1225 N HILLGROVE PL 90210

Certificate Information: 1225 N HILLGROVE PL 90210

Application / Permit
17010-20000-03384
Plan Check / Job No.
B17VN13219
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 84.2' x 148.2' (IRR. SHAPE) TWO STORY SINGLE FAMILY DWELLING WITH BASEMENT, ROOF DECK, AND ATTACHED 5 CAR GARAGE
Permit Issued
Issued on 9/3/2021
Issuing Office
Valley
Current Status
Issued on 9/3/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/1/2017 APPLICANT
Assigned to Plan Check Engineer 9/7/2017 JEFFREY TANGONAN
Corrections Issued 9/11/2017 JEFFREY TANGONAN
Quality Review Completed 9/15/2017 GUANG MIN TUNG
Green Plans Picked Up 9/18/2017 APPLICANT
Applicant returned to address corrections 4/29/2021 JEFFREY TANGONAN
Plan Check Approved 7/23/2021 JEFFREY TANGONAN
Building Plans Picked Up 8/5/2021 APPLICANT
Issued 9/3/2021 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/25/2017 KENNETH PHAM
BHO/Hillside ordinance Cleared 10/25/2017 KENNETH PHAM
CPC Cleared 10/25/2017 ANNA VIDAL
Permit Cleared 10/25/2017 KENNETH PHAM
ZA Case Cleared 10/25/2017 ANNA VIDAL
Low Impact Development Cleared 12/14/2017 SAM NAVID
Green Code Cleared 1/4/2018 MICKEY YAMASHITA
Hydrant and Access approval Cleared 3/13/2018 OSCAR SALGADO JR
BHO/Hillside ordinance Cleared 3/15/2018 CHRISTOPHER LAW
Eng Process Fee Ord 176,300 Cleared 3/15/2018 KENNETH PHAM
GPI Written Notices Cleared 3/15/2018 JEFFREY TANGONAN
Grading Pre-Inspection Cleared 3/15/2018 JEFFREY TANGONAN
Roof/Waste drainage to street Cleared 3/15/2018 KENNETH PHAM
Sewer availability Cleared 3/15/2018 KENNETH PHAM

Contact Information

Architect Jazayeri, Siavash; Lic. No.: C22240 20230 WELLS DR      WOODLAND HILLS, CA 91364
Contractor Ke General Building Inc; Lic. No.: 1049318-B 5227 PACIFIC AVENUE      LONG BEACH, CA 90805
Engineer Yuzon, Benigno S Jr; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302
Geologist Lieurance, Martin Ellis; Lic. No.: EG1810 GROVER-HOLLINGSWORTH & ASSOCIATE   31129 VIA COLINAS STE 707    WESTLAKE VILLAGE, CA 91362

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 8/22/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/26/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 10/6/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 10/6/2022 Approved GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 10/8/2022 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 10/8/2022 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 10/8/2022 Off-Hour Fees Due
Footing/Foundation/Slab 10/12/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 10/18/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 11/7/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 11/10/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 11/15/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 11/30/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 11/30/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/7/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 12/9/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 12/14/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 1/20/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 2/13/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 2/13/2023 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 2/22/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 2/22/2023 Off-Hour Fees Due
Deputy Reinf. Concrete 2/23/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 4/7/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 4/7/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Shotcrete 4/11/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 4/17/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 4/18/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 4/20/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 5/15/2023 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 5/15/2023 Partial Approval BRENDAN LOONEY
Deputy Reinf. Concrete 5/17/2023 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 7/18/2023 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Partial Approval MICHAEL PELHAM
Deputy Wood Construction 8/9/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 12/5/2023 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 3/8/2024 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 3/8/2024 Corrections Issued SEAN HAUPT
Gas Test 3/8/2024 Partial Approval SEAN HAUPT
Green Building Rough 3/8/2024 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 3/8/2024 Corrections Issued SEAN HAUPT
Verify Sprinkler Sign Off 3/8/2024 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Corrections Issued SEAN HAUPT
Deputy Wood Construction 3/14/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Approved SEAN HAUPT
PLUMBING-Rough 4/11/2024 Partial Approval STEPHANIE SWANSON
Deputy Steel/Welding 5/7/2024 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 5/13/2024 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 5/17/2024 Conditional Approval MICHAEL PELHAM
HVAC-Rough 6/10/2024 Corrections Issued MICHAEL PELHAM
Interior/Exterior Lathing 6/12/2024 Partial Approval STEPHANIE SWANSON
HVAC-Rough 6/21/2024 Approved SEAN HAUPT
Shower Pan 7/10/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 9/3/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 9/10/2024 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 9/20/2024 Partial Approval SEAN HAUPT
Green Building Rough 9/20/2024 Partial Approval SEAN HAUPT
Verify Sprinkler Sign Off 9/20/2024 Approved SEAN HAUPT
Insulation 9/30/2024 Partial Approval SEAN HAUPT
Interior/Exterior Lathing 10/23/2024 Partial Approval SEAN HAUPT
Interior/Exterior Lathing 11/5/2024 Approved STEPHANIE SWANSON
Drywall Nailing 12/12/2024 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 12/18/2024 Partial Approval REGINA MENDEZ
Special/Order Compliance 3/18/2026 Corrections Issued CARLOS MATAMOROS