5733 S ALBA ST 90058
Certificate Information: 5733 S ALBA ST 90058
- Application / Permit
- 17010-20000-03673
- Plan Check / Job No.
- B17VN14389
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- NEW 1-STORY, IRR. 100'-6" X 54' WAREHOUSE & OFFICE AND ATTACHED 49'-10" X 40'-8" CARPORT "COMPLY WITH DEPARTMENT ORDER effective date 07/15/2015. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 12/24/2019
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 7/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2017 | ALEXANDER SBARDELLATI |
| Corrections Issued | 10/30/2017 | ALEXANDER SBARDELLATI |
| Quality Review Completed | 10/31/2017 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 11/7/2017 | APPLICANT |
| Disabled Access Plans Picked Up | 11/7/2017 | APPLICANT |
| Green Plans Picked Up | 3/18/2019 | APPLICANT |
| Plan Check Approved | 12/17/2019 | SELLA BENYAMIN |
| Issued | 12/24/2019 | LADBS |
| CofO in Progress | 9/4/2024 | JAMES POWERS |
| CofO Issued-Status Void | 9/4/2024 | ERNESTO CORRAL |
| Permit Finaled-Status Void | 9/4/2024 | ERNESTO CORRAL |
| Re-Activate Permit | 7/21/2025 | ERNESTO CORRAL |
| Permit Finaled | 7/21/2025 | ERNESTO CORRAL |
| CofO Corrected | 7/21/2025 | ERNESTO CORRAL |
| Permit Finaled | 7/21/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Highway dedication | Cleared | 4/11/2019 | JEANETTE VONG |
| Address approval | Cleared | 7/11/2019 | ELENA LOPEZ |
| CPC | Cleared | 7/11/2019 | DIANA JIMENEZ |
| Miscellaneous | Cleared | 7/11/2019 | DIANA JIMENEZ |
| Permit | Cleared | 7/11/2019 | ELENA LOPEZ |
| Project located in CRA area | Cleared | 7/11/2019 | JIM URQUHART |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 7/15/2019 | GILBERT URREA |
| Sewer availability | Cleared | 7/15/2019 | CELINA MORENO |
| Work Adjacent to Public Way | Cleared | 8/5/2019 | BOK GOH |
| Green Code | Cleared | 8/19/2019 | DAVID MATSON |
| ZI | Cleared | 9/3/2019 | STEVE GARCIA |
| Low Impact Development | Cleared | 12/4/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/4/2019 | CELINA MORENO |
| DAS Clearance | Cleared | 12/9/2019 | ALEXANDER SBARDELLATI |
Contact Information
| Contractor | Ksj Design Build; Lic. No.: 997235-B | 13337 SOUTH ST #266 CERRITOS, CA 90703 |
| Engineer | Kim, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/6/2020 | Approved | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 4/30/2020 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 4/30/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 5/1/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 5/4/2020 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 5/8/2020 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 5/12/2020 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 5/13/2020 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 5/15/2020 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 9/21/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 9/21/2020 | Partial Approval | JAMES POWERS |
| Green Building Rough | 2/19/2021 | Approved | JAMES POWERS |
| Structural Steel Frame | 2/19/2021 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 2/19/2021 | Not Ready for Inspection | JAMES POWERS |
| Structural Steel Frame | 5/5/2021 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 5/5/2021 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 6/17/2021 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2021 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/17/2021 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 7/14/2021 | Approved | JAMES POWERS |
| Wall Anchors | 7/14/2021 | Approved | JAMES POWERS |
| Final | 9/6/2023 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 9/6/2023 | Approved | JAMES POWERS |
| Green Building Final | 9/6/2023 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 9/6/2023 | SGSOV No Gas | JAMES POWERS |
| Smoke Detectors | 9/6/2023 | Approved | JAMES POWERS |
| Structural Steel Frame | 9/6/2023 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 9/6/2023 | Approved | JAMES POWERS |
| Wood Frame | 9/6/2023 | Approved | JAMES POWERS |
| Final | 2/8/2024 | No Access for Inspection | JAMES POWERS |
| Final | 2/9/2024 | Not Ready for Inspection | JAMES POWERS |
| Final | 9/4/2024 | OK to Issue CofO | JAMES POWERS |