5/21/2019 Partial Approval DANIEL COLLINS
METHANE-Barrier 5/21/2019 Partial Approval DANIEL COLLINS
METHANE-Subgrade 5/21/2019 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 5/24/2019 Partial Approval DANIEL COLLINS
METHANE-Barrier 5/24/2019 Partial Inspection DANIEL COLLINS
METHANE-Subgrade 5/24/2019 Partial Inspection DANIEL COLLINS
Deputy Methane Barrier 7/2/2019 Conditional Approval DANIEL COLLINS
Masonry Wall/Backfill 7/2/2019 Partial Approval DANIEL COLLINS
METHANE-Rough 7/18/2019 Partial Approval DANIEL COLLINS
SUSMP-Std. Urban Storm Water 7/18/2019 Conditional Approval DANIEL COLLINS
Pre-Inspection 7/24/2019 Corrections Issued DANIEL COLLINS
Footing/Foundation/Slab 9/5/2019 Partial Inspection DANIEL COLLINS
METHANE-Barrier 9/5/2019 Partial Inspection DANIEL COLLINS
METHANE-Rough 9/5/2019 Partial Inspection DANIEL COLLINS
METHANE-Subgrade 9/5/2019 Partial Inspection DANIEL COLLINS
Reinforced Concrete Frame 9/5/2019 Partial Inspection DANIEL COLLINS
Verify Sprinkler Sign Off 9/5/2019 Approved DANIEL COLLINS
Deputy Pre-Stress Concrete 9/6/2019 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 9/6/2019 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 9/6/2019 Conditional Approval DANIEL COLLINS
Pre-Inspection 9/10/2019 Partial Inspection DANIEL COLLINS
Pre-Inspection 9/11/2019 Partial Inspection DANIEL COLLINS
Pre-Inspection 9/12/2019 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 9/13/2019 Conditional Approval DANIEL COLLINS
Reinforced Concrete Frame 9/13/2019 Conditional Approval DANIEL COLLINS
METHANE-Rough 9/17/2019 Partial Inspection DANIEL COLLINS
Reinforced Concrete Frame 9/17/2019 Partial Inspection DANIEL COLLINS
METHANE-Rough 9/19/2019 Not Ready for Inspection DANIEL COLLINS
Reinforced Concrete Frame 9/19/2019 Corrections Issued DANIEL COLLINS
Light Gage Steel Frame 9/24/2019 Partial Inspection DANIEL COLLINS
Reinforced Concrete Frame 9/26/2019 Partial Inspection DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 9/27/2019 Partial Approval DANIEL COLLINS
Wall Anchors 10/3/2019 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/10/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 10/10/2019 Partial Approval DANIEL COLLINS
METHANE-Rough 10/10/2019 Approved DANIEL COLLINS
Reinforced Concrete Frame 10/10/2019 Partial Approval DANIEL COLLINS
Deputy Methane Barrier 10/24/2019 Conditional Approval DANIEL COLLINS
Structural Steel Frame 10/24/2019 Corrections Issued DANIEL COLLINS
Structural Steel Frame 11/6/2019 Partial Inspection DANIEL COLLINS
SUSMP-Std. Urban Storm Water 11/14/2019 Partial Approval DANIEL COLLINS
Structural Steel Frame 11/18/2019 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 11/21/2019 Approved DANIEL COLLINS
METHANE-Barrier 11/21/2019 Approved DANIEL COLLINS
METHANE-Subgrade 11/21/2019 Approved DANIEL COLLINS
Deputy Reinf. Concrete 11/25/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/26/2019 Conditional Approval DANIEL COLLINS
Pre-Inspection 12/20/2019 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 1/3/2020 Partial Inspection DANIEL COLLINS
Light Gage Steel Frame 1/7/2020 Corrections Issued DANIEL COLLINS
Pre-Inspection 1/7/2020 Partial Inspection DANIEL COLLINS
Reinforced Concrete Frame 1/9/2020 Conditional Approval DANIEL COLLINS
Pre-Inspection 1/14/2020 Partial Approval DANIEL COLLINS
Structural Steel Frame 1/15/2020 Corrections Issued DANIEL COLLINS
Light Gage Steel Frame 1/22/2020 Corrections Issued DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 2/10/2020 Partial Approval DANIEL COLLINS
Pre-Inspection 2/13/2020 Partial Inspection DANIEL COLLINS
Insulation 2/18/2020 Not Ready for Inspection DANIEL COLLINS
Drywall Nailing 2/21/2020 Partial Approval DANIEL COLLINS
Insulation 2/21/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 2/21/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 2/27/2020 Partial Approval DANIEL COLLINS
Insulation 2/27/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 3/6/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 3/10/2020 Partial Approval DANIEL COLLINS
Pre-Inspection 3/10/2020 Partial Inspection DANIEL COLLINS
Pre-Inspection 3/13/2020 Partial Inspection DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 3/20/2020 Partial Approval DANIEL COLLINS
Pre-Inspection 4/10/2020 Partial Inspection DANIEL COLLINS
Drywall Nailing 4/17/2020 Partial Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Approved DANIEL COLLINS
Insulation 4/21/2020 Partial Approval DANIEL COLLINS
Structural Steel Frame 4/21/2020 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 4/23/2020 Partial Approval DANIEL COLLINS
Insulation 4/23/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 4/23/2020 Partial Approval DANIEL COLLINS
Insulation 4/28/2020 Partial Approval DANIEL COLLINS
Structural Steel Frame 4/28/2020 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 4/30/2020 Partial Approval DANIEL COLLINS
Insulation 4/30/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 4/30/2020 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 5/19/2020 Partial Approval DANIEL COLLINS
T-Bar Ceiling 5/19/2020 Conditional Approval DANIEL COLLINS
Light Gage Steel Frame 5/26/2020 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 5/28/2020 Partial Approval DANIEL COLLINS
Insulation 5/28/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 5/28/2020 Partial Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 6/3/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 6/3/2020 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 6/9/2020 Partial Approval DANIEL COLLINS
Insulation 6/9/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 6/16/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 6/19/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 6/19/2020 Not Ready for Inspection DANIEL COLLINS
Light Gage Steel Frame 6/22/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 7/9/2020 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 7/9/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 7/9/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 7/14/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 7/16/2020 Not Ready for Inspection DANIEL COLLINS
Footing/Foundation/Slab 7/20/2020 Partial Approval DANIEL COLLINS
Masonry Wall/Backfill 7/23/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 7/24/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 8/25/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 9/23/2020 Partial Approval DANIEL COLLINS
Special/Order Compliance 11/18/2020 Partial Inspection DANIEL COLLINS
Special/Order Compliance 12/2/2020 Partial Inspection DANIEL COLLINS
Drywall Nailing 12/8/2020 Partial Approval DANIEL COLLINS
Special/Order Compliance 12/22/2020 Partial Approval DANIEL COLLINS
Pre-Inspection 1/8/2021 Partial Inspection DANIEL COLLINS
Final 1/26/2021 Corrections Issued DANIEL COLLINS
Footing/Foundation/Slab 1/26/2021 Approved DANIEL COLLINS
Green Building Final 1/26/2021 Not Ready for Inspection DANIEL COLLINS
Reinforced Concrete Frame 1/26/2021 Approved DANIEL COLLINS
Reinforced Masonry Frame 1/26/2021 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 1/26/2021 SGSOV Approved DANIEL COLLINS
SUSMP-Std. Urban Storm Water 1/26/2021 Not Ready for Inspection DANIEL COLLINS
Smoke Detectors 1/26/2021 Not Ready for Inspection DANIEL COLLINS
Special/Order Compliance 1/26/2021 Approved DANIEL COLLINS
Pre-Inspection 1/27/2021 Partial Inspection DANIEL COLLINS
Final 2/23/2021 Not Ready for Inspection DANIEL COLLINS
Green Building Final 2/23/2021 Not Ready for Inspection DANIEL COLLINS
SUSMP-Std. Urban Storm Water 2/23/2021 Not Ready for Inspection DANIEL COLLINS
Smoke Detectors 2/23/2021 Not Ready for Inspection DANIEL COLLINS
Special/Order Compliance 2/23/2021 Approved DANIEL COLLINS
Special/Order Compliance 3/4/2021 Approved DANIEL COLLINS
Pre-Inspection 3/8/2021 Partial Inspection DANIEL COLLINS
Green Building Final 3/15/2021 Approved DANIEL COLLINS
Special/Order Compliance 3/15/2021 Approved DANIEL COLLINS
Special/Order Compliance 4/29/2021 Partial Inspection DANIEL COLLINS
Pre-Inspection 6/23/2021 Partial Approval DANIEL COLLINS
Pre-Inspection 7/9/2021 Partial Approval DANIEL COLLINS
Special/Order Compliance 1/13/2022 Approved EDWIN GREGORYONA
Special/Order Compliance 8/3/2022 Approved ERNESTO CORRAL
Final 11/30/2022 OK to Issue CofO ERNESTO CORRAL
SUSMP-Std. Urban Storm Water 11/30/2022 Approved ERNESTO CORRAL
Smoke Detectors 11/30/2022 Approved ERNESTO CORRAL