7327 N HAZELTINE AVE LOT #9 91405

Certificate Information: 7327 N HAZELTINE AVE LOT #9 91405

Application / Permit
17010-20000-02166
Plan Check / Job No.
B17VN08090
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 3/20/2018
Issuing Office
Valley
Current Status
CofO Issued on 11/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2017 APPLICANT
Assigned to Plan Check Engineer 6/15/2017 NILOOFAR MEHRAIN
Corrections Issued 6/19/2017 NILOOFAR MEHRAIN
Green Plans Picked Up 6/19/2017 APPLICANT
Quality Review Completed 6/20/2017 GUANG MIN TUNG
Building Plans Picked Up 6/22/2017 APPLICANT
Applicant returned to address corrections 8/15/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/21/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/8/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/15/2018 NILOOFAR MEHRAIN
Plan Check Approved 2/15/2018 NILOOFAR MEHRAIN
Issued 3/20/2018 LADBS
CofO in Progress 11/9/2020 JOSEPH SAGEN
Permit Finaled 11/9/2020 DONALD SUNSERI
CofO Issued 11/9/2020 DONALD SUNSERI
Permit Finaled 11/9/2020 DONALD SUNSERI

Permit Application Clearance Information

Low Impact Development Cleared 8/23/2017 RYAN HUDSON
Tract Map conditions Cleared 8/23/2017 JESSE RAMOS
ZA Case Cleared 8/23/2017 JESSE RAMOS
ZA Case Cleared 8/23/2017 JESSE RAMOS
Address approval Cleared 9/12/2017 KENNETH PHAM
Miscellaneous Cleared 9/12/2017 KENNETH PHAM
Permit Cleared 9/12/2017 KENNETH PHAM
Roof/Waste drainage to street Cleared 9/12/2017 KENNETH PHAM
Eng Process Fee Ord 176,300 Cleared 10/4/2017 EDUARDO PEDROZA
Sewer availability Cleared 10/4/2017 EDUARDO PEDROZA
Hydrant and Access approval Cleared 10/17/2017 JOHN DALLAS
Highway dedication Cleared 11/1/2017 EDUARDO PEDROZA
Internal circulation Cleared 11/14/2017 DURRE SHAMSI
Disturb/Remove Protected Trees Cleared 11/30/2017 LUIS TORRES
"Q" conditions Cleared 2/5/2018 RICK TORRES
APC Cleared 2/5/2018 RICK TORRES
Tract Map conditions Cleared 2/5/2018 RICK TORRES
Green Code Cleared 2/23/2018 DAVID MATSON
Green Code Cleared 2/23/2018 NILOOFAR MEHRAIN
"T" removal Cleared 3/15/2018 ANNA VIDAL

Contact Information

Architect Bucilla, Greg G; Lic. No.: C26879 19782 MACARTHUR BLVD SUITE 270      IRVINE, CA 92612
Contractor Etco Homes Inc; Lic. No.: 879789-B 8447 WILSHIRE BLVD 400      BEVERLY HILLS, CA 902113209
Engineer Deihimi, Amir Hossein; Lic. No.: C78194 4400 CAMPUS DR      NEWPORT BEACH, CA 92660
Engineer Walter, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/20/2018 Approved DONALD SUNSERI
Deputy Reinf. Concrete 9/18/2018 Approved DONALD SUNSERI
Footing/Foundation/Slab 9/19/2018 Approved DONALD SUNSERI
Deputy Wood Construction 11/9/2018 Approved DONALD SUNSERI
Deputy Wood Construction 11/9/2018 Conditional Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/14/2018 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/29/2018 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/10/2019 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 8/15/2019 Not Ready for Inspection JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 9/4/2019 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Rough 9/4/2019 Approved JOSEPH SAGEN
ELECTRICAL-Rough 9/11/2019 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 9/13/2019 Partial Approval JOSEPH SAGEN
HVAC-Rough 9/13/2019 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 9/30/2019 Approved JOSEPH SAGEN
Green Building Rough 9/30/2019 Approved JOSEPH SAGEN
Verify Sprinkler Sign Off 9/30/2019 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 10/21/2019 Approved JOSEPH SAGEN
Drywall Nailing 10/21/2019 Approved JOSEPH SAGEN
Interior/Exterior Lathing 10/21/2019 Partial Approval JOSEPH SAGEN
Interior/Exterior Lathing 11/12/2019 Not Ready for Inspection JOSEPH SAGEN
Interior/Exterior Lathing 11/15/2019 Approved JOSEPH SAGEN
Underground Mechanical 4/24/2020 Partial Approval JOSEPH SAGEN
Service/Power Release 5/15/2020 Approved JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 6/9/2020 SGSOV Approved JOSEPH SAGEN
Gas Test 8/12/2020 Approved JOSEPH SAGEN
ELECTRICAL-Final 9/2/2020 Approved JOSEPH SAGEN
Final 9/2/2020 Partial Approval JOSEPH SAGEN
Green Building Final 9/2/2020 Approved JOSEPH SAGEN
HVAC-Final 9/2/2020 Approved JOSEPH SAGEN
PLUMBING-Final 9/2/2020 Approved JOSEPH SAGEN
Smoke Detectors 9/2/2020 Approved JOSEPH SAGEN
Final 9/16/2020 Not Ready for Inspection DONALD SUNSERI
ELECTRICAL-Final 11/6/2020 Approved JOSEPH SAGEN
Final 11/6/2020 OK to Issue CofO JOSEPH SAGEN
HVAC-Final 11/6/2020 Approved JOSEPH SAGEN
PLUMBING-Final 11/6/2020 Approved JOSEPH SAGEN