20700 W SESNON BLVD 91326
Certificate Information: 20700 W SESNON BLVD 91326
- Application / Permit
- 17010-20000-04058
- Plan Check / Job No.
- B17VN15970
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- (N) 1-STORY OFFICE/GUARDHOUSE W/ COVERED DRIVEWAY.
- Permit Issued
- Issued on 2/6/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2017 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/30/2017 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/31/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/31/2017 | APPLICANT |
| Disabled Access Plans Picked Up | 10/31/2017 | APPLICANT |
| Green Plans Picked Up | 10/31/2017 | APPLICANT |
| Plan Check Approved | 2/6/2018 | NILOOFAR MEHRAIN |
| Issued | 2/6/2018 | LADBS |
| CofO in Progress | 5/5/2021 | JEFFREY DURAN |
| Permit Finaled | 5/21/2021 | RICKEY JACKSON |
| CofO Issued | 5/21/2021 | RICKEY JACKSON |
| Permit Finaled | 5/21/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| "T" removal | Cleared | 12/12/2017 | ANNA VIDAL |
| CPC | Cleared | 12/12/2017 | ANNA VIDAL |
| Miscellaneous | Cleared | 12/12/2017 | ANNA VIDAL |
| Specific Plan | Cleared | 12/12/2017 | ANNA VIDAL |
| Tract Map conditions | Cleared | 12/12/2017 | ANNA VIDAL |
| Tract Map conditions | Cleared | 12/12/2017 | ANNA VIDAL |
| Tract Map conditions | Cleared | 12/12/2017 | ANNA VIDAL |
| Tract Map conditions | Cleared | 12/12/2017 | ANNA VIDAL |
| ZA Case | Cleared | 12/12/2017 | ANNA VIDAL |
| ZA Case | Cleared | 12/12/2017 | ANNA VIDAL |
| Address approval | Cleared | 12/21/2017 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 12/21/2017 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 12/21/2017 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 12/21/2017 | KAYLA PEJI |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2017 | KAYLA PEJI |
| Roof/Waste drainage to street | Cleared | 12/21/2017 | KAYLA PEJI |
| Sewer availability | Cleared | 12/21/2017 | KAYLA PEJI |
| Low Impact Development | Cleared | 1/4/2018 | AMMAR ELTAWIL |
| Green Code | Cleared | 1/9/2018 | MICHAEL AYERS |
| DAS Clearance | Cleared | 1/17/2018 | NORLITO MEDRANO |
| GPI Written Notices | Cleared | 1/17/2018 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 1/17/2018 | NILOOFAR MEHRAIN |
| Hydrant and Access approval | Cleared | 2/5/2018 | ROBERT DUFF |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
| Engineer | Nelson, William Mc Kee; Lic. No.: S3417 | 5 DELLWOOD DOVE CANYON, CA 92679 |
| Engineer | Toedter, Randy Wayne; Lic. No.: C37316 | 7474 EISENHOWER ST VENTURA, CA 93003 |
| Engineer | Wong, Ramon Roman Ii; Lic. No.: S2345 | 1800 E. 16TH STREET SANTA ANA, CA 92701 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/5/2018 | Not Ready for Inspection | ROBERT COLE |
| METHANE-Barrier | 4/5/2018 | Not Ready for Inspection | ROBERT COLE |
| METHANE-Subgrade | 4/5/2018 | Not Ready for Inspection | ROBERT COLE |
| Pre-Inspection | 4/5/2018 | Not Ready for Inspection | ROBERT COLE |
| Footing/Foundation/Slab | 4/19/2018 | Corrections Issued | DANNY RODRIGUEZ |
| METHANE-Barrier | 4/19/2018 | Not Ready for Inspection | DANNY RODRIGUEZ |
| METHANE-Subgrade | 4/19/2018 | Corrections Issued | DANNY RODRIGUEZ |
| Deputy Pre-Stress Concrete | 4/20/2018 | Conditional Approval | ROBERT COLE |
| Excavation/Setback/Form/Re-Bar | 4/20/2018 | Partial Approval | ROBERT COLE |
| Pre-Inspection | 4/20/2018 | Approved | ROBERT COLE |
| Deputy Reinf. Concrete | 4/24/2018 | Conditional Approval | ROBERT COLE |
| Footing/Foundation/Slab | 4/26/2018 | Approved | ROBERT COLE |
| METHANE-Barrier | 4/26/2018 | Approved | ROBERT COLE |
| METHANE-Subgrade | 4/26/2018 | Approved | ROBERT COLE |
| Deputy Pre-Stress Concrete | 5/1/2018 | Conditional Approval | ROBERT COLE |
| Deputy Wood Construction | 5/3/2018 | Conditional Approval | ROBERT COLE |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2018 | Partial Approval | ROBERT COLE |
| Pre-Inspection | 5/3/2018 | Partial Inspection | ROBERT COLE |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2018 | Partial Approval | ROBERT COLE |
| Green Building Rough | 6/4/2018 | Not Ready for Inspection | ROBERT COLE |
| METHANE-Rough | 6/4/2018 | Partial Inspection | ROBERT COLE |
| Verify Sprinkler Sign Off | 6/4/2018 | Conditional Approval | ROBERT COLE |
| Wood Frame | 6/4/2018 | Partial Approval | ROBERT COLE |
| Insulation | 6/6/2018 | Approved | ROBERT COLE |
| Interior/Exterior Lathing | 6/7/2018 | Approved | ROBERT COLE |
| Drywall Nailing | 6/8/2018 | Approved | ROBERT COLE |
| Pre-Inspection | 9/30/2019 | Partial Inspection | ROBERT COLE |
| Special/Order Compliance | 5/7/2020 | Partial Inspection | JEFFREY FULTON |
| Final | 2/23/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| Green Building Final | 2/23/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| Green Building Rough | 2/23/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| SGSOV-Seismic Gas S/O Valve | 2/23/2021 | SGSOV Not Ready | HAMID PISHEHVAR |
| Smoke Detectors | 2/23/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| Verify Sprinkler Sign Off | 2/23/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| Wood Frame | 2/23/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| Final | 2/26/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| Green Building Final | 2/26/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| Green Building Rough | 2/26/2021 | Approved | HAMID PISHEHVAR |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV No Gas | HAMID PISHEHVAR |
| Smoke Detectors | 2/26/2021 | Approved | HAMID PISHEHVAR |
| Verify Sprinkler Sign Off | 2/26/2021 | Approved | HAMID PISHEHVAR |
| Wood Frame | 2/26/2021 | Approved | HAMID PISHEHVAR |
| Final | 3/3/2021 | Partial Approval | HAMID PISHEHVAR |
| Green Building Final | 3/3/2021 | Approved | HAMID PISHEHVAR |