7401 N LANKERSHIM BLVD 91605

Certificate Information: 7401 N LANKERSHIM BLVD 91605

Application / Permit
17010-20000-02985
Plan Check / Job No.
B17VN11495
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
5-story mixed use commercial residential building. 4-story, 108 units (9 units (8%) set aside for Extremely low income household), Type VA apartment building over one level Type I podium commercial/parking over one level basement parking. (TOC project - See comment)
Permit Issued
Issued on 9/19/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2017 APPLICANT
Assigned to Plan Check Engineer 8/17/2017 KAMRAN GHOTBI RAVANDI
Corrections Issued 8/21/2017 KAMRAN GHOTBI RAVANDI
Quality Review Completed 8/25/2017 TIEN JEN WANG
Building Plans Picked Up 9/14/2017 APPLICANT
Green Plans Picked Up 9/14/2017 APPLICANT
Disabled Access Plans Picked Up 10/4/2017 APPLICANT
Applicant returned to address corrections 8/29/2018 KAMRAN GHOTBI RAVANDI
Plan Check Approved 9/19/2019 KAMRAN GHOTBI RAVANDI
Issued 9/19/2019 LADBS
CofO in Progress 4/20/2021 DANNY RODRIGUEZ
Permit Finaled 4/23/2021 RICKEY JACKSON
CofO Issued 4/23/2021 RICKEY JACKSON
Permit Finaled 4/23/2021 RICKEY JACKSON

Permit Application Clearance Information

Work Adjacent to Public Way Cleared 7/30/2018 KAYLA PEJI
Hydrant and Access approval Cleared 8/28/2018 JOHN DALLAS
Driveway location Cleared 10/17/2018 KEN AITCHISON
Internal circulation Cleared 10/17/2018 KEN AITCHISON
Address approval Cleared 10/23/2018 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 11/8/2018 KAYLA PEJI
Highway dedication Cleared 11/8/2018 KAYLA PEJI
Construction near power lines Cleared 11/28/2018 RIDWAN HARDY
Density Bonus 12.22.A.31 Cleared 12/17/2018 JAMES MCCARTHY
"Q" conditions Cleared 12/18/2018 DAISY BENICIA
"T" removal Cleared 12/18/2018 DAISY BENICIA
CPC Cleared 12/18/2018 DAISY BENICIA
Tract Map conditions Cleared 12/18/2018 DAISY BENICIA
Low Impact Development Cleared 12/21/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 12/21/2018 ADRIAN SANCHEZ
Miscellaneous Cleared 1/29/2019 DAISY BENICIA
Opn space landscape/Water mgmt Cleared 1/29/2019 DAISY BENICIA
Site Plan review Cleared 1/29/2019 DAISY BENICIA
DAS Clearance Cleared 3/22/2019 NORLITO MEDRANO
Green Code Cleared 3/22/2019 DAVID MATSON
Sewer availability Cleared 3/22/2019 ISRAEL TAMIRU
Fire Marshall Fire Life Safety Cleared 9/9/2019 OSCAR SALGADO JR
Building over 3-story or 36-ft Cleared 9/19/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 9/19/2019 CALOSHA APPROVED
Permit Cleared 9/19/2019 MIKE KOUYOUMDJIAN

Contact Information

Contractor Jasco Enterprise Inc; Lic. No.: 871467-B 12439 MAGNOLIA BL 185      VALLEY VILLAGE, CA 91607
Engineer Demetreos,, Emily Wood; Lic. No.: C71467 1983 N DOUGLAS AVE      CLOVIS, CA 93619
Engineer Vidal, Juan Alonso; Lic. No.: GE861 15331 DOGWOOD ST      WESTMINSTER, CA 92683

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/7/2019 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 10/7/2019 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 10/8/2019 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/9/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/10/2019 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/15/2019 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/16/2019 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 10/16/2019 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/17/2019 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 10/24/2019 Not Ready for Inspection JOHN KITCKO
Green Building Rough 10/24/2019 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 10/24/2019 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 10/24/2019 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 11/1/2019 Partial Approval DANNY RODRIGUEZ
Green Building Rough 11/1/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 11/1/2019 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/1/2019 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/12/2019 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/19/2019 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 11/20/2019 No Access for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/21/2019 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/22/2019 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 11/22/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 11/22/2019 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/22/2019 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/4/2019 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 12/4/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 12/4/2019 Corrections Issued DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/4/2019 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/6/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/6/2019 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/9/2019 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/11/2019 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/13/2019 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 12/13/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 12/13/2019 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/13/2019 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/20/2019 Partial Approval DANNY RODRIGUEZ
Pre-Inspection 1/8/2020 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 1/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 1/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 1/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/15/2020 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 1/16/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 1/16/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 1/16/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/16/2020 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/23/2020 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 1/23/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 1/27/2020 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/28/2020 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 1/28/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 1/28/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 1/28/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/28/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/29/2020 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/5/2020 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/5/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/5/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 2/5/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/5/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 2/7/2020 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 2/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 2/10/2020 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 2/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/11/2020 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/12/2020 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 2/12/2020 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/12/2020 SGSOV Not Ready DANNY RODRIGUEZ
Deputy Wood Construction 2/14/2020 Conditional Approval RICKEY JACKSON
Floor/Roof Diaphrgm/Shear Wall 2/14/2020 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 2/21/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 2/21/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 2/24/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 2/24/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/25/2020 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/25/2020 Corrections Issued DANNY RODRIGUEZ
Green Building Rough 2/25/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/25/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 2/26/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 2/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 2/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/28/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 3/2/2020 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 3/2/2020 Not Ready for Inspection JEFFREY DURAN
Footing/Foundation/Slab 3/2/2020 Corrections Issued JOHN KITCKO
Reinforced Concrete Frame 3/2/2020 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 3/2/2020 Not Ready for Inspection JEFFREY DURAN
Masonry Wall/Backfill 3/4/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 3/4/2020 Corrections Issued DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/5/2020 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/5/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/6/2020 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 3/11/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/11/2020 Partial Inspection DANNY RODRIGUEZ
Deputy Wood Construction 3/12/2020 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 3/17/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 3/17/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/17/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 3/17/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 3/18/2020 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 3/18/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 3/19/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/19/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 3/19/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/19/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 3/19/2020 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/20/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 No Access for Inspection JEFFREY FULTON
Green Building Rough 3/26/2020 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 3/26/2020 Not Ready for Inspection JEFFREY FULTON
Wood Frame 3/26/2020 No Access for Inspection JEFFREY FULTON
Footing/Foundation/Slab 3/31/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 3/31/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/1/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/1/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/1/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/1/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/3/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 4/3/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/6/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/9/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/9/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/9/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/9/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/15/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/15/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/15/2020 Partial Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 4/21/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Wood Construction 4/22/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 4/23/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 4/23/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/23/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/23/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/28/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Partial Approval JOE VELASQUEZ
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 5/4/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/4/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 5/4/2020 Partial Approval DANNY RODRIGUEZ
Wood Frame 5/5/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 5/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/6/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 5/6/2020 Partial Approval DANNY RODRIGUEZ
Insulation 5/7/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 5/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 5/11/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 5/11/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/11/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 5/11/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 5/12/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/12/2020 Partial Approval DANNY RODRIGUEZ
Insulation 5/12/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/13/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/13/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/14/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 5/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/14/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 5/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/15/2020 Partial Approval JOE VELASQUEZ
Insulation 5/15/2020 Approved JOE VELASQUEZ
Drywall Nailing 5/20/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/20/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 5/20/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/21/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 5/21/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 5/22/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 5/22/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 5/22/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/22/2020 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 5/28/2020 Not Ready for Inspection JOE VELASQUEZ
Floor/Roof Diaphrgm/Shear Wall 5/28/2020 Partial Approval JOE VELASQUEZ
Green Building Rough 5/28/2020 Not Ready for Inspection JOE VELASQUEZ
Verify Sprinkler Sign Off 5/28/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 5/28/2020 Partial Approval JOE VELASQUEZ
Drywall Nailing 6/3/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 6/3/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 6/4/2020 Partial Approval DANNY RODRIGUEZ
Insulation 6/4/2020 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 6/9/2020 Approved DANNY RODRIGUEZ
Drywall Nailing 6/9/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 6/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 6/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 6/11/2020 Partial Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 6/12/2020 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 6/15/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 6/16/2020 Partial Approval DANNY RODRIGUEZ
Insulation 6/16/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/16/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 6/16/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/17/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/18/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 6/18/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/18/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 6/18/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Partial Approval DANNY RODRIGUEZ
Insulation 6/22/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 6/22/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/24/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/24/2020 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 6/24/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 6/24/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/24/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 6/24/2020 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 6/25/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 6/26/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 6/30/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 6/30/2020 Partial Approval DANNY RODRIGUEZ
Insulation 7/1/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 7/1/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/2/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 7/2/2020 Partial Approval DANNY RODRIGUEZ
Insulation 7/2/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/2/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 7/2/2020 Partial Approval DANNY RODRIGUEZ
Pre-Inspection 7/6/2020 Partial Approval ROBERT DAVIS
Wood Frame 7/7/2020 Partial Approval DANNY RODRIGUEZ
Insulation 7/8/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 7/8/2020 Approved HAMID PISHEHVAR
Insulation 7/9/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/10/2020 Partial Approval DANNY RODRIGUEZ
Insulation 7/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 7/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 7/13/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/14/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/14/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 7/14/2020 Partial Approval DANNY RODRIGUEZ
Insulation 7/14/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 7/14/2020 Partial Inspection DANNY RODRIGUEZ
Insulation 7/15/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/16/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 7/16/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 7/16/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 7/17/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 7/17/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/20/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 7/20/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 7/21/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 7/21/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 7/21/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/21/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 7/21/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/22/2020 Partial Approval DANNY RODRIGUEZ
Wood Frame 7/22/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/23/2020 Partial Approval DANNY RODRIGUEZ
Insulation 7/23/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 7/27/2020 Partial Approval DANNY RODRIGUEZ
Insulation 7/27/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/27/2020 Partial Approval DANNY RODRIGUEZ
Wood Frame 7/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/28/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/28/2020 Partial Approval DANNY RODRIGUEZ
Insulation 7/29/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 7/29/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 7/30/2020 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 7/30/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/31/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 7/31/2020 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 7/31/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/3/2020 Partial Inspection ANDREW DORSO
Green Building Rough 8/3/2020 Not Ready for Inspection ANDREW DORSO
Insulation 8/3/2020 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 8/3/2020 Not Ready for Inspection ANDREW DORSO
Verify Sprinkler Sign Off 8/3/2020 Not Ready for Inspection ANDREW DORSO
Wood Frame 8/3/2020 Not Ready for Inspection ANDREW DORSO
Insulation 8/4/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 8/4/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/5/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 8/5/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/6/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 8/6/2020 Partial Approval DANNY RODRIGUEZ
Insulation 8/7/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 8/7/2020 Partial Approval DANNY RODRIGUEZ
Insulation 8/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 8/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/11/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 8/11/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/12/2020 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 8/12/2020 Not Ready for Inspection JOHN KITCKO
Light Gage Steel Frame 8/12/2020 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 8/13/2020 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 8/13/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 8/13/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 8/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 8/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 8/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/17/2020 Not Ready for Inspection HAMID PISHEHVAR
Light Gage Steel Frame 8/17/2020 Approved HAMID PISHEHVAR
Drywall Nailing 8/18/2020 Approved HAMID PISHEHVAR
Insulation 8/18/2020 Approved HAMID PISHEHVAR
Green Building Rough 8/19/2020 Partial Approval HAMID PISHEHVAR
Insulation 8/19/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 8/19/2020 Approved HAMID PISHEHVAR
Verify Sprinkler Sign Off 8/19/2020 Partial Approval HAMID PISHEHVAR
Wood Frame 8/19/2020 Partial Approval HAMID PISHEHVAR
Insulation 8/21/2020 Partial Approval RONALD PACHECO
Light Gage Steel Frame 8/21/2020 Partial Approval RONALD PACHECO
Drywall Nailing 8/24/2020 Partial Approval DANNY RODRIGUEZ
Insulation 8/24/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/25/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 8/25/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 8/25/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 8/26/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 8/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 8/27/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 8/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/28/2020 Partial Approval DANNY RODRIGUEZ
Insulation 8/28/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/31/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/1/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 9/2/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/3/2020 Partial Approval DANNY RODRIGUEZ
Insulation 9/3/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/4/2020 Not Ready for Inspection JOE VELASQUEZ
Light Gage Steel Frame 9/4/2020 Not Ready for Inspection JOE VELASQUEZ
Drywall Nailing 9/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/14/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 9/22/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/22/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 9/22/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/23/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 9/25/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 9/25/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/29/2020 Partial Approval DANNY RODRIGUEZ
Insulation 9/29/2020 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/30/2020 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 10/2/2020 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/2/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 10/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 10/9/2020 Not Ready for Inspection RONALD PACHECO
Light Gage Steel Frame 10/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 10/15/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 10/16/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 10/21/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 10/22/2020 Not Ready for Inspection HAMID PISHEHVAR
Light Gage Steel Frame 10/23/2020 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 10/26/2020 Approved DANNY RODRIGUEZ
Drywall Nailing 10/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 11/2/2020 Partial Inspection JONATHAN QUACH
Drywall Nailing 11/5/2020 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 11/12/2020 Partial Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 11/17/2020 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 11/18/2020 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/20/2020 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/23/2020 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/25/2020 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/11/2020 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 12/15/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 12/15/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 12/16/2020 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 12/17/2020 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/23/2020 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 12/24/2020 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 12/28/2020 Not Ready for Inspection HAMID PISHEHVAR
Light Gage Steel Frame 1/7/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 1/13/2021 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 1/15/2021 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 1/22/2021 Partial Approval DANNY RODRIGUEZ
T-Bar Ceiling 1/29/2021 Not Ready for Inspection JOHN KITCKO
T-Bar Ceiling 2/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 2/8/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 2/10/2021 Partial Approval DANNY RODRIGUEZ
Final 2/24/2021 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/24/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 2/24/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/24/2021 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 2/24/2021 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/24/2021 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 2/24/2021 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/24/2021 Partial Inspection DANNY RODRIGUEZ
Wood Frame 2/24/2021 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 2/25/2021 Not Ready for Inspection DANNY RODRIGUEZ
Final 2/26/2021 Partial Inspection DANNY RODRIGUEZ
Smoke Detectors 2/26/2021 Partial Approval DANNY RODRIGUEZ
Final 3/2/2021 Partial Inspection DANNY RODRIGUEZ
Smoke Detectors 3/2/2021 Partial Approval DANNY RODRIGUEZ
Final 3/3/2021 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/3/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 3/3/2021 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 3/3/2021 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/3/2021 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 3/3/2021 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/3/2021 Partial Inspection DANNY RODRIGUEZ
Wood Frame 3/3/2021 Not Ready for Inspection DANNY RODRIGUEZ
Final 3/4/2021 Partial Inspection DANNY RODRIGUEZ
Final 3/9/2021 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/9/2021 Approved DANNY RODRIGUEZ
Green Building Final 3/9/2021 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 3/9/2021 Approved DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/9/2021 SGSOV Approved DANNY RODRIGUEZ
Smoke Detectors 3/9/2021 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/9/2021 Approved DANNY RODRIGUEZ
Wood Frame 3/9/2021 Approved DANNY RODRIGUEZ
Final 4/9/2021 Partial Inspection DANNY RODRIGUEZ
Final 4/14/2021 Not Ready for Inspection DANNY RODRIGUEZ
Final 4/16/2021 OK to Issue CofO DANNY RODRIGUEZ