11311 W CHANDLER BLVD 91601

Certificate Information: 11311 W CHANDLER BLVD 91601

Application / Permit
17010-20000-03994
Plan Check / Job No.
B17VN13190
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
Seven-story mixed use building (five-story of Type III-A residential building over two-story Type I-A Concrete Podium) over two levels subterranean parking garage. Project contains 127 dwelling units, with 11 dwelling units reserved for Very Low Income Households, with a ground floor commercial/retail (Core & Shell) space.
Permit Issued
Issued on 9/25/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2017 APPLICANT
Assigned to Plan Check Engineer 10/19/2017 DOUGLAS NAKATANI
Corrections Issued 10/31/2017 DOUGLAS NAKATANI
Quality Review Completed 11/1/2017 GUANG MIN TUNG
Building Plans Picked Up 11/2/2017 APPLICANT
Applicant returned to address corrections 7/18/2018 JEFFREY TANGONAN
Plan Check Approved 9/23/2019 JEFFREY TANGONAN
Issued 9/25/2019 LADBS
TCO Issued (Expire Date: 06-13-2023) 12/15/2022 RICKEY JACKSON
CofO in Progress 8/30/2023 JOHN KITCKO
Permit Finaled 8/30/2023 RICKEY JACKSON
CofO Issued 8/30/2023 RICKEY JACKSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/19/2018 EDUARDO PEDROZA
Highway dedication Cleared 5/24/2018 MARKOS PEREZ-BRAN
Sewer availability Cleared 5/24/2018 MARKOS PEREZ-BRAN
Green Code Cleared 8/13/2018 MICHAEL AYERS
Miscellaneous Cleared 9/25/2018 LEE GUILBEAUX
DCP conditions approval Cleared 2/13/2019 JAMES MCCARTHY
Density Bonus 12.22.A.25 Cleared 2/13/2019 JAMES MCCARTHY
Address approval Cleared 2/25/2019 HOWARD COOPER
Address approval Cleared 2/25/2019 HOWARD COOPER
Hydrant and Access approval Cleared 2/25/2019 JOHN DALLAS
DAS Clearance Cleared 4/10/2019 DOUGLAS NAKATANI
Fire Marshall Fire Life Safety Cleared 4/18/2019 MENOA AGHAJANI
Low Impact Development Cleared 4/18/2019 ORVAL HERNANDEZ-MARCI
Driveway location Cleared 5/21/2019 ALBERT ISAGULIAN
Internal circulation Cleared 5/21/2019 ALBERT ISAGULIAN
Metro Rail approval Cleared 8/2/2019 DOUGLAS NAKATANI
Project located in CRA area Cleared 8/15/2019 JIM URQUHART
Roof/Waste drainage to street Cleared 8/23/2019 GUILLERMO PETRA
Permit Cleared 9/6/2019 JULIUS GARCIA
"D" conditions Cleared 9/9/2019 DIANA JIMENEZ
Frnt yard landscape/Water mgmt Cleared 9/9/2019 DIANA JIMENEZ
Miscellaneous Cleared 9/9/2019 DIANA JIMENEZ
Opn space landscape/Water mgmt Cleared 9/9/2019 DIANA JIMENEZ
Prkng lot landscape/Water mgmt Cleared 9/9/2019 DIANA JIMENEZ
ZI Cleared 9/9/2019 DIANA JIMENEZ
Historic monument Cleared 9/11/2019 MELISSA JONES
Building over 3-story or 36-ft Cleared 9/19/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 9/19/2019 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 9/24/2019 LEE GUILBEAUX

Contact Information

Architect Mccarthy,, Dion P; Lic. No.: C26044 DESIGNARC   10524 ILONA AVE.    LOS ANGELES, CA 90064
Contractor Staples Construction Company Inc; Lic. No.: 710039-B 1501 EASTMAN AVE      VENTURA, CA 93003
Engineer Michal,, Jerry Lee; Lic. No.: GE2515 2499 ROCK VIEW GLEN      ESCONDIDO, CA 92026
Engineer Slaybaugh, Ryan Matthew; Lic. No.: S5619 3270 KEOKUK CT      SAN DIEGO, CA 92117

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 10/24/2019 Approved JOHN KITCKO
Deputy Grading 10/25/2019 Conditional Approval RICKEY JACKSON
Deputy Grading 10/28/2019 Approved JOHN KITCKO
Deputy Grading 10/29/2019 Approved JOHN KITCKO
Deputy Grading 10/30/2019 Approved JOHN KITCKO
Deputy Grading 10/31/2019 Approved JOHN KITCKO
Deputy Grading 11/1/2019 Approved JOHN KITCKO
Deputy Grading 11/5/2019 Approved JOHN KITCKO
Deputy Grading 11/6/2019 Approved JOHN KITCKO
Deputy Grading 11/7/2019 Approved JOHN KITCKO
Deputy Grading 11/8/2019 Approved JOHN KITCKO
Deputy Grading 11/12/2019 Approved JOHN KITCKO
Deputy Grading 11/13/2019 Approved JOHN KITCKO
Deputy Grading 11/14/2019 Approved JOHN KITCKO
Deputy Grading 11/15/2019 Conditional Approval JOHN KITCKO
Deputy Grading 11/18/2019 Conditional Approval JOHN KITCKO
Deputy Grading 11/19/2019 Approved JOHN KITCKO
Deputy Grading 11/20/2019 Approved JOHN KITCKO
Deputy Grading 11/21/2019 Approved JOHN KITCKO
Deputy Grading 11/22/2019 Approved JOHN KITCKO
Deputy Grading 11/26/2019 Conditional Approval RICKEY JACKSON
Deputy Grading 11/27/2019 Conditional Approval ROBERT COLE
Deputy Grading 12/2/2019 Approved JOHN KITCKO
Deputy Grading 12/3/2019 Approved JOHN KITCKO
Deputy Grading 12/4/2019 Approved JOHN KITCKO
Deputy Grading 12/5/2019 Conditional Approval JAMES STEPHENS
Deputy Grading 12/6/2019 Approved JEFF BYTHEWAY
Deputy Grading 12/11/2019 Approved JOHN KITCKO
Deputy Grading 12/12/2019 Approved JOHN KITCKO
Deputy Grading 12/13/2019 Approved JOHN KITCKO
Deputy Grading 12/16/2019 Approved JOHN KITCKO
Deputy Grading 12/17/2019 Approved JOHN KITCKO
Deputy Grading 12/18/2019 Approved JOHN KITCKO
Deputy Grading 12/19/2019 Approved JOHN KITCKO
Deputy Grading 12/20/2019 Approved JOHN KITCKO
Deputy Grading 12/24/2019 Approved JOHN KITCKO
Deputy Grading 12/26/2019 Approved JOHN KITCKO
Deputy Grading 12/27/2019 Conditional Approval JOHN KITCKO
Deputy Grading 12/30/2019 Approved JOHN KITCKO
Deputy Grading 12/31/2019 Approved JOHN KITCKO
Deputy Grading 1/2/2020 Approved JOHN KITCKO
Deputy Grading 1/3/2020 Approved JOHN KITCKO
Deputy Grading 1/6/2020 Conditional Approval JOHN KITCKO
Deputy Grading 1/7/2020 Conditional Approval JOHN KITCKO
Deputy Grading 1/8/2020 Conditional Approval JOHN KITCKO
Deputy Grading 1/9/2020 Approved JOHN KITCKO
Deputy Grading 1/10/2020 Conditional Approval JAMES STEPHENS
Deputy Grading 1/13/2020 Conditional Approval JOHN KITCKO
Deputy Grading 1/14/2020 Conditional Approval JOHN KITCKO
Deputy Grading 1/15/2020 Approved JOHN KITCKO
Deputy Grading 1/16/2020 Approved JOHN KITCKO
Deputy Grading 1/17/2020 Approved JOHN KITCKO
Deputy Grading 1/21/2020 Approved JOHN KITCKO
Deputy Grading 1/22/2020 Approved JOHN KITCKO
Deputy Grading 1/23/2020 Approved JOHN KITCKO
Deputy Grading 1/24/2020 Approved JOHN KITCKO
Deputy Grading 1/27/2020 Approved JOHN KITCKO
Deputy Grading 1/28/2020 Approved JOHN KITCKO
Deputy Grading 1/29/2020 Approved JOHN KITCKO
Deputy Grading 1/30/2020 Approved JOHN KITCKO
Deputy Grading 1/31/2020 Approved JOHN KITCKO
Deputy Grading 2/3/2020 Approved JOHN KITCKO
Deputy Grading 2/4/2020 Approved JOHN KITCKO
Deputy Grading 2/5/2020 Approved JOHN KITCKO
Deputy Grading 2/6/2020 Approved JOHN KITCKO
Deputy Grading 2/7/2020 Approved JOHN KITCKO
Deputy Grading 2/10/2020 Approved JOHN KITCKO
Deputy Grading 2/11/2020 Approved JOHN KITCKO
Deputy Grading 2/12/2020 Approved JOHN KITCKO
Deputy Grading 2/13/2020 Approved JOHN KITCKO
Deputy Grading 2/14/2020 Approved JOHN KITCKO
Deputy Grading 2/18/2020 Approved JOHN KITCKO
Deputy Grading 2/19/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/19/2020 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 2/19/2020 Partial Inspection JOHN KITCKO
Piling/Pier/Caisson 2/19/2020 Partial Inspection JOHN KITCKO
Pre-Inspection 2/19/2020 Partial Inspection JOHN KITCKO
Deputy Grading 2/20/2020 Approved JOHN KITCKO
Deputy Grading 2/21/2020 Approved JOHN KITCKO
Deputy Grading 2/25/2020 Approved JOHN KITCKO
Deputy Grading 2/26/2020 Approved JOHN KITCKO
Deputy Grading 2/27/2020 Approved JOHN KITCKO
Deputy Grading 2/28/2020 Approved JOHN KITCKO
Deputy Grading 3/2/2020 Conditional Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/5/2020 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 3/5/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 3/6/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 3/11/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 3/11/2020 Corrections Issued JOHN KITCKO
Deputy Grading 3/12/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 3/12/2020 Approved JOHN KITCKO
Deputy Grading 3/13/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 3/13/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 3/17/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 3/18/2020 Approved JOHN KITCKO
Deputy Shotcrete 3/18/2020 Approved JOHN KITCKO
Deputy Shotcrete 3/19/2020 Approved JOHN KITCKO
Deputy Shotcrete 3/20/2020 Approved JOHN KITCKO
Deputy Shotcrete 3/23/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/23/2020 Conditional Approval JOHN KITCKO
Deputy Grading 3/24/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 3/24/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 3/25/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/25/2020 Partial Approval DANNY RODRIGUEZ
Deputy Shotcrete 3/26/2020 Approved JOHN KITCKO
Deputy Shotcrete 3/27/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/27/2020 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 3/27/2020 Partial Approval JOHN KITCKO
Deputy Grading 3/31/2020 Approved JOHN KITCKO
Deputy Shotcrete 3/31/2020 Approved JOHN KITCKO
Deputy Grading 4/1/2020 Approved JOHN KITCKO
Deputy Shotcrete 4/1/2020 Approved JOHN KITCKO
Deputy Grading 4/2/2020 Approved JOHN KITCKO
Deputy Shotcrete 4/2/2020 Approved JOHN KITCKO
Piling/Pier/Caisson 4/2/2020 Partial Approval JOHN KITCKO
Deputy Grading 4/3/2020 Approved JOHN KITCKO
Deputy Shotcrete 4/3/2020 Approved JOHN KITCKO
Deputy Shotcrete 4/7/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 4/7/2020 Corrections Issued JOHN KITCKO
Deputy Shotcrete 4/8/2020 Approved JOHN KITCKO
Deputy Shotcrete 4/9/2020 Approved JOHN KITCKO
Deputy Shotcrete 4/10/2020 Approved JOHN KITCKO
Pre-Inspection 4/10/2020 Partial Approval JOHN KITCKO
Deputy Shotcrete 4/13/2020 Approved JOHN KITCKO
Deputy Shotcrete 4/14/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 4/14/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 4/15/2020 Approved JOHN KITCKO
Deputy Shotcrete 4/15/2020 Approved JOHN KITCKO
Pre-Inspection 4/15/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 4/16/2020 Approved JOHN KITCKO
Deputy Shotcrete 4/16/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 4/17/2020 Approved JOHN KITCKO
Deputy Shotcrete 4/17/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 4/20/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 4/22/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 4/23/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 4/23/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 4/24/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 4/24/2020 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 4/28/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 4/30/2020 Approved JOHN KITCKO
Deputy Grading 5/4/2020 Approved JOHN KITCKO
Deputy Grading 5/5/2020 Approved JOHN KITCKO
Deputy Drilled-In Anchors 5/7/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 5/8/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 5/8/2020 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 5/15/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 5/19/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 5/21/2020 Approved JOHN KITCKO
Deputy Reinf. Masonry 5/21/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 5/22/2020 Approved JOHN KITCKO
Deputy Reinf. Masonry 5/22/2020 Approved JOHN KITCKO
Green Building Rough 5/22/2020 Not Ready for Inspection JOHN KITCKO
Reinforced Masonry Frame 5/22/2020 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 5/22/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 5/26/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/27/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 5/28/2020 Approved JOHN KITCKO
Deputy Drilled-In Anchors 5/29/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 6/1/2020 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 6/1/2020 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 6/2/2020 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 6/2/2020 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 6/3/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 6/4/2020 Approved JOHN KITCKO
Deputy Reinf. Masonry 6/4/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/4/2020 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 6/5/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 6/8/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 6/8/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 6/10/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 6/11/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 6/11/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 6/12/2020 Approved HAMID PISHEHVAR
Excavation/Setback/Form/Re-Bar 6/15/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 6/16/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/17/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 6/17/2020 Corrections Issued JOHN KITCKO
Pre-Inspection 6/17/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 6/18/2020 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 6/19/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 6/19/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 6/23/2020 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 6/24/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 6/25/2020 Approved JOHN KITCKO
Deputy Shotcrete 6/25/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 6/26/2020 Approved JOHN KITCKO
Deputy Shotcrete 6/26/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 6/26/2020 Partial Approval JOHN KITCKO
Deputy Shotcrete 6/29/2020 Approved JOHN KITCKO
Deputy Shotcrete 6/30/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/30/2020 Partial Approval JOHN KITCKO
Deputy Shotcrete 7/1/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 7/1/2020 Not Ready for Inspection JOHN KITCKO
Deputy Shotcrete 7/2/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 7/2/2020 Partial Approval JOHN KITCKO
Deputy Shotcrete 7/6/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 7/6/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 7/7/2020 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 7/7/2020 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 7/7/2020 No Access for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 7/8/2020 Approved JOHN KITCKO
Deputy Shotcrete 7/8/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 7/8/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 7/9/2020 Approved JOHN KITCKO
Deputy Shotcrete 7/9/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 7/10/2020 Approved JOHN KITCKO
Deputy Shotcrete 7/10/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 7/10/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 7/13/2020 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 7/14/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 7/14/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 7/15/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 7/16/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 7/16/2020 Partial Approval JOHN KITCKO
Deputy Grading 7/20/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 7/20/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 7/20/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 7/22/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 7/23/2020 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 7/31/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 8/3/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 8/4/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/5/2020 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 8/6/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 8/7/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 8/10/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 8/11/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 8/12/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 8/14/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 8/17/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 8/18/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 8/19/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 8/19/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 8/20/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 8/20/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 8/21/2020 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 8/21/2020 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 8/22/2020 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 8/24/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 8/27/2020 Approved HAMID PISHEHVAR
Excavation/Setback/Form/Re-Bar 8/28/2020 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 8/31/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 8/31/2020 Partial Inspection JOHN KITCKO
Deputy Reinf. Concrete 9/1/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 9/2/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 9/3/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 9/3/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 9/4/2020 Approved JOHN KITCKO
Deputy Shotcrete 9/4/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 9/4/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 9/8/2020 Approved JOHN KITCKO
Green Building Rough 9/8/2020 Partial Approval JOHN KITCKO
Reinforced Concrete Frame 9/8/2020 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 9/8/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 9/9/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 9/10/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 9/11/2020 Conditional Approval RICKEY JACKSON
Excavation/Setback/Form/Re-Bar 9/11/2020 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 9/14/2020 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 9/14/2020 Corrections Issued JOHN KITCKO
Deputy Reinf. Concrete 9/15/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 9/16/2020 Approved JOHN KITCKO
Deputy Shotcrete 9/16/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 9/18/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 9/21/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 9/22/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 9/22/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 9/28/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 10/1/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 10/2/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 10/5/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 10/6/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 10/7/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 10/9/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 10/13/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 10/14/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 10/15/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 10/15/2020 Partial Inspection JOHN KITCKO
Deputy Reinf. Concrete 10/16/2020 Partial Approval JOHN KITCKO
Drywall Nailing 10/16/2020 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 10/19/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 10/22/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 10/23/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 10/23/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 10/26/2020 Approved JOHN KITCKO
Deputy Shotcrete 10/26/2020 Approved JOHN KITCKO
Deputy Shotcrete 10/27/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 10/27/2020 Partial Approval JOHN KITCKO
Insulation 10/27/2020 Not Ready for Inspection JOHN KITCKO
Deputy Shotcrete 10/28/2020 Approved JOHN KITCKO
Deputy Shotcrete 10/29/2020 Approved JOHN KITCKO
Deputy Shotcrete 10/30/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 10/30/2020 Partial Approval JOHN KITCKO
Light Gage Steel Frame 11/2/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 11/4/2020 Approved JOHN KITCKO
Deputy Shotcrete 11/4/2020 Approved JOHN KITCKO
Drywall Nailing 11/4/2020 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 11/5/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 11/6/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 11/10/2020 Partial Approval JOHN KITCKO
Reinforced Concrete Frame 11/12/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 11/13/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 11/13/2020 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 11/16/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 11/17/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/2/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/3/2020 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 12/4/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 12/4/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 12/7/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/8/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/9/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/10/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/11/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/14/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/15/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/17/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/21/2020 Approved JOHN KITCKO
Deputy Drilled-In Anchors 12/24/2020 Approved JOHN KITCKO
Deputy Drilled-In Anchors 12/28/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/28/2020 Approved JOHN KITCKO
Footing/Foundation/Slab 12/28/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 12/29/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/30/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/31/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 1/4/2021 Approved JOHN KITCKO
Footing/Foundation/Slab 1/4/2021 Partial Inspection JOHN KITCKO
Deputy Reinf. Concrete 1/5/2021 Approved JOHN KITCKO
Wood Frame 1/5/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 1/6/2021 Approved JOHN KITCKO
Deputy Steel/Welding 1/11/2021 Approved HAMID PISHEHVAR
Deputy Steel/Welding 1/12/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 1/13/2021 Approved JOHN KITCKO
Deputy Steel/Welding 1/13/2021 Approved JOHN KITCKO
Deputy Reinf. Masonry 1/14/2021 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 1/14/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 1/15/2021 Approved JOHN KITCKO
Deputy Steel/Welding 1/15/2021 Approved JOHN KITCKO
Deputy Drilled-In Anchors 1/20/2021 Approved JOHN KITCKO
Deputy Reinf. Masonry 1/20/2021 Approved JOHN KITCKO
Deputy Steel/Welding 1/20/2021 Approved JOHN KITCKO
Masonry Wall/Backfill 1/20/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 1/21/2021 Approved JOHN KITCKO
Deputy Reinf. Masonry 1/21/2021 Approved JOHN KITCKO
Deputy Steel/Welding 1/21/2021 Approved JOHN KITCKO
Deputy Drilled-In Anchors 1/22/2021 Approved JOHN KITCKO
Deputy Reinf. Masonry 1/22/2021 Approved JOHN KITCKO
Deputy Reinf. Masonry 1/26/2021 Approved JOHN KITCKO
Deputy Reinf. Masonry 1/29/2021 Approved JOHN KITCKO
Light Gage Steel Frame 1/29/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 2/2/2021 Approved JOHN KITCKO
Deputy Steel/Welding 2/2/2021 Approved JOHN KITCKO
Masonry Wall/Backfill 2/2/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 2/3/2021 Approved JOHN KITCKO
Deputy Steel/Welding 2/3/2021 Approved JOHN KITCKO
Light Gage Steel Frame 2/3/2021 Partial Approval JOHN KITCKO
Masonry Wall/Backfill 2/3/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 2/4/2021 Approved JOHN KITCKO
Light Gage Steel Frame 2/5/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 2/8/2021 Approved JOHN KITCKO
Masonry Wall/Backfill 2/9/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 2/10/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 2/12/2021 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 2/17/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 2/18/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 2/18/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 2/22/2021 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/25/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 2/26/2021 Approved JOHN KITCKO
Deputy Reinf. Masonry 2/26/2021 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/26/2021 Partial Approval JOHN KITCKO
Drywall Nailing 3/2/2021 Partial Approval JOHN KITCKO
Drywall Nailing 3/4/2021 Partial Approval JOHN KITCKO
Green Building Rough 3/4/2021 Not Ready for Inspection JOHN KITCKO
Reinforced Masonry Frame 3/4/2021 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 3/4/2021 Approved JOHN KITCKO
Deputy Reinf. Concrete 3/5/2021 Approved JOHN KITCKO
Deputy Reinf. Masonry 3/5/2021 Approved JOHN KITCKO
Drywall Nailing 3/5/2021 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/5/2021 Partial Approval JOHN KITCKO
Deputy Shotcrete 3/8/2021 Conditional Approval JOHN KITCKO
Deputy Wood Construction 3/10/2021 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/11/2021 Partial Approval JOHN KITCKO
Masonry Wall/Backfill 3/11/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 3/12/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Not Ready for Inspection JOHN KITCKO
Deputy Wood Construction 3/15/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Not Ready for Inspection JOHN KITCKO
Deputy Wood Construction 3/17/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 3/17/2021 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/18/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 3/18/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 3/19/2021 Approved JOHN KITCKO
Deputy Reinf. Masonry 3/19/2021 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/19/2021 Partial Approval JOHN KITCKO
Drywall Nailing 3/24/2021 Partial Approval JOHN KITCKO
Masonry Wall/Backfill 3/24/2021 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/26/2021 Partial Approval JOHN KITCKO
Drywall Nailing 3/30/2021 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/30/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 4/1/2021 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 4/6/2021 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 4/6/2021 Corrections Issued JOHN KITCKO
Drywall Nailing 4/7/2021 Partial Approval HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 4/7/2021 Approved HAMID PISHEHVAR
Deputy Wood Construction 4/8/2021 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 4/8/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 4/9/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Wood Construction 4/13/2021 Approved JOHN KITCKO
Drywall Nailing 4/14/2021 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 4/14/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 4/15/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 4/16/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 4/19/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 4/20/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 4/21/2021 Approved JOHN KITCKO
Footing/Foundation/Slab 4/21/2021 Not Ready for Inspection JOHN KITCKO
Deputy Wood Construction 4/22/2021 Approved HAMID PISHEHVAR
Excavation/Setback/Form/Re-Bar 4/22/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 4/22/2021 Partial Approval JOHN KITCKO
Light Gage Steel Frame 4/23/2021 Partial Approval JOHN KITCKO
Drywall Nailing 4/27/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 4/29/2021 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 4/29/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 4/29/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 5/3/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 5/5/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/7/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 5/10/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 5/19/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/20/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 5/21/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Partial Approval JOHN KITCKO
Insulation 5/28/2021 Partial Approval JOHN KITCKO
Deputy Steel/Welding 6/1/2021 Approved JOHN KITCKO
Insulation 6/1/2021 Partial Approval JOHN KITCKO
Deputy Steel/Welding 6/2/2021 Approved JOHN KITCKO
Deputy Wood Construction 6/3/2021 Conditional Approval CAMERON CHABAN
Deputy Drilled-In Anchors 6/4/2021 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 6/4/2021 Partial Approval SORIN CIRSTOIU
Deputy Wood Construction 6/8/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/8/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Partial Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/10/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 6/14/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/14/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/15/2021 Corrections Issued JOHN KITCKO
Deputy Wood Construction 6/16/2021 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2021 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 6/18/2021 No Access for Inspection JOHN KITCKO
Deputy Wood Construction 6/21/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/21/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/22/2021 Partial Approval JOHN KITCKO
Drywall Nailing 6/24/2021 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 6/24/2021 Partial Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/25/2021 Partial Approval CAMERON CHABAN
Deputy Drilled-In Anchors 6/28/2021 Approved JOHN KITCKO
Deputy Reinf. Concrete 6/28/2021 Approved JOHN KITCKO
Deputy Wood Construction 6/28/2021 Approved JOHN KITCKO
Insulation 6/28/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 6/29/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 7/1/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/1/2021 Partial Approval JOHN KITCKO
Wood Frame 7/2/2021 Partial Inspection JOHN KITCKO
Insulation 7/6/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 7/7/2021 Approved JOHN KITCKO
Deputy Steel/Welding 7/7/2021 Approved JOHN KITCKO
Deputy Wood Construction 7/7/2021 Approved JOHN KITCKO
Wood Frame 7/7/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/9/2021 Conditional Approval KENNETH ROBERTS
Deputy Wood Construction 7/9/2021 Conditional Approval KENNETH ROBERTS
Wood Frame 7/13/2021 Partial Approval JOE VELASQUEZ
Deputy Wood Construction 7/14/2021 Conditional Approval DANIEL VARNUM
Wood Frame 7/14/2021 Partial Approval DANIEL VARNUM
Deputy Steel/Welding 7/15/2021 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Partial Approval SORIN CIRSTOIU
Insulation 7/16/2021 Partial Approval ROBERT DAVIS
Wood Frame 7/19/2021 Partial Approval ROBERT DAVIS
Deputy Steel/Welding 7/20/2021 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Partial Approval DANIEL VARNUM
Insulation 7/20/2021 Partial Approval DANIEL VARNUM
Deputy Steel/Welding 7/21/2021 Conditional Approval JEFFREY DURAN
Wood Frame 7/21/2021 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Partial Approval CAMERON CHABAN
Insulation 7/22/2021 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 7/23/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/26/2021 Partial Approval JOHN KITCKO
Insulation 7/27/2021 Partial Approval JOHN KITCKO
Wood Frame 7/27/2021 Partial Approval JOHN KITCKO
Insulation 7/28/2021 Partial Inspection JOHN KITCKO
Deputy Wood Construction 7/29/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/30/2021 Partial Approval JOHN KITCKO
Insulation 8/2/2021 Partial Approval JOHN KITCKO
Deputy Steel/Welding 8/3/2021 Conditional Approval JOHN KITCKO
Insulation 8/3/2021 Partial Approval JOHN KITCKO
Wood Frame 8/4/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 8/6/2021 Conditional Approval JEFFREY DURAN
Insulation 8/6/2021 Partial Approval JOHN KITCKO
Wood Frame 8/9/2021 Partial Approval DANIEL VARNUM
Insulation 8/10/2021 Not Ready for Inspection JOHN KITCKO
Wood Frame 8/10/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 8/12/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 8/12/2021 Partial Approval JOHN KITCKO
Insulation 8/13/2021 Partial Approval JOHN KITCKO
Deputy Steel/Welding 8/17/2021 Approved JOHN KITCKO
Insulation 8/17/2021 Partial Approval JOHN KITCKO
Deputy Drilled-In Anchors 8/18/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 8/20/2021 Partial Approval JOHN KITCKO
Drywall Nailing 8/24/2021 Partial Approval JOHN KITCKO
Drywall Nailing 8/25/2021 Partial Approval JOHN KITCKO
Insulation 8/26/2021 Partial Approval JOHN KITCKO
Insulation 8/27/2021 Partial Approval JOHN KITCKO
Drywall Nailing 8/30/2021 Partial Approval JOHN KITCKO
Insulation 8/31/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Partial Approval JOHN KITCKO
Insulation 9/3/2021 Partial Approval JOHN KITCKO
Drywall Nailing 9/9/2021 Partial Approval JOHN KITCKO
Insulation 9/9/2021 Partial Approval JOHN KITCKO
Drywall Nailing 9/10/2021 Partial Approval JOHN KITCKO
Insulation 9/10/2021 Partial Inspection JOHN KITCKO
Wood Frame 9/17/2021 Partial Inspection JOHN KITCKO
Wood Frame 9/21/2021 Conditional Approval JOHN KITCKO
Insulation 9/24/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 9/30/2021 Approved JOHN KITCKO
Deputy Wood Construction 10/1/2021 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Partial Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Partial Approval JOHN KITCKO
Wood Frame 10/8/2021 Partial Approval JOHN KITCKO
Wood Frame 10/12/2021 Partial Approval JOHN KITCKO
Wood Frame 10/14/2021 Partial Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Partial Approval JOHN KITCKO
Green Building Rough 10/19/2021 Partial Approval JOHN KITCKO
Insulation 10/19/2021 Partial Approval JOHN KITCKO
Insulation 10/20/2021 Not Ready for Inspection JOHN KITCKO
Insulation 10/21/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 10/27/2021 Conditional Approval JEFFREY DURAN
Light Gage Steel Frame 10/27/2021 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Partial Approval JOHN KITCKO
Wood Frame 10/28/2021 Partial Approval JOHN KITCKO
Insulation 11/1/2021 Partial Approval DANNY RODRIGUEZ
Insulation 11/2/2021 Not Ready for Inspection JOHN KITCKO
Insulation 11/3/2021 Partial Approval JOHN KITCKO
Insulation 11/4/2021 Partial Approval DANIEL VARNUM
Deputy Steel/Welding 11/5/2021 No Access for Inspection JOE VELASQUEZ
Wood Frame 11/5/2021 Partial Approval JOE VELASQUEZ
Insulation 11/8/2021 Not Ready for Inspection JOE VELASQUEZ
Insulation 11/9/2021 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 11/15/2021 Approved JOHN KITCKO
Wood Frame 11/15/2021 Partial Approval JOHN KITCKO
Insulation 11/17/2021 Partial Inspection JOHN KITCKO
Insulation 11/18/2021 Partial Approval JOHN KITCKO
Light Gage Steel Frame 11/18/2021 Partial Approval JOHN KITCKO
Wood Frame 11/23/2021 Partial Approval JOHN KITCKO
Insulation 11/29/2021 Partial Approval JOHN KITCKO
Insulation 12/1/2021 Partial Approval JOHN KITCKO
Wood Frame 12/1/2021 Not Ready for Inspection JOHN KITCKO
Light Gage Steel Frame 12/7/2021 Not Ready for Inspection JOHN KITCKO
Wood Frame 12/8/2021 Partial Approval JOHN KITCKO
Insulation 12/10/2021 Partial Approval JOHN KITCKO
Insulation 12/15/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 12/16/2021 Approved JOHN KITCKO
Deputy Reinf. Masonry 12/16/2021 Approved JOHN KITCKO
Light Gage Steel Frame 12/16/2021 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 12/20/2021 Partial Approval JOHN KITCKO
Wood Frame 12/21/2021 Partial Approval JOHN KITCKO
Insulation 12/22/2021 Partial Inspection JOHN KITCKO
Insulation 12/27/2021 Not Ready for Inspection JOHN KITCKO
Insulation 12/29/2021 Partial Approval JOHN KITCKO
Light Gage Steel Frame 1/4/2022 Partial Approval JOHN KITCKO
Drywall Nailing 1/5/2022 Partial Inspection JOHN KITCKO
Light Gage Steel Frame 1/6/2022 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 1/12/2022 Corrections Issued JOHN KITCKO
Insulation 1/14/2022 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 1/19/2022 Partial Approval JOHN KITCKO
Light Gage Steel Frame 1/31/2022 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 2/3/2022 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 2/4/2022 Partial Approval JOHN KITCKO
Light Gage Steel Frame 2/10/2022 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 2/16/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 2/17/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 2/17/2022 Conditional Approval JOHN KITCKO
Interior/Exterior Lathing 2/18/2022 Corrections Issued JOHN KITCKO
Interior/Exterior Lathing 2/19/2022 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 2/19/2022 Off-Hour Fees Due
Interior/Exterior Lathing 2/23/2022 Partial Inspection ANDREW DORSO
Drywall Nailing 2/25/2022 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 3/3/2022 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 3/22/2022 Partial Approval JOHN KITCKO
Drywall Nailing 4/29/2022 Partial Inspection JOHN KITCKO
Drywall Nailing 7/8/2022 Partial Inspection JOHN KITCKO
Drywall Nailing 7/29/2022 Partial Inspection JOHN KITCKO
Pre-Inspection 9/1/2022 Not Ready for Inspection DANIEL VARNUM
T-Bar Ceiling 9/30/2022 Partial Inspection JOHN KITCKO
Special/Order Compliance 10/13/2022 Partial Inspection JOHN KITCKO
Final 10/31/2022 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 10/31/2022 Approved JOHN KITCKO
Green Building Final 10/31/2022 Not Ready for Inspection JOHN KITCKO
Green Building Rough 10/31/2022 Approved JOHN KITCKO
Reinforced Concrete Frame 10/31/2022 Approved JOHN KITCKO
Reinforced Masonry Frame 10/31/2022 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 10/31/2022 Approved JOHN KITCKO
Final 11/3/2022 Partial Inspection JOHN KITCKO
Green Building Final 11/3/2022 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Approved JOHN KITCKO
Pre-Inspection 11/4/2022 Partial Inspection JOHN KITCKO
Pre-Inspection 11/7/2022 Partial Inspection JOHN KITCKO
Special/Order Compliance 11/7/2022 Partial Inspection JOHN KITCKO
Special/Order Compliance 5/17/2023 Partial Inspection JOHN KITCKO
Final 8/30/2023 OK to Issue CofO JOHN KITCKO
Green Building Final 8/30/2023 Approved JOHN KITCKO