11825 W KLING ST 91607
Certificate Information: 11825 W KLING ST 91607
- Application / Permit
- 17010-20000-01902
- Plan Check / Job No.
- B17VN06957
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- (N) 1-STORY DETACHED ACCESSORY LIVING QUARTERS (NFPA-13D FIRE SPRINLERS THROUGHOUT)
- Permit Issued
- Issued on 5/12/2020
- Issuing Office
- Current Status
- CofO Issued on 1/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2017 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/30/2017 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/30/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 5/31/2017 | APPLICANT |
| Green Plans Picked Up | 5/31/2017 | APPLICANT |
| Applicant returned to address corrections | 12/7/2017 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/29/2018 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/26/2018 | NILOOFAR MEHRAIN |
| Plan Check Approved | 5/12/2020 | NILOOFAR MEHRAIN |
| Issued | 5/12/2020 | APPLICANT |
| CofO in Progress | 8/30/2023 | JACK KARGODORIAN |
| CofO in Progress | 12/28/2023 | JUAN VALENZUELA |
| CofO in Progress | 1/4/2024 | RUBEN SALAS |
| CofO Issued | 1/4/2024 | RUBEN SALAS |
| Permit Finaled | 1/4/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/6/2017 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2017 | KENNETH PHAM |
| Permit | Cleared | 7/6/2017 | KENNETH PHAM |
| Sewer availability | Cleared | 7/6/2017 | KENNETH PHAM |
| Low Impact Development | Cleared | 11/13/2017 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/13/2017 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 1/19/2018 | GILBERT URREA |
| Green Code | Cleared | 3/15/2018 | MICHAEL AYERS |
| Miscellaneous | Cleared | 3/21/2018 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 3/21/2018 | STEVEN WECHSLER |
| Specific Plan | Cleared | 3/21/2018 | STEVEN WECHSLER |
| Tract Map conditions | Cleared | 3/21/2018 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kamkar,, Albert; Lic. No.: C38311 | 12340 SANTA MONICA BLVD 236 SANTA MONICA, CA 90025 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/31/2020 | Approved | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 9/8/2020 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/24/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 10/24/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Rough | 10/24/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 10/24/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 10/24/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 11/18/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 11/18/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 11/18/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/18/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 11/18/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/20/2022 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 12/20/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/8/2023 | Approved | JACK KARGODORIAN |
| Final | 5/8/2023 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 5/8/2023 | Approved | JACK KARGODORIAN |
| Green Building Final | 5/8/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 5/8/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2023 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 5/8/2023 | Not Required | JACK KARGODORIAN |
| Smoke Detectors | 5/8/2023 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 5/8/2023 | Approved | JACK KARGODORIAN |
| Final | 6/12/2023 | Corrections Issued | JACK KARGODORIAN |
| Final | 6/26/2023 | Corrections Issued | DAVID MATSON |
| Final | 7/12/2023 | Conditional Approval | JACK KARGODORIAN |
| Final | 8/21/2023 | Partial Inspection | MISAEL ESPARZA |
| Final | 8/29/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 12/28/2023 | Corrections Issued | JUAN VALENZUELA |
| Final | 1/4/2024 | OK to Issue CofO | RUBEN SALAS |