2869 S CORNING ST 90034
Certificate Information: 2869 S CORNING ST 90034
- Application / Permit
- 17010-20000-02981
- Plan Check / Job No.
- B17VN11435
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 90' X 30'6" THREE STORY 3-UNIT APARTMENT, RECREATION ROOM WITH BASEMENT PARKING
- Permit Issued
- Issued on 8/22/2022
- Issuing Office
- Valley
- Current Status
- Issued on 8/22/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/2/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2017 | JEFFREY TANGONAN |
| Corrections Issued | 8/29/2017 | JEFFREY TANGONAN |
| Disabled Access Plans Picked Up | 8/30/2017 | APPLICANT |
| Green Plans Picked Up | 8/30/2017 | APPLICANT |
| Quality Review Completed | 9/1/2017 | GUANG MIN TUNG |
| Applicant returned to address corrections | 10/10/2018 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 6/15/2022 | JEFFREY TANGONAN |
| Plan Check Approved | 8/4/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 8/11/2022 | APPLICANT |
| Issued | 8/22/2022 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 2/9/2018 | OLLIE CARTER |
| Address approval | Cleared | 3/2/2018 | BRIAN KELLY |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2018 | BRIAN KELLY |
| Green Code | Cleared | 3/2/2018 | MICHAEL AYERS |
| Highway dedication | Cleared | 3/2/2018 | BRIAN KELLY |
| Hydrant and Access approval | Cleared | 3/2/2018 | JOHN DALLAS |
| Permit | Cleared | 3/2/2018 | BRIAN KELLY |
| Sewer availability | Cleared | 3/2/2018 | BRIAN KELLY |
| Fire Marshall Fire Life Safety | Cleared | 12/30/2019 | OSCAR SALGADO JR |
| Low Impact Development | Cleared | 4/19/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 5/2/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 8/22/2023 | Approved | DERRICK SPENCER |
| Pre-Inspection | 8/22/2023 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Not Ready | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 11/7/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Pre-Inspection | 11/7/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Special/Order Compliance | 11/7/2023 | Approved | DERRICK SPENCER |
| Grading Pre-Inspection | 12/15/2023 | Partial Inspection | DERRICK SPENCER |
| Pre-Inspection | 12/15/2023 | Partial Inspection | DERRICK SPENCER |
| Grading Pre-Inspection | 1/26/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 1/26/2024 | Approved | DERRICK SPENCER |
| Grading Pre-Inspection | 2/21/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 7/19/2024 | Approved | PAUL DAVIDSON |
| Special/Order Compliance | 7/30/2024 | Partial Inspection | FARHAD DADBIN |
| Special/Order Compliance | 7/30/2024 | Partial Inspection | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 8/13/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 8/13/2024 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Not Ready | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 8/19/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/19/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 8/20/2024 | Conditional Approval | FARHAD DADBIN |
| Deputy Reinf. Masonry | 9/20/2024 | Approved | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 9/20/2024 | Partial Approval | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 10/8/2024 | Approved | AMANUEL BERHE |
| Footing/Foundation/Slab | 10/23/2024 | No Access for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 10/25/2024 | Partial Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Conditional Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Special/Order Compliance | 1/5/2026 | Partial Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 2/6/2026 | Partial Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 3/20/2026 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 3/24/2026 | Partial Approval | PAUL DAVIDSON |