12007 N SUSAN DR 91344

Certificate Information: 12007 N SUSAN DR 91344

Application / Permit
17010-20000-03736
Plan Check / Job No.
B17VN14660
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT PER AB 2299 AND SB 1069 ( 41'-8"x36'-7")
Permit Issued
Issued on 3/19/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2017 APPLICANT
Assigned to Plan Check Engineer 10/5/2017 SARAH YOUSSEF
Corrections Issued 10/10/2017 SARAH YOUSSEF
Quality Review Completed 10/10/2017 GUANG MIN TUNG
Building Plans Picked Up 10/10/2017 APPLICANT
Green Plans Picked Up 10/10/2017 APPLICANT
Plan Check Approved 3/16/2020 MOHAMMAD ESMAILI
Issued 3/19/2020 LADBS
CofO in Progress 3/4/2021 MARK JOHNSON
Permit Finaled 4/29/2021 MICHAEL SMITH
CofO Issued 4/29/2021 MICHAEL SMITH
Permit Finaled 4/29/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/18/2017 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/18/2017 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/18/2017 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/18/2017 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/18/2017 LEE GUILBEAUX
Hydrant and Access approval Cleared 12/18/2017 JOHN DALLAS
Sewer availability Cleared 12/18/2017 LEE GUILBEAUX
Green Code Cleared 1/29/2020 DAVID MATSON
Low Impact Development Cleared 2/13/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/13/2020 THOMAS LANG
GPI Written Notices Cleared 3/13/2020 SARAH YOUSSEF
Grading Pre-Inspection Cleared 3/13/2020 SARAH YOUSSEF

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/11/2020 Partial Approval MARK JOHNSON
Sewer 5/11/2020 Approved MARK JOHNSON
Excavation/Setback/Form/Re-Bar 6/5/2020 Approved MARK JOHNSON
Excavation/Setback/Form/Re-Bar 6/9/2020 Approved MARK JOHNSON
Deputy Reinf. Concrete 6/15/2020 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 7/27/2020 Corrections Issued MICHAEL TEMPLE
Green Building Rough 7/27/2020 Not Ready for Inspection MICHAEL TEMPLE
Verify Sprinkler Sign Off 7/27/2020 Not Ready for Inspection MICHAEL TEMPLE
Deputy Wood Construction 7/30/2020 No Access for Inspection MARK JOHNSON
BUILDING-Rough-Frame 8/13/2020 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 8/13/2020 Not Ready for Inspection MARK JOHNSON
Green Building Rough 8/13/2020 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 8/13/2020 Corrections Issued MARK JOHNSON
PLUMBING-Rough 8/13/2020 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 8/21/2020 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 8/21/2020 Approved MICHAEL TEMPLE
Green Building Rough 8/21/2020 No Access for Inspection MICHAEL TEMPLE
HVAC-Rough 8/21/2020 Approved MICHAEL TEMPLE
PLUMBING-Rough 8/21/2020 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 9/3/2020 Partial Approval MARK JOHNSON
Interior/Exterior Lathing 9/3/2020 Approved MARK JOHNSON
Insulation 9/10/2020 Approved DAVID SCANTLIN
Drywall Nailing 9/22/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 9/30/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 10/6/2020 Approved MARK JOHNSON
Shower Pan 10/6/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 12/17/2020 Not Ready for Inspection MARK JOHNSON
Final 12/17/2020 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 12/17/2020 Approved MARK JOHNSON
Green Building Final 12/17/2020 Approved MARK JOHNSON
Green Building Rough 12/17/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 12/17/2020 SGSOV Approved MARK JOHNSON
Service/Power Release 12/17/2020 Not Required MARK JOHNSON
Smoke Detectors 12/17/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 2/22/2021 Corrections Issued MARK JOHNSON
Final 2/22/2021 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 3/3/2021 Approved MARK JOHNSON
Final 3/3/2021 OK to Issue CofO MARK JOHNSON