11900 N MASON AVE 91326

Certificate Information: 11900 N MASON AVE 91326

Application / Permit
17010-20000-03818
Plan Check / Job No.
B17VN15015
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Storage Building
Work Description
(N) 1-STORY PAVILION BUILDING W/ ATTACHED COVERED STAGE ACCESSORY TO PARK & RECREATION FACILITIES (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 2/17/2022
Issuing Office
Current Status
CofO Issued on 10/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2017 APPLICANT
Assigned to Plan Check Engineer 10/26/2017 RODNEY SAMIIAN
Disabled Access Plans Picked Up 10/30/2017 APPLICANT
Corrections Issued 11/3/2017 RODNEY SAMIIAN
Quality Review Completed 11/6/2017 ABDUL CHEGENI
Building Plans Picked Up 11/9/2017 APPLICANT
Green Plans Picked Up 11/9/2017 APPLICANT
Applicant returned to address corrections 10/1/2018 RODNEY SAMIIAN
Applicant returned to address corrections 10/18/2018 RODNEY SAMIIAN
Applicant returned to address corrections 11/8/2018 RODNEY SAMIIAN
Applicant returned to address corrections 12/10/2018 RODNEY SAMIIAN
Applicant returned to address corrections 6/13/2019 RODNEY SAMIIAN
Applicant returned to address corrections 8/8/2019 RODNEY SAMIIAN
Applicant returned to address corrections 1/6/2020 RODNEY SAMIIAN
Applicant returned to address corrections 6/17/2020 RODNEY SAMIIAN
Applicant returned to address corrections 7/6/2020 RODNEY SAMIIAN
Applicant returned to address corrections 1/27/2022 NILOOFAR MEHRAIN
Plan Check Approved 2/3/2022 NILOOFAR MEHRAIN
Issued 2/17/2022 APPLICANT
CofO in Progress 10/22/2024 GREGORY POMISH
Permit Finaled 10/30/2024 RICKEY JACKSON
CofO Issued 10/30/2024 RICKEY JACKSON
Permit Finaled 10/30/2024 RICKEY JACKSON

Permit Application Clearance Information

"T" removal Cleared 10/16/2018 ANNA VIDAL
Miscellaneous Cleared 10/16/2018 ANNA VIDAL
Miscellaneous Cleared 10/16/2018 ANNA VIDAL
Miscellaneous Cleared 10/16/2018 ANNA VIDAL
Miscellaneous Cleared 10/16/2018 ANNA VIDAL
Specific Plan Cleared 10/16/2018 ANNA VIDAL
Tract Map conditions Cleared 10/16/2018 ANNA VIDAL
ZA Case Cleared 10/16/2018 ANNA VIDAL
ZA Case Cleared 10/16/2018 ANNA VIDAL
Hydrant and Access approval Cleared 11/6/2018 JOHN DALLAS
Address approval Cleared 12/10/2018 HOWARD COOPER
Specific Plan Cleared 12/18/2018 ALBERT ISAGULIAN
Fire Marshall Fire Life Safety Cleared 6/12/2019 MENOA AGHAJANI
DAS Clearance Cleared 6/20/2019 OLLIE CARTER
Eng Process Fee Ord 176,300 Cleared 6/25/2019 ROBYN STEELE
Green Code Cleared 7/3/2019 DAVID MATSON
Low Impact Development Cleared 7/18/2019 ORVAL HERNANDEZ-MARCI
Highway dedication Cleared 12/4/2019 LEE GUILBEAUX
Permit Cleared 12/4/2019 LEE GUILBEAUX
Sewer availability Cleared 12/17/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 4/21/2020 LEE GUILBEAUX
GPI Written Notices Cleared 7/6/2020 ABDUL CHEGENI
Grading Pre-Inspection Cleared 7/6/2020 ABDUL CHEGENI

Contact Information

Architect Kalban, Jeffrey Michael; Lic. No.: C11124 10585 SANTA MONICA BLVD STE 160      LOS ANGELES, CA 90025
Contractor Oakridge Landscape Inc; Lic. No.: 798565-B 28064 AVENUE STANFORD UNIT K      VALENCIA, CA 91355
Engineer Wong, Ramon Roman Ii; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/1/2022 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Grading Pre-Inspection 5/5/2022 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/31/2022 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 6/3/2022 Partial Inspection JEFFREY FULTON
METHANE-Barrier 6/3/2022 Approved JEFFREY FULTON
METHANE-Subgrade 6/3/2022 Approved JEFFREY FULTON
Deputy Reinf. Masonry 6/27/2022 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 6/28/2022 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 6/30/2022 Conditional Approval JEFFREY FULTON
Reinforced Concrete Frame 7/1/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 7/5/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/7/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/8/2022 Conditional Approval JEFFREY DURAN
Reinforced Concrete Frame 7/8/2022 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 7/11/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/11/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/11/2022 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 7/12/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/12/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/13/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/13/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/14/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/14/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/15/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/15/2022 Conditional Approval JEFFREY DURAN
Green Building Rough 7/18/2022 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 7/18/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 7/18/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/18/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 7/21/2022 Not Ready for Inspection JEFFREY FULTON
METHANE-Rough 7/21/2022 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 7/21/2022 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 7/21/2022 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 7/26/2022 Partial Inspection JEFFREY FULTON
Green Building Rough 8/5/2022 Not Ready for Inspection JEFFREY FULTON
METHANE-Rough 8/5/2022 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 8/5/2022 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/5/2022 Not Ready for Inspection JEFFREY FULTON
Wall Anchors 8/8/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 8/9/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 8/10/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 8/11/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/12/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/15/2022 Conditional Approval JOHN KITCKO
Green Building Rough 8/16/2022 No Access for Inspection EDWIN GREGORYONA
METHANE-Rough 8/16/2022 No Access for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 8/16/2022 No Access for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 8/16/2022 No Access for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Partial Approval JOHN KITCKO
Green Building Rough 8/18/2022 Not Ready for Inspection JOHN KITCKO
METHANE-Rough 8/18/2022 Not Ready for Inspection JOHN KITCKO
Reinforced Masonry Frame 8/18/2022 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 8/18/2022 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 8/22/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 8/22/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 8/23/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/23/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/24/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 8/24/2022 Approved DANNY RODRIGUEZ
Green Building Rough 8/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 8/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 8/24/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 8/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/25/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 8/25/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/26/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/26/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/30/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 8/31/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/1/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 9/1/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/2/2022 No Access for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 9/2/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/7/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/8/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/9/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/12/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 9/13/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/14/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 9/15/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 9/16/2022 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/29/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/29/2022 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 9/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 10/7/2022 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 10/12/2022 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 10/18/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/3/2022 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 11/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 11/4/2022 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 11/17/2022 Corrections Issued DANNY RODRIGUEZ
Reinforced Concrete Frame 11/18/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 11/22/2022 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/13/2022 No Access for Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 12/14/2022 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 12/19/2022 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 12/19/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/19/2022 Partial Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/19/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 12/29/2022 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 12/29/2022 Partial Inspection JEFFREY FULTON
METHANE-Rough 12/29/2022 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 12/29/2022 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/29/2022 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 1/5/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 1/5/2023 Partial Inspection STEVEN LEVITT
Insulation 1/11/2023 Corrections Issued JEFFREY FULTON
Drywall Nailing 1/13/2023 Partial Inspection JEFFREY FULTON
Insulation 1/13/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/17/2023 Approved JEFFREY FULTON
Green Building Rough 1/17/2023 Approved JEFFREY FULTON
Deputy Reinf. Concrete 1/19/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 1/23/2023 Conditional Approval JEFFREY FULTON
Deputy Drilled-In Anchors 1/24/2023 Conditional Approval JEFFREY FULTON
Reinforced Concrete Frame 1/25/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 1/31/2023 Conditional Approval JEFFREY FULTON
METHANE-Rough 2/2/2023 Approved JEFFREY FULTON
Reinforced Masonry Frame 2/2/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 2/2/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 2/17/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 3/20/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 4/6/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 4/12/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 4/18/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 4/20/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/25/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 6/2/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 6/27/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 7/26/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 9/13/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 9/14/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/18/2023 Conditional Approval DANNY RODRIGUEZ
T-Bar Ceiling 11/3/2023 Partial Inspection JEFFREY FULTON
Final 3/4/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 3/4/2024 Approved GREGORY POMISH
Green Building Final 3/4/2024 Approved GREGORY POMISH
Reinforced Masonry Frame 3/4/2024 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV No Gas GREGORY POMISH
Smoke Detectors 3/4/2024 Approved GREGORY POMISH
Structural Steel Frame 3/4/2024 Approved GREGORY POMISH
Verify Sprinkler Sign Off 3/4/2024 Approved GREGORY POMISH
Wood Frame 3/4/2024 Approved GREGORY POMISH
Final 10/22/2024 OK to Issue CofO GREGORY POMISH