6656 N BALBOA BLVD 91406

Certificate Information: 6656 N BALBOA BLVD 91406

Application / Permit
17010-20000-01974
Plan Check / Job No.
B17VN07266
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW TYPE V-A 2 STORY 4-UNIT APARTMENT OVER TYPE V-A BASEMENT GARAGE
Permit Issued
Issued on 12/31/2018
Issuing Office
Valley
Current Status
CofO Issued on 5/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2017 APPLICANT
Assigned to Plan Check Engineer 6/15/2017 GUANG MIN TUNG
Disabled Access Plans Picked Up 6/16/2017 APPLICANT
Corrections Issued 6/19/2017 GUANG MIN TUNG
Green Plans Picked Up 6/20/2017 APPLICANT
Quality Review Completed 6/21/2017 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 6/21/2017 APPLICANT
Plan Check Approved 12/4/2017 GUANG MIN TUNG
Issued 12/31/2018 LADBS
CofO in Progress 4/28/2021 JEFFREY DURAN
CofO Issued 5/4/2021 RICKEY JACKSON
Permit Finaled 5/4/2021 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 6/22/2017 YESENIA DIAZ
Eng Process Fee Ord 176,300 Cleared 6/22/2017 YESENIA DIAZ
Low Impact Development Cleared 6/29/2017 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/30/2017 KENNETH PHAM
ZI Cleared 6/30/2017 ANNA VIDAL
Fire Marshall Fire Life Safety Cleared 7/18/2017 OSCAR SALGADO JR
Hydrant and Access approval Cleared 7/18/2017 JOHN DALLAS
DAS Clearance Cleared 8/7/2017 NORLITO MEDRANO
Highway dedication Cleared 8/17/2017 MARKOS PEREZ-BRAN
Permit Cleared 8/17/2017 MARKOS PEREZ-BRAN
Green Code Cleared 8/22/2017 MICHAEL AYERS
Sewer availability Cleared 8/25/2017 MARKOS PEREZ-BRAN

Contact Information

Architect Friedman, John Benjamin; Lic. No.: C9167 23427 BLYTHE STREET      WEST HILLS, CA 91304
Contractor Quillin Construction Corp; Lic. No.: 574175-B 23901 CALABASAS ROAD STE 2010      CALABASAS, CA 91302
Engineer Berkoz, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer Smith, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/1/2019 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 7/24/2019 Conditional Approval JAMES STEPHENS
Reinforced Concrete Frame 8/20/2019 Partial Approval JEFFREY DURAN
Structural Steel Frame 8/20/2019 Partial Inspection JEFFREY DURAN
Deputy Steel/Welding 9/11/2019 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/2/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/24/2019 Partial Approval JEFFREY DURAN
Masonry Wall/Backfill 1/17/2020 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Approved ROBERT DAVIS
Pre-Inspection 6/23/2020 Partial Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/9/2020 Approved HAMID PISHEHVAR
Green Building Rough 7/24/2020 Partial Approval HAMID PISHEHVAR
Verify Sprinkler Sign Off 7/24/2020 Partial Approval HAMID PISHEHVAR
Wood Frame 7/24/2020 Partial Approval HAMID PISHEHVAR
Insulation 8/3/2020 Approved HAMID PISHEHVAR
Drywall Nailing 8/12/2020 Approved HAMID PISHEHVAR
Interior/Exterior Lathing 8/20/2020 Approved JOHN DODGE
Interior/Exterior Lathing 10/8/2020 Approved ANDREW DORSO
Footing/Foundation/Slab 12/7/2020 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/15/2020 Approved HAMID PISHEHVAR
Piling/Pier/Caisson 1/15/2021 Partial Inspection HAMID PISHEHVAR
Reinforced Concrete Frame 1/15/2021 Partial Inspection HAMID PISHEHVAR
Final 4/1/2021 Partial Approval HAMID PISHEHVAR
Footing/Foundation/Slab 4/1/2021 Approved HAMID PISHEHVAR
Green Building Final 4/1/2021 Approved HAMID PISHEHVAR
Green Building Rough 4/1/2021 Approved HAMID PISHEHVAR
SGSOV-Seismic Gas S/O Valve 4/1/2021 SGSOV Approved HAMID PISHEHVAR
Smoke Detectors 4/1/2021 Approved HAMID PISHEHVAR
Verify Sprinkler Sign Off 4/1/2021 Approved HAMID PISHEHVAR
Wood Frame 4/1/2021 Approved HAMID PISHEHVAR
Final 4/19/2021 Partial Inspection CAMERON CHABAN
Final 4/22/2021 Partial Inspection CAMERON CHABAN