8812 W BEVERLYWOOD ST 90034

Certificate Information: 8812 W BEVERLYWOOD ST 90034

Application / Permit
17010-20000-03711
Plan Check / Job No.
B17VN14550
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DET. GARAGE W/ADU ABOVE - PER AB 2299 AND SB 1069
Permit Issued
Issued on 2/5/2018
Issuing Office
Valley
Current Status
CofO Issued on 7/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2017 APPLICANT
Assigned to Plan Check Engineer 10/5/2017 TARIK SAOUD
Green Plans Picked Up 10/6/2017 APPLICANT
Corrections Issued 10/10/2017 TARIK SAOUD
Quality Review Completed 10/13/2017 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 10/17/2017 APPLICANT
Plan Check Approved 1/11/2018 TARIK SAOUD
Issued 2/5/2018 LADBS
CofO in Progress 1/13/2020 EVAN COOPER
Permit Finaled 7/9/2020 VINCENT COTTON
CofO Issued 7/9/2020 VINCENT COTTON
Permit Finaled 7/9/2020 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 11/2/2017 KENNETH PHAM
Eng Process Fee Ord 176,300 Cleared 11/2/2017 KENNETH PHAM
Permit Cleared 11/2/2017 KENNETH PHAM
Sewer availability Cleared 11/2/2017 KENNETH PHAM
Green Code Cleared 11/16/2017 MICKEY YAMASHITA
Low Impact Development Cleared 12/18/2017 MITESH PATEL
Hydrant and Access approval Cleared 1/4/2018 GILBERT URREA
Permit Cleared 1/4/2018 KAYLA PEJI
Roof/Waste drainage to street Cleared 1/4/2018 KAYLA PEJI

Contact Information

Architect Maly, Farzin; Lic. No.: C33731 PO BOX 57002      SHERMAN OAKS, CA 91413
Contractor Owner-Builder       ,
Engineer Munroe, Massie; Lic. No.: C59905 PO BOX 7278      BEVERLY HILLS, CA 90212

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/6/2018 Conditional Approval MATTHEW NUCKOLLS
Floor/Roof Diaphrgm/Shear Wall 5/22/2018 Partial Approval MATTHEW NUCKOLLS
BUILDING-Rough-Frame 8/30/2018 Conditional Approval AJA COLLAY
Green Building Rough 8/30/2018 Not Ready for Inspection AJA COLLAY
MERV13>=Rough 8/30/2018 Not Ready for Inspection AJA COLLAY
Rough-Elec/Plmb/HVAC 8/30/2018 Approved AJA COLLAY
Verify Sprinkler Sign Off 8/30/2018 Not Ready for Inspection AJA COLLAY
Floor/Roof Diaphrgm/Shear Wall 9/20/2018 Partial Approval ROBERT VORHIS
Interior/Exterior Lathing 9/20/2018 Approved ROBERT VORHIS
BUILDING-Rough-Frame 9/27/2018 Corrections Issued ROBERT VORHIS
Green Building Rough 9/27/2018 Approved ROBERT VORHIS
MERV13>=Rough 9/27/2018 Approved ROBERT VORHIS
Verify Sprinkler Sign Off 9/27/2018 Corrections Issued ROBERT VORHIS
BUILDING-Rough-Frame 10/4/2018 Corrections Issued ROBERT VORHIS
Pre-Inspection 10/4/2018 Partial Inspection MICHAEL TEMPLE
Verify Sprinkler Sign Off 10/4/2018 Partial Inspection ROBERT VORHIS
BUILDING-Rough-Frame 3/4/2019 Partial Inspection ROBERT VORHIS
ELECTRICAL-Rough 3/4/2019 Approved ROBERT VORHIS
PLUMBING-Rough 3/4/2019 Conditional Approval ROBERT VORHIS
Verify Sprinkler Sign Off 3/4/2019 Not Ready for Inspection ROBERT VORHIS
BUILDING-Rough-Frame 4/26/2019 Not Ready for Inspection KEVIN BEAULIEU
Interior/Exterior Lathing 4/26/2019 Not Ready for Inspection KEVIN BEAULIEU
Rough-Elec/Plmb/HVAC 4/26/2019 Approved KEVIN BEAULIEU
Verify Sprinkler Sign Off 4/26/2019 Approved KEVIN BEAULIEU
BUILDING-Rough-Frame 5/1/2019 Approved ROBERT VORHIS
Green Building Rough 5/1/2019 Approved ROBERT VORHIS
Insulation 5/1/2019 Approved ROBERT VORHIS
Drywall Nailing 6/20/2019 Approved ROBERT VORHIS
Service/Power Release 10/31/2019 Not Ready for Inspection ROBERT SHELLY
Final 12/9/2019 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 12/9/2019 Not Ready for Inspection EVAN COOPER
Green Building Final 12/9/2019 Not Ready for Inspection EVAN COOPER
MERV13>=Final 12/9/2019 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/9/2019 SGSOV Approved EVAN COOPER
Service/Power Release 12/9/2019 Not Ready for Inspection EVAN COOPER
Smoke Detectors 12/9/2019 Not Ready for Inspection EVAN COOPER
Final 12/18/2019 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 12/18/2019 Approved EVAN COOPER
Green Building Final 12/18/2019 Not Ready for Inspection EVAN COOPER
Service/Power Release 12/18/2019 Not Ready for Inspection EVAN COOPER
Smoke Detectors 12/18/2019 Approved EVAN COOPER
Final 1/3/2020 OK to Issue CofO EVAN COOPER
Service/Power Release 1/3/2020 Approved EVAN COOPER
Green Building Final 1/6/2020 Approved KENNETH NAGLE
Special/Order Compliance 1/23/2020 Corrections Issued EVAN COOPER