8812 W BEVERLYWOOD ST 90034
Certificate Information: 8812 W BEVERLYWOOD ST 90034
- Application / Permit
- 17010-20000-03711
- Plan Check / Job No.
- B17VN14550
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DET. GARAGE W/ADU ABOVE - PER AB 2299 AND SB 1069
- Permit Issued
- Issued on 2/5/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2017 | TARIK SAOUD |
| Green Plans Picked Up | 10/6/2017 | APPLICANT |
| Corrections Issued | 10/10/2017 | TARIK SAOUD |
| Quality Review Completed | 10/13/2017 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 10/17/2017 | APPLICANT |
| Plan Check Approved | 1/11/2018 | TARIK SAOUD |
| Issued | 2/5/2018 | LADBS |
| CofO in Progress | 1/13/2020 | EVAN COOPER |
| Permit Finaled | 7/9/2020 | VINCENT COTTON |
| CofO Issued | 7/9/2020 | VINCENT COTTON |
| Permit Finaled | 7/9/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 11/2/2017 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2017 | KENNETH PHAM |
| Permit | Cleared | 11/2/2017 | KENNETH PHAM |
| Sewer availability | Cleared | 11/2/2017 | KENNETH PHAM |
| Green Code | Cleared | 11/16/2017 | MICKEY YAMASHITA |
| Low Impact Development | Cleared | 12/18/2017 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 1/4/2018 | GILBERT URREA |
| Permit | Cleared | 1/4/2018 | KAYLA PEJI |
| Roof/Waste drainage to street | Cleared | 1/4/2018 | KAYLA PEJI |
Contact Information
| Architect | Maly, Farzin; Lic. No.: C33731 | PO BOX 57002 SHERMAN OAKS, CA 91413 |
| Contractor | Owner-Builder | , |
| Engineer | Munroe, Massie; Lic. No.: C59905 | PO BOX 7278 BEVERLY HILLS, CA 90212 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/6/2018 | Conditional Approval | MATTHEW NUCKOLLS |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2018 | Partial Approval | MATTHEW NUCKOLLS |
| BUILDING-Rough-Frame | 8/30/2018 | Conditional Approval | AJA COLLAY |
| Green Building Rough | 8/30/2018 | Not Ready for Inspection | AJA COLLAY |
| MERV13>=Rough | 8/30/2018 | Not Ready for Inspection | AJA COLLAY |
| Rough-Elec/Plmb/HVAC | 8/30/2018 | Approved | AJA COLLAY |
| Verify Sprinkler Sign Off | 8/30/2018 | Not Ready for Inspection | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2018 | Partial Approval | ROBERT VORHIS |
| Interior/Exterior Lathing | 9/20/2018 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 9/27/2018 | Corrections Issued | ROBERT VORHIS |
| Green Building Rough | 9/27/2018 | Approved | ROBERT VORHIS |
| MERV13>=Rough | 9/27/2018 | Approved | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 9/27/2018 | Corrections Issued | ROBERT VORHIS |
| BUILDING-Rough-Frame | 10/4/2018 | Corrections Issued | ROBERT VORHIS |
| Pre-Inspection | 10/4/2018 | Partial Inspection | MICHAEL TEMPLE |
| Verify Sprinkler Sign Off | 10/4/2018 | Partial Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 3/4/2019 | Partial Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 3/4/2019 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 3/4/2019 | Conditional Approval | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 3/4/2019 | Not Ready for Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 4/26/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Interior/Exterior Lathing | 4/26/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Rough-Elec/Plmb/HVAC | 4/26/2019 | Approved | KEVIN BEAULIEU |
| Verify Sprinkler Sign Off | 4/26/2019 | Approved | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 5/1/2019 | Approved | ROBERT VORHIS |
| Green Building Rough | 5/1/2019 | Approved | ROBERT VORHIS |
| Insulation | 5/1/2019 | Approved | ROBERT VORHIS |
| Drywall Nailing | 6/20/2019 | Approved | ROBERT VORHIS |
| Service/Power Release | 10/31/2019 | Not Ready for Inspection | ROBERT SHELLY |
| Final | 12/9/2019 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 12/9/2019 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 12/9/2019 | Not Ready for Inspection | EVAN COOPER |
| MERV13>=Final | 12/9/2019 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/9/2019 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 12/9/2019 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 12/9/2019 | Not Ready for Inspection | EVAN COOPER |
| Final | 12/18/2019 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 12/18/2019 | Approved | EVAN COOPER |
| Green Building Final | 12/18/2019 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 12/18/2019 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 12/18/2019 | Approved | EVAN COOPER |
| Final | 1/3/2020 | OK to Issue CofO | EVAN COOPER |
| Service/Power Release | 1/3/2020 | Approved | EVAN COOPER |
| Green Building Final | 1/6/2020 | Approved | KENNETH NAGLE |
| Special/Order Compliance | 1/23/2020 | Corrections Issued | EVAN COOPER |