11825 W KLING ST 91607
Certificate Information: 11825 W KLING ST 91607
- Application / Permit
- 17010-20000-01899
- Plan Check / Job No.
- B17VN06957
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 5/12/2020
- Issuing Office
- Current Status
- CofO Issued on 1/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2017 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/30/2017 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/30/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 5/31/2017 | APPLICANT |
| Green Plans Picked Up | 5/31/2017 | APPLICANT |
| Applicant returned to address corrections | 12/7/2017 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/29/2018 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/26/2018 | NILOOFAR MEHRAIN |
| Plan Check Approved | 5/12/2020 | NILOOFAR MEHRAIN |
| Issued | 5/12/2020 | APPLICANT |
| CofO in Progress | 8/30/2023 | JACK KARGODORIAN |
| CofO in Progress | 12/28/2023 | JUAN VALENZUELA |
| CofO in Progress | 1/4/2024 | RUBEN SALAS |
| Permit Finaled | 1/4/2024 | RUBEN SALAS |
| CofO Issued | 1/4/2024 | RUBEN SALAS |
| Permit Finaled | 1/4/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/6/2017 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2017 | KENNETH PHAM |
| Permit | Cleared | 7/6/2017 | KENNETH PHAM |
| Sewer availability | Cleared | 7/6/2017 | KENNETH PHAM |
| Low Impact Development | Cleared | 11/13/2017 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/13/2017 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 1/18/2018 | GILBERT URREA |
| Green Code | Cleared | 3/15/2018 | MICHAEL AYERS |
| Miscellaneous | Cleared | 3/21/2018 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 3/21/2018 | STEVEN WECHSLER |
| Specific Plan | Cleared | 3/21/2018 | STEVEN WECHSLER |
| Tract Map conditions | Cleared | 3/21/2018 | STEVEN WECHSLER |
| Hold | Cleared | 8/5/2020 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kamkar,, Albert; Lic. No.: C38311 | 12340 SANTA MONICA BLVD 236 SANTA MONICA, CA 90025 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/18/2020 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 8/21/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 8/26/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 8/31/2020 | Corrections Issued | DANIEL DREW |
| Footing/Foundation/Slab | 9/3/2020 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/8/2020 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/15/2020 | Conditional Approval | THOMAS FINNILA |
| Wood Frame | 9/30/2020 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 10/27/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 10/27/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2020 | Partial Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2020 | Partial Approval | DAVID MATSON |
| ELECTRICAL-Rough | 6/18/2021 | Partial Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/23/2021 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 6/23/2021 | Approved | THOMAS FINNILA |
| HVAC-Rough | 6/28/2021 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/1/2021 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 7/1/2021 | Conditional Approval | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 7/1/2021 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/9/2021 | No Access for Inspection | CHARLES POWELL |
| Shower Pan | 7/9/2021 | No Access for Inspection | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/2/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 8/2/2021 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/5/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Inspection | 8/9/2021 | Corrections Issued | THOMAS FINNILA |
| Wood Frame | 8/11/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2021 | Conditional Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 8/20/2021 | Conditional Approval | MICHAEL PELHAM |
| Interior/Exterior Lathing | 8/26/2021 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/2/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 9/2/2021 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 9/2/2021 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 9/2/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/7/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/17/2021 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 9/17/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/21/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 9/21/2021 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 9/21/2021 | Approved | THOMAS FINNILA |
| Insulation | 9/29/2021 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 10/14/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 11/2/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/2/2021 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/17/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 11/8/2022 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Final | 11/8/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 12/27/2022 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Final | 12/27/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 1/9/2023 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Final | 1/9/2023 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 2/2/2023 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Final | 2/2/2023 | Approved | JACK KARGODORIAN |
| Final | 5/8/2023 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 5/8/2023 | Approved | JACK KARGODORIAN |
| Green Building Final | 5/8/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 5/8/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2023 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 5/8/2023 | Corrections Issued | JACK KARGODORIAN |
| Smoke Detectors | 5/8/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 6/12/2023 | Approved | JACK KARGODORIAN |
| Final | 6/12/2023 | Corrections Issued | JACK KARGODORIAN |
| Final | 7/12/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Service/Power Release | 7/12/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 8/21/2023 | Partial Inspection | MISAEL ESPARZA |
| Service/Power Release | 8/21/2023 | Partial Inspection | MISAEL ESPARZA |
| Service/Power Release | 8/25/2023 | Approved | JACK KARGODORIAN |
| Final | 8/29/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 12/28/2023 | Corrections Issued | JUAN VALENZUELA |
| Final | 1/4/2024 | OK to Issue CofO | RUBEN SALAS |