19959 W PARTHENIA ST 91324

Certificate Information: 19959 W PARTHENIA ST 91324

Application / Permit
17010-20000-02851
Plan Check / Job No.
B17VN10805
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY ACCESSORY DWELLING UNIT PER AB 494 & AB 229 PER WFPP
Permit Issued
Issued on 2/14/2018
Issuing Office
Valley
Current Status
CofO Issued on 2/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2017 APPLICANT
Assigned to Plan Check Engineer 8/17/2017 NILOOFAR MEHRAIN
Green Plans Picked Up 8/17/2017 APPLICANT
Corrections Issued 9/1/2017 NILOOFAR MEHRAIN
Quality Review Completed 9/1/2017 GUANG MIN TUNG
Building Plans Picked Up 10/12/2017 APPLICANT
Plan Check Approved 2/14/2018 NILOOFAR MEHRAIN
Issued 2/14/2018 LADBS
CofO in Progress 2/14/2022 JEFFREY PARD
CofO Issued 2/22/2022 JOHN JANSON
Permit Finaled 2/22/2022 JOHN JANSON

Permit Application Clearance Information

Miscellaneous Cleared 2/8/2018 TOM HENRY
Address approval Cleared 2/13/2018 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 2/13/2018 KAYLA PEJI
Green Code Cleared 2/13/2018 MICHAEL AYERS
Hydrant and Access approval Cleared 2/13/2018 JOHN DALLAS
Low Impact Development Cleared 2/13/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 2/13/2018 KAYLA PEJI
Sewer availability Cleared 2/13/2018 KAYLA PEJI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/8/2019 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 2/8/2019 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 2/8/2019 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 4/3/2019 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 4/3/2019 Partial Approval VINCENT HANLEY
PLUMBING-Rough 4/3/2019 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 4/12/2019 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 4/12/2019 Approved VINCENT HANLEY
PLUMBING-Rough 4/12/2019 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/21/2019 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 6/21/2019 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/15/2019 Partial Approval JOHN COLEMAN
ELECTRICAL-Rough 10/22/2019 Approved VINCENT HANLEY
HVAC-Rough 10/22/2019 Approved VINCENT HANLEY
PLUMBING-Rough 10/22/2019 Approved VINCENT HANLEY
Sewer 11/27/2019 Approved VINCENT HANLEY
HVAC-Rough 1/16/2020 Approved VINCENT HANLEY
Underground Mechanical 1/16/2020 Approved VINCENT HANLEY
Drywall Nailing 3/12/2020 Approved DAVID SANDOVAL
Green Building Rough 3/12/2020 Approved DAVID SANDOVAL
Interior/Exterior Lathing 3/12/2020 Partial Approval DAVID SANDOVAL
Interior/Exterior Lathing 8/21/2020 Approved JEFFREY PARD
Service/Power Release 8/21/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Final 3/4/2021 Not Ready for Inspection JEFFREY PARD
HVAC-Final 3/4/2021 Not Ready for Inspection JEFFREY PARD
PLUMBING-Final 3/4/2021 Not Ready for Inspection JEFFREY PARD
Special/Order Compliance 3/4/2021 Corrections Issued JEFFREY PARD
BUILDING-Rough-Frame 8/30/2021 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Final 8/30/2021 Not Ready for Inspection JEFFREY PARD
Final 8/30/2021 Corrections Issued JEFFREY PARD
Gas Test 8/30/2021 Approved JEFFREY PARD
Green Building Final 8/30/2021 Corrections Issued JEFFREY PARD
HVAC-Final 8/30/2021 Corrections Issued JEFFREY PARD
PLUMBING-Final 8/30/2021 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 8/30/2021 SGSOV Approved JEFFREY PARD
Service/Power Release 8/30/2021 Not Ready for Inspection JEFFREY PARD
Smoke Detectors 8/30/2021 Approved JEFFREY PARD
Verify Sprinkler Sign Off 8/30/2021 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 2/10/2022 Approved JEFFREY PARD
ELECTRICAL-Final 2/10/2022 Approved JEFFREY PARD
Final 2/10/2022 OK to Issue CofO JEFFREY PARD
Green Building Final 2/10/2022 Approved JEFFREY PARD
HVAC-Final 2/10/2022 Approved JEFFREY PARD
PLUMBING-Final 2/10/2022 Approved JEFFREY PARD
Service/Power Release 2/10/2022 Approved JEFFREY PARD
Verify Sprinkler Sign Off 2/10/2022 Approved JEFFREY PARD