11402 W TALIA CT 91602
Certificate Information: 11402 W TALIA CT 91602
- Application / Permit
- 17010-20000-02639
- Plan Check / Job No.
- B17VN09998
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- "Small lot subdivision pursuant to Tentative Tract No./Preliminary Parcel Map No. VTT-74064-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded." NEW 3-STORY 37'-0" X 22'-1" SFD WITH ATT. 2-CAR GAR. & ROOF DECK; FIRE SPRINKLERS REQ'D THROUGH-OUT (PER VTT-74064-SL).
- Permit Issued
- Issued on 5/14/2018
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 11/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2017 | ALEXANDER SBARDELLATI |
| Corrections Issued | 8/7/2017 | ALEXANDER SBARDELLATI |
| Quality Review Completed | 8/9/2017 | CHON CHIO KUO |
| Building Plans Picked Up | 8/29/2017 | APPLICANT |
| Green Plans Picked Up | 8/29/2017 | APPLICANT |
| Applicant returned to address corrections | 9/7/2017 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 9/19/2017 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 9/22/2017 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 11/3/2017 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 12/22/2017 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 1/17/2018 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 1/23/2018 | ALEXANDER SBARDELLATI |
| Plan Check Approved | 1/26/2018 | ALEXANDER SBARDELLATI |
| Issued | 5/14/2018 | LADBS |
| CofO in Progress | 6/26/2020 | JOSEPH SAGEN |
| CofO Issued-Status Void | 6/30/2020 | DONALD SUNSERI |
| Permit Finaled-Status Void | 6/30/2020 | DONALD SUNSERI |
| Re-Activate Permit | 11/16/2020 | ERIC JAKEMAN |
| Permit Finaled | 11/17/2020 | ERIC JAKEMAN |
| CofO Corrected | 11/17/2020 | ERIC JAKEMAN |
| Permit Finaled | 11/17/2020 | ERIC JAKEMAN |
Permit Application Clearance Information
| Green Code | Cleared | 9/13/2017 | MICHAEL AYERS |
| CPC | Cleared | 9/28/2017 | EDBER MACEDO |
| ZA Case | Cleared | 9/28/2017 | EDBER MACEDO |
| ZA Case | Cleared | 9/28/2017 | EDBER MACEDO |
| ZA Case | Cleared | 9/28/2017 | EDBER MACEDO |
| ZI | Cleared | 9/28/2017 | EDBER MACEDO |
| Hydrant and Access approval | Cleared | 10/4/2017 | JOHN DALLAS |
| Miscellaneous | Cleared | 10/18/2017 | DURRE SHAMSI |
| Low Impact Development | Cleared | 11/7/2017 | SAM NAVID |
| Frnt yard landscape/Water mgmt | Cleared | 12/8/2017 | FIPE LEILUA |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2017 | MARKOS PEREZ-BRAN |
| Permit | Cleared | 12/15/2017 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 12/15/2017 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 12/15/2017 | MARKOS PEREZ-BRAN |
| Address approval | Cleared | 12/20/2017 | HOWARD COOPER |
| Highway dedication | Cleared | 12/21/2017 | KENNETH PHAM |
| Miscellaneous | Cleared | 12/21/2017 | KENNETH PHAM |
| Disturb/Remove Protected Trees | Cleared | 1/12/2018 | LUIS TORRES |
| Miscellaneous | Cleared | 1/18/2018 | FIPE LEILUA |
| Miscellaneous | Cleared | 1/18/2018 | FIPE LEILUA |
| Tract Map conditions | Cleared | 1/18/2018 | FIPE LEILUA |
| ZI | Cleared | 1/18/2018 | FIPE LEILUA |
| Miscellaneous | Cleared | 1/25/2018 | DENNIS CHEW |
Contact Information
| Architect | Stark, Anthony Alan; Lic. No.: C18639 | 6240 WINANS DRIVE LOS ANGELES, CA 90068 |
| Contractor | Owner-Builder | , |
| Engineer | Fox, Mark Dean; Lic. No.: L6892 | 25296 AVENIDA DORENA NEWHALL, CA 91321 |
| Engineer | Mahn, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Oruncakciel, Sayat; Lic. No.: C77182 | 18246 ANNA LANE TARZANA, CA 91356 |
Inspector Information
| JOSEPH SAGEN, (818) 774-4353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/13/2018 | Not Ready for Inspection | DONALD SUNSERI |
| Excavation/Setback/Form/Re-Bar | 6/22/2018 | Partial Approval | DONALD SUNSERI |
| Footing/Foundation/Slab | 6/22/2018 | Partial Approval | DONALD SUNSERI |
| Underground Mechanical | 6/22/2018 | Approved | DONALD SUNSERI |
| Footing/Foundation/Slab | 6/29/2018 | Approved | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2018 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2018 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2018 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2018 | Corrections Issued | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2018 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2018 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2018 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2018 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2018 | Approved | BRUCE ROZAK |
| ELECTRICAL-Rough | 12/3/2018 | Approved | JOHN KIDWELL |
| HVAC-Rough | 12/5/2018 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/28/2018 | Approved | JOHN KIDWELL |
| Green Building Rough | 12/28/2018 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 12/28/2018 | Not Ready for Inspection | JOHN KIDWELL |
| MERV13>=Rough | 12/28/2018 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 12/28/2018 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 12/28/2018 | Approved | JOHN KIDWELL |
| Drywall Nailing | 1/23/2019 | Approved | JOHN KIDWELL |
| Insulation | 1/23/2019 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/23/2019 | Approved | JOHN KIDWELL |
| Shower Pan | 2/12/2019 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/27/2019 | Approved | DONALD SUNSERI |
| Underground Mechanical | 10/4/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| Underground Mechanical | 10/8/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| Underground Mechanical | 1/17/2020 | Partial Approval | JOSEPH SAGEN |
| Gas Test | 2/21/2020 | Approved | JOSEPH SAGEN |
| Service/Power Release | 2/21/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| SGSOV-Seismic Gas S/O Valve | 2/24/2020 | SGSOV Approved | JOSEPH SAGEN |
| Service/Power Release | 2/24/2020 | Approved | JOSEPH SAGEN |
| Service/Power Release | 3/18/2020 | Approved | JOSEPH SAGEN |
| ELECTRICAL-Final | 5/27/2020 | Approved | JOSEPH SAGEN |
| HVAC-Final | 5/27/2020 | Approved | JOSEPH SAGEN |
| PLUMBING-Final | 5/27/2020 | Approved | JOSEPH SAGEN |
| Final | 6/11/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| Green Building Final | 6/11/2020 | Approved | JOSEPH SAGEN |
| MERV13>=Final | 6/11/2020 | Approved | JOSEPH SAGEN |
| Smoke Detectors | 6/11/2020 | Approved | JOSEPH SAGEN |
| Final | 6/26/2020 | OK to Issue CofO | JOSEPH SAGEN |