521 N GRAMERCY PL 90004
Certificate Information: 521 N GRAMERCY PL 90004
- Application / Permit
- 17010-20000-02344
- Plan Check / Job No.
- B17VN08876
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 19 UNIT APT BLDG WITH PARKING ON GRADE. COMPLY WITHDEPARTMENT ORDER effective date 12/15/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 3/7/2018
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 4/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2017 | RODNEY SAMIIAN |
| Corrections Issued | 7/14/2017 | RODNEY SAMIIAN |
| Building Plans Picked Up | 7/21/2017 | APPLICANT |
| Disabled Access Plans Picked Up | 7/21/2017 | APPLICANT |
| Green Plans Picked Up | 7/21/2017 | APPLICANT |
| Quality Review Completed | 7/24/2017 | GUANG MIN TUNG |
| Applicant returned to address corrections | 7/31/2017 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 8/17/2017 | RODNEY SAMIIAN |
| Plan Check Approved | 1/24/2018 | RODNEY SAMIIAN |
| Issued | 3/7/2018 | LADBS |
| CofO in Progress | 3/25/2022 | DANIEL MC AULIFFE |
| CofO Issued-Status Void | 3/25/2022 | TERRY HERR |
| Permit Finaled-Status Void | 3/25/2022 | TERRY HERR |
| Re-Activate Permit | 4/1/2022 | ERNESTO CORRAL |
| Permit Finaled | 4/1/2022 | ERNESTO CORRAL |
| CofO Corrected | 4/1/2022 | ERNESTO CORRAL |
| Permit Finaled | 4/1/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2017 | FATIMA GUERRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2017 | FATIMA GUERRA |
| Highway dedication | Cleared | 8/10/2017 | FATIMA GUERRA |
| Sewer availability | Cleared | 8/10/2017 | FATIMA GUERRA |
| Permit | Cleared | 8/24/2017 | FATIMA GUERRA |
| Frnt yard landscape/Water mgmt | Cleared | 8/28/2017 | DENNIS CHEW |
| Opn space landscape/Water mgmt | Cleared | 8/28/2017 | DENNIS CHEW |
| Hydrant and Access approval | Cleared | 8/31/2017 | JOHN CONNEALLY |
| Fire Marshall Fire Life Safety | Cleared | 9/6/2017 | OSCAR SALGADO JR |
| DAS Clearance | Cleared | 9/28/2017 | RODNEY SAMIIAN |
| Low Impact Development | Cleared | 10/6/2017 | IDA MEISAMI-FARD |
| Green Code | Cleared | 10/17/2017 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 12/28/2017 | RAVIL MANAPOV |
| Building over 3-story or 36-ft | Cleared | 1/24/2018 | CALOSHA APPROVED |
Contact Information
| Architect | Ghafoori-Tabrizi, Kamran; Lic. No.: C20369 | 21731 AMBAR DRIVE WOODLAND HILLS, CA 91364 |
| Contractor | Lumar Corporation; Lic. No.: 1027838-B | 11420 SANTA MONICA BLVD LOS ANGELES,, CA 90025 |
| Engineer | Dejban, Masoud; Lic. No.: S2521 | 17200 VENTURA BLVD STE 213A ENCINO, CA 91316 |
| Engineer | Minas, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/13/2018 | No Access for Inspection | TED RIES |
| Pre-Inspection | 10/25/2018 | Approved | JEFF BYTHEWAY |
| Excavation/Setback/Form/Re-Bar | 2/15/2019 | Partial Approval | JEFF BYTHEWAY |
| Excavation/Setback/Form/Re-Bar | 4/5/2019 | Not Ready for Inspection | LESLIE TRUJILLO |
| Footing/Foundation/Slab | 4/5/2019 | No Access for Inspection | LESLIE TRUJILLO |
| Excavation/Setback/Form/Re-Bar | 9/12/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Pre-Inspection | 9/12/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/1/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/15/2020 | Approved | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/16/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/17/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/21/2020 | Approved | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/22/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Wood Construction | 11/2/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Wood Construction | 12/23/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 3/25/2022 | Approved | DANIEL MC AULIFFE |
| Final | 3/25/2022 | Conditional Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 3/25/2022 | Approved | DANIEL MC AULIFFE |
| Green Building Final | 3/25/2022 | Approved | DANIEL MC AULIFFE |
| Green Building Rough | 3/25/2022 | Approved | DANIEL MC AULIFFE |
| Reinforced Concrete Frame | 3/25/2022 | Approved | DANIEL MC AULIFFE |
| Reinforced Masonry Frame | 3/25/2022 | Approved | DANIEL MC AULIFFE |
| SGSOV-Seismic Gas S/O Valve | 3/25/2022 | SGSOV Approved | DANIEL MC AULIFFE |
| Smoke Detectors | 3/25/2022 | Approved | DANIEL MC AULIFFE |
| Structural Steel Frame | 3/25/2022 | Approved | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 3/25/2022 | Approved | DANIEL MC AULIFFE |
| Wood Frame | 3/25/2022 | Approved | DANIEL MC AULIFFE |