- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2017 | CHON CHIO KUO |
| Corrections Issued | 7/18/2017 | CHON CHIO KUO |
| Green Plans Picked Up | 7/18/2017 | APPLICANT |
| Quality Review Completed | 7/19/2017 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 8/4/2017 | APPLICANT |
| Applicant returned to address corrections | 8/29/2018 | CHON CHIO KUO |
| Applicant returned to address corrections | 10/30/2018 | CHON CHIO KUO |
| Applicant returned to address corrections | 11/13/2018 | CHON CHIO KUO |
| Applicant returned to address corrections | 11/20/2018 | CHON CHIO KUO |
| Applicant returned to address corrections | 12/4/2018 | CHON CHIO KUO |
| Applicant returned to address corrections | 12/13/2018 | CHON CHIO KUO |
| Applicant returned to address corrections | 12/26/2018 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/1/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/31/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 2/25/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 4/28/2022 | COLIN LOREDO |
| Plan Check Approved | 7/12/2022 | COLIN LOREDO |
| Issued | 9/7/2022 | APPLICANT |
| CofO in Progress | 4/25/2025 | JOHN HAYES |
| CofO in Progress | 5/20/2025 | SEAN WIRCH |
| No Progress | 5/20/2025 | SEAN WIRCH |
| Permit Finaled | 8/22/2025 | JOHN JANSON |
| CofO Issued | 8/22/2025 | JOHN JANSON |
| Permit Finaled | 8/22/2025 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 4/19/2018 | MITESH PATEL |
| Green Code | Cleared | 7/11/2018 | ROLLIN GETTLE III |
| BHO/Hillside ordinance | Cleared | 11/30/2018 | APEKSHYA BAJRACHARYA |
| BHO/Hillside ordinance | Cleared | 11/30/2018 | APEKSHYA BAJRACHARYA |
| BHO/Hillside ordinance | Cleared | 11/30/2018 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2018 | APEKSHYA BAJRACHARYA |
| Permit | Cleared | 11/30/2018 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 11/30/2018 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 11/30/2018 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 1/3/2019 | JOHN DALLAS |
| Building over 3-story or 36-ft | Cleared | 5/1/2019 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 5/1/2019 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 2/25/2020 | CHON CHIO KUO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abrahamian, Zaven; Lic. No.: C41672 | 237 S LAMER ST BURBANK, CA 91506 |
| Engineer | Burnazyan, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/8/2022 | Partial Approval | PETER FOLLING |
| Deputy Reinf. Concrete | 12/9/2022 | Conditional Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 12/23/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 12/27/2022 | No Access for Inspection | PETER FOLLING |
| Deputy Reinf. Concrete | 12/28/2022 | No Access for Inspection | PETER FOLLING |
| Deputy Other (see comments) | 1/18/2023 | No Access for Inspection | PETER FOLLING |
| Deputy Reinf. Concrete | 1/18/2023 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 1/24/2023 | Approved | PETER FOLLING |
| Deputy Reinf. Concrete | 1/25/2023 | No Access for Inspection | PETER FOLLING |
| Deputy Reinf. Concrete | 2/1/2023 | No Access for Inspection | PETER FOLLING |
| Deputy Reinf. Concrete | 2/8/2023 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 2/17/2023 | Partial Approval | SEAN WIRCH |
| Deputy Reinf. Concrete | 2/21/2023 | Conditional Approval | JUSTIN HAWLEY |
| Deputy Reinf. Concrete | 3/28/2023 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 4/10/2023 | Partial Approval | PETER FOLLING |
| Deputy Reinf. Concrete | 4/12/2023 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 4/19/2023 | Partial Approval | PETER FOLLING |
| Deputy Reinf. Concrete | 4/20/2023 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 4/28/2023 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 4/28/2023 | Partial Approval | PETER FOLLING |
| Deputy Reinf. Concrete | 5/1/2023 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 5/26/2023 | Approved | SEAN WIRCH |
| Wood Frame | 5/26/2023 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Partial Approval | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Partial Approval | PETER FOLLING |
| Sewer | 10/31/2023 | Approved | PETER FOLLING |
| HVAC-Rough | 11/6/2023 | Corrections Issued | PETER FOLLING |
| Deputy Wood Construction | 11/21/2023 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2023 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/14/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/27/2023 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 12/27/2023 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 12/27/2023 | Approved | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 12/27/2023 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | Corrections Issued | MORRIS JACKSON |
| Insulation | 1/8/2024 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/16/2024 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 1/22/2024 | No Access for Inspection | MORRIS JACKSON |
| Drywall Nailing | 1/23/2024 | Approved | MORRIS JACKSON |
| Shower Pan | 3/6/2024 | Approved | MORRIS JACKSON |
| Deputy Reinf. Concrete | 5/8/2024 | Conditional Approval | MORRIS JACKSON |
| Deputy Reinf. Concrete | 6/18/2024 | Conditional Approval | JOHN HAYES |
| Insulation | 1/3/2025 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 3/7/2025 | Corrections Issued | JOHN HAYES |
| Service/Power Release | 3/10/2025 | Approved | SEAN WIRCH |
| Gas Test | 3/24/2025 | Corrections Issued | JOHN COLEMAN |
| HVAC-Final | 3/24/2025 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 3/26/2025 | Corrections Issued | JOHN COLEMAN |
| Gas Test | 3/26/2025 | Approved | JOHN COLEMAN |
| PLUMBING-Final | 3/26/2025 | Partial Inspection | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 3/26/2025 | SGSOV Approved | JOHN COLEMAN |
| Smoke Detectors | 3/26/2025 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 4/9/2025 | Approved | JOHN HAYES |
| Final | 4/9/2025 | Corrections Issued | JOHN HAYES |
| Green Building Final | 4/9/2025 | Approved | JOHN HAYES |
| Reinforced Masonry Frame | 4/9/2025 | Approved | JOHN HAYES |
| Final | 4/24/2025 | OK to Issue CofO | JOHN HAYES |