14612 W CALVERT ST #1 - #19 91411

Certificate Information: 14612 W CALVERT ST #1 - #19 91411

Application / Permit
17010-20000-02238
Plan Check / Job No.
B17VN08326
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY 19 UNIT APARTMENT WITH STREET LEVEL GARAGE.
Permit Issued
Issued on 5/31/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2017 APPLICANT
Assigned to Plan Check Engineer 6/22/2017 CHON CHIO KUO
Corrections Issued 6/26/2017 CHON CHIO KUO
Disabled Access Plans Picked Up 6/27/2017 APPLICANT
Green Plans Picked Up 6/27/2017 APPLICANT
Quality Review Completed 6/28/2017 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 6/28/2017 APPLICANT
Applicant returned to address corrections 7/28/2017 CHON CHIO KUO
Applicant returned to address corrections 9/5/2017 CHON CHIO KUO
Applicant returned to address corrections 10/11/2017 CHON CHIO KUO
Applicant returned to address corrections 1/12/2018 CHON CHIO KUO
Plan Check Approved 4/16/2018 CHON CHIO KUO
Issued 5/31/2018 LADBS
TCO Issued (Expire Date: 12-14-2020) 6/17/2020 JEFFREY DURAN
TCO Issued (Expire Date: 06-06-2021) 12/8/2020 JEFFREY DURAN
CofO in Progress 4/29/2021 JEFFREY DURAN
No Progress 4/29/2021 JEFFREY DURAN
CofO in Progress 5/26/2021 JEFFREY DURAN
CofO Issued 6/9/2021 RICKEY JACKSON
Permit Finaled 6/9/2021 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 8/29/2017 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/29/2017 HISASHI KOBAYAKAWA
Permit Cleared 8/29/2017 HISASHI KOBAYAKAWA
Sewer availability Cleared 8/29/2017 HISASHI KOBAYAKAWA
Highway dedication Cleared 10/17/2017 LEE GUILBEAUX
Hydrant and Access approval Cleared 12/5/2017 JOHN DALLAS
Green Code Cleared 12/11/2017 MICKEY YAMASHITA
DAS Clearance Cleared 12/14/2017 CHON CHIO KUO
Frnt yard landscape/Water mgmt Cleared 1/3/2018 DENNIS CHEW
Opn space landscape/Water mgmt Cleared 1/3/2018 DENNIS CHEW
Fire Marshall Fire Life Safety Cleared 1/22/2018 ANDREW KO
Low Impact Development Cleared 2/26/2018 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/20/2018 ANGEL SALCEDO
Building over 3-story or 36-ft Cleared 4/16/2018 CALOSHA APPROVED
Hold Cleared 6/25/2018 PRECY SANCHEZ

Contact Information

Architect Charles, Hefner; Lic. No.: C23963 1836 PARNELL AVE   #105    LOS ANGELES, CA 90025
Contractor Design Construction; Lic. No.: 840542-B 4401 WILLENS STREET #C      WOODLAND HILLS, CA 91364
Engineer Ertunga, Berkoz; Lic. No.: S2504 5530 CORBIN AVE   #355    TARZANA,, CA 91356

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/12/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 7/20/2018 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 7/24/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/25/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 7/30/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 7/31/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/1/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/2/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/3/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 8/3/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/6/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/8/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/10/2018 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/10/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Masonry 8/13/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/14/2018 Conditional Approval ROBERT COLE
Green Building Rough 8/14/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 8/14/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 8/14/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 8/15/2018 Approved JEFFREY DURAN
Reinforced Masonry Frame 8/15/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/16/2018 Approved JEFFREY DURAN
Reinforced Masonry Frame 8/16/2018 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 8/29/2018 Partial Approval JEFFREY DURAN
Masonry Wall/Backfill 9/6/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/7/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/12/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/13/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 9/13/2018 Partial Approval JEFFREY DURAN
Deputy Other (see comments) 9/17/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/17/2018 Conditional Approval JEFFREY DURAN
Green Building Rough 10/4/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 10/4/2018 Partial Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 10/4/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 10/15/2018 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 10/15/2018 Partial Inspection CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 10/17/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/19/2018 Conditional Approval JEFFREY DURAN
Green Building Rough 11/16/2018 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 11/16/2018 Not Ready for Inspection JEFFREY DURAN
Wood Frame 11/16/2018 Partial Approval JEFFREY DURAN
Green Building Rough 12/14/2018 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 12/14/2018 Not Ready for Inspection JEFFREY DURAN
Wood Frame 12/14/2018 Partial Approval JEFFREY DURAN
Green Building Rough 1/3/2019 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 1/3/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 1/3/2019 Partial Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 1/24/2019 Approved DANIEL VARNUM
Deputy Steel/Welding 2/7/2019 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 2/12/2019 Partial Inspection JEFFREY DURAN
Insulation 3/19/2019 Partial Approval JEFFREY DURAN
Wood Frame 4/16/2019 Conditional Approval CAMERON CHABAN
Green Building Rough 4/25/2019 Partial Inspection CAMERON CHABAN
Insulation 4/25/2019 Conditional Approval CAMERON CHABAN
Verify Sprinkler Sign Off 4/25/2019 Conditional Approval CAMERON CHABAN
Wood Frame 4/25/2019 Conditional Approval CAMERON CHABAN
Green Building Rough 5/6/2019 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 5/6/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 5/6/2019 Not Ready for Inspection JEFFREY DURAN
Green Building Rough 5/10/2019 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 5/10/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 5/10/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 5/16/2019 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/17/2019 Partial Approval JEFFREY DURAN
Green Building Rough 5/22/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 5/22/2019 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 5/22/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 5/22/2019 Partial Approval JEFFREY DURAN
Insulation 5/31/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 6/11/2019 Partial Approval JEFFREY DURAN
Green Building Rough 6/11/2019 Partial Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 7/22/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 7/24/2019 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 7/25/2019 Partial Inspection JEFFREY DURAN
Green Building Rough 7/30/2019 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 7/30/2019 Partial Approval JEFFREY DURAN
Wood Frame 7/30/2019 Partial Approval JEFFREY DURAN
Insulation 8/5/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 8/12/2019 Partial Approval JEFFREY DURAN
Green Building Rough 8/12/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 8/15/2019 Conditional Approval JOHN KITCKO
Green Building Rough 8/15/2019 Approved JOHN KITCKO
Wood Frame 8/15/2019 Conditional Approval JOHN KITCKO
Verify Sprinkler Sign Off 8/16/2019 Partial Approval JOHN KITCKO
Wood Frame 8/16/2019 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 8/20/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 8/20/2019 Partial Inspection JEFFREY DURAN
Wood Frame 8/21/2019 Partial Approval JEFFREY DURAN
Insulation 8/22/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 8/30/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 9/5/2019 Partial Approval DANIEL VARNUM
Insulation 9/5/2019 Partial Approval DANIEL VARNUM
Drywall Nailing 9/6/2019 Partial Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/10/2019 Conditional Approval JEFFREY DURAN
Drywall Nailing 9/17/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 9/19/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 9/30/2019 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 10/16/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 10/21/2019 Partial Approval JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 11/7/2019 SGSOV Not Ready JEFFREY DURAN
Drywall Nailing 11/13/2019 Not Ready for Inspection JEFFREY DURAN
Final 11/13/2019 Not Ready for Inspection JEFFREY DURAN
Footing/Foundation/Slab 11/13/2019 Not Ready for Inspection JEFFREY DURAN
Green Building Final 11/13/2019 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 11/13/2019 Not Ready for Inspection JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 11/13/2019 SGSOV Not Ready JEFFREY DURAN
Smoke Detectors 11/13/2019 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 11/13/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 11/13/2019 Partial Inspection JEFFREY DURAN
Drywall Nailing 12/5/2019 Not Ready for Inspection JEFFREY DURAN
Final 12/5/2019 Not Ready for Inspection JEFFREY DURAN
Footing/Foundation/Slab 12/5/2019 Not Ready for Inspection JEFFREY DURAN
Green Building Final 12/5/2019 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 12/5/2019 Not Ready for Inspection JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 12/5/2019 SGSOV Not Ready JEFFREY DURAN
Smoke Detectors 12/5/2019 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 12/5/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 12/5/2019 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 1/2/2020 Partial Inspection JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/22/2020 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 1/24/2020 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 1/24/2020 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 1/30/2020 Partial Approval JEFFREY DURAN
Masonry Wall/Backfill 1/30/2020 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 1/30/2020 Partial Inspection JEFFREY DURAN
Footing/Foundation/Slab 2/6/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 2/11/2020 Partial Inspection JEFFREY DURAN
Drywall Nailing 2/18/2020 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 2/26/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 2/28/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 3/23/2020 Partial Inspection JEFFREY DURAN
Final 3/25/2020 Not Ready for Inspection JEFFREY DURAN
Footing/Foundation/Slab 3/25/2020 Approved JEFFREY DURAN
Green Building Final 3/25/2020 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 3/25/2020 Not Ready for Inspection JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 3/25/2020 SGSOV Not Ready JEFFREY DURAN
Smoke Detectors 3/25/2020 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 3/25/2020 Not Ready for Inspection JEFFREY DURAN
Wood Frame 3/25/2020 Not Ready for Inspection JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 4/10/2020 SGSOV Not Ready JEFFREY DURAN
Grading Pre-Inspection 4/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 5/19/2020 Approved JEFFREY DURAN
Final 5/19/2020 Not Ready for Inspection JEFFREY DURAN
Green Building Final 5/19/2020 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 5/19/2020 Conditional Approval JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 5/19/2020 SGSOV Approved JEFFREY DURAN
Smoke Detectors 5/19/2020 Approved JEFFREY DURAN
Verify Sprinkler Sign Off 5/19/2020 Conditional Approval JEFFREY DURAN
Wood Frame 5/19/2020 Conditional Approval JEFFREY DURAN
Final 6/5/2020 Not Ready for Inspection HAMID PISHEHVAR
Green Building Final 6/5/2020 Not Ready for Inspection HAMID PISHEHVAR
Reinforced Concrete Frame 6/5/2020 Not Ready for Inspection HAMID PISHEHVAR
Verify Sprinkler Sign Off 6/5/2020 Not Ready for Inspection HAMID PISHEHVAR
Wood Frame 6/5/2020 Not Ready for Inspection HAMID PISHEHVAR
Final 6/10/2020 Not Ready for Inspection HAMID PISHEHVAR
Green Building Final 6/10/2020 Not Ready for Inspection HAMID PISHEHVAR
Reinforced Concrete Frame 6/10/2020 Not Ready for Inspection HAMID PISHEHVAR
Verify Sprinkler Sign Off 6/10/2020 Not Ready for Inspection HAMID PISHEHVAR
Wood Frame 6/10/2020 Not Ready for Inspection HAMID PISHEHVAR
Final 6/11/2020 Not Ready for Inspection JEFFREY DURAN
Green Building Final 6/11/2020 Approved JEFFREY DURAN
Reinforced Concrete Frame 6/11/2020 Approved JEFFREY DURAN
Verify Sprinkler Sign Off 6/11/2020 Approved JEFFREY DURAN
Wood Frame 6/11/2020 Approved JEFFREY DURAN
Final 6/12/2020 Not Ready for Inspection JEFFREY DURAN
Final 6/16/2020 Not Ready for Inspection JEFFREY DURAN
Green Building Final 6/16/2020 Approved JEFFREY DURAN
Special/Order Compliance 6/16/2020 Approved JEFFREY DURAN
Final 6/18/2020 Partial Approval HAMID PISHEHVAR
Special/Order Compliance 11/30/2020 Not Ready for Inspection RICKEY JACKSON
Special/Order Compliance 5/12/2021 Partial Inspection CAMERON CHABAN