9900 N BALBOA BLVD 91325
Certificate Information: 9900 N BALBOA BLVD 91325
- Application / Permit
- 17010-20000-03135
- Plan Check / Job No.
- B17VN12130
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- NEW RESTURANT WITH DRIVE THRU.
- Permit Issued
- Issued on 4/23/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/5/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2017 | RODNEY SAMIIAN |
| Corrections Issued | 9/18/2017 | RODNEY SAMIIAN |
| Quality Review Completed | 9/20/2017 | ABDUL CHEGENI |
| Building Plans Picked Up | 9/26/2017 | APPLICANT |
| Disabled Access Plans Picked Up | 9/26/2017 | APPLICANT |
| Green Plans Picked Up | 9/26/2017 | APPLICANT |
| Applicant returned to address corrections | 3/21/2019 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 3/26/2019 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 4/8/2019 | RODNEY SAMIIAN |
| Plan Check Approved | 4/16/2019 | RODNEY SAMIIAN |
| Issued | 4/23/2019 | LADBS |
| TCO Issued (Expire Date: 10-19-2020) | 4/22/2020 | RICKEY JACKSON |
| CofO in Progress | 10/5/2020 | RICKEY JACKSON |
| Permit Finaled | 10/5/2020 | RICKEY JACKSON |
| CofO Issued | 10/5/2020 | RICKEY JACKSON |
| Permit Finaled | 10/5/2020 | RICKEY JACKSON |
Permit Application Clearance Information
| Green Code | Cleared | 10/24/2017 | MICHAEL AYERS |
| ZA Case | Cleared | 4/12/2018 | DENNIS CHEW |
| Low Impact Development | Cleared | 4/19/2018 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2018 | EDUARDO PEDROZA |
| Fire Marshall Fire Life Safety | Cleared | 4/24/2018 | JOHN DALLAS |
| Highway dedication | Cleared | 4/24/2018 | EDUARDO PEDROZA |
| Hydrant and Access approval | Cleared | 4/24/2018 | JOHN DALLAS |
| Roof/Waste drainage to street | Cleared | 4/24/2018 | EDUARDO PEDROZA |
| Sewer availability | Cleared | 4/24/2018 | EDUARDO PEDROZA |
| Food Service Establishment | Cleared | 5/16/2018 | PAWAN VERMA |
| Comm Cor/Mini-Mall | Cleared | 3/21/2019 | SHEILA GERSHON |
| Comm Cor/Mini-Mall | Cleared | 3/21/2019 | SHEILA GERSHON |
| Drive-through fast food | Cleared | 3/21/2019 | SHEILA GERSHON |
| Food establishment approval | Cleared | 3/21/2019 | LACDHS APPROVED |
| GPI Written Notices | Cleared | 3/21/2019 | ABDUL CHEGENI |
| Grading Pre-Inspection | Cleared | 3/21/2019 | ABDUL CHEGENI |
| Miscellaneous | Cleared | 3/21/2019 | ABDUL CHEGENI |
| Prkng lot landscape/Water mgmt | Cleared | 3/21/2019 | SHEILA GERSHON |
| ZA Case | Cleared | 3/21/2019 | SHEILA GERSHON |
| ZA Case | Cleared | 3/21/2019 | SHEILA GERSHON |
| Permit | Cleared | 3/26/2019 | MARKOS PEREZ-BRAN |
| DAS Clearance | Cleared | 4/16/2019 | NORLITO MEDRANO |
Contact Information
| Architect | Couper, Douglas S; Lic. No.: C25874 | 24315 AIRPORTER WAY LAGUNA NIGUEL, CA 92677 |
| Contractor | Cirks Construction Inc; Lic. No.: 763589-B | 1442 E LINCOLN AVENUE #334 ORANGE, CA 92865 |
| Engineer | New, Rod G; Lic. No.: S3419 | 1710 AURELIA DRIVE CUMMING, GA 30041 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/9/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Pre-Inspection | 10/21/2019 | Partial Inspection | ROBERT COLE |
| Excavation/Setback/Form/Re-Bar | 11/18/2019 | Not Ready for Inspection | ROBERT COLE |
| Excavation/Setback/Form/Re-Bar | 11/19/2019 | Partial Approval | ROBERT COLE |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2019 | Not Ready for Inspection | ROBERT COLE |
| Deputy Wood Construction | 12/13/2019 | Conditional Approval | JAMES STEPHENS |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 12/18/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 12/18/2019 | Partial Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 12/18/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 12/18/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 1/15/2020 | Not Ready for Inspection | ROBERT COLE |
| Verify Sprinkler Sign Off | 1/15/2020 | Not Ready for Inspection | ROBERT COLE |
| Wood Frame | 1/15/2020 | Conditional Approval | ROBERT COLE |
| Green Building Rough | 1/23/2020 | Not Ready for Inspection | ROBERT COLE |
| Verify Sprinkler Sign Off | 1/23/2020 | Not Ready for Inspection | ROBERT COLE |
| Wood Frame | 1/23/2020 | Partial Approval | ROBERT COLE |
| Excavation/Setback/Form/Re-Bar | 2/3/2020 | Partial Approval | JEFFREY DURAN |
| Interior/Exterior Lathing | 2/3/2020 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 2/5/2020 | Partial Approval | ROBERT COLE |
| Green Building Rough | 2/5/2020 | Not Ready for Inspection | ROBERT COLE |
| Insulation | 2/5/2020 | Partial Approval | ROBERT COLE |
| Drywall Nailing | 2/6/2020 | Partial Approval | ROBERT COLE |
| T-Bar Ceiling | 2/14/2020 | Not Ready for Inspection | ROBERT COLE |
| T-Bar Ceiling | 2/26/2020 | Approved | ROBERT COLE |
| Drywall Nailing | 3/23/2020 | Not Ready for Inspection | ROBERT COLE |
| Final | 3/23/2020 | Not Ready for Inspection | ROBERT COLE |
| Footing/Foundation/Slab | 3/23/2020 | Not Ready for Inspection | ROBERT COLE |
| Green Building Final | 3/23/2020 | Not Ready for Inspection | ROBERT COLE |
| Green Building Rough | 3/23/2020 | Approved | ROBERT COLE |
| SGSOV-Seismic Gas S/O Valve | 3/23/2020 | SGSOV Approved | ROBERT COLE |
| Smoke Detectors | 3/23/2020 | Approved | ROBERT COLE |
| Verify Sprinkler Sign Off | 3/23/2020 | Approved | ROBERT COLE |
| Wood Frame | 3/23/2020 | Not Ready for Inspection | ROBERT COLE |
| Drywall Nailing | 4/6/2020 | Approved | ROBERT COLE |
| Final | 4/6/2020 | Partial Inspection | ROBERT COLE |
| Footing/Foundation/Slab | 4/6/2020 | Approved | ROBERT COLE |
| Green Building Final | 4/6/2020 | Approved | ROBERT COLE |
| Wood Frame | 4/6/2020 | Approved | ROBERT COLE |
| Final | 4/20/2020 | Partial Inspection | ROBERT COLE |
| Special/Order Compliance | 9/25/2020 | Approved | HAMID PISHEHVAR |
| Final | 10/5/2020 | OK to Issue CofO | RICKEY JACKSON |