7348 N DARBY PL 91335
Certificate Information: 7348 N DARBY PL 91335
- Application / Permit
- 17010-20000-01532
- Plan Check / Job No.
- B17VN05607
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 20' x 20' DETACHED TWO-CAR GARAGE. ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/7/2017
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 6/9/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/21/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2017 | SIAVOSH POURSABAHIAN |
| Corrections Issued | 4/21/2017 | ANDRES MATA |
| Plan Check Approved | 6/7/2017 | JENNIFER LEE |
| Issued | 6/7/2017 | LADBS |
| CofO in Progress | 6/9/2026 | ARUTYUN MADATYAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2017 | KENNETH PHAM |
| Hydrant and Access approval | Cleared | 4/21/2017 | JOHN DALLAS |
| Permit | Cleared | 4/21/2017 | KENNETH PHAM |
| Construction near power lines | Cleared | 5/15/2017 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/6/2017 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/7/2017 | YESENIA DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Shower Pan | 6/13/2017 | Not Ready for Inspection | FELIX ARROYO |
| Excavation/Setback/Form/Re-Bar | 6/15/2017 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 7/18/2017 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 7/18/2017 | Approved | SEAN WIRCH |
| Green Building Rough | 7/18/2017 | Approved | SEAN WIRCH |
| Drywall Nailing | 8/2/2017 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/2/2017 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 12/14/2017 | Approved | JOHN COLEMAN |
| Final | 12/14/2017 | Partial Inspection | JOHN COLEMAN |
| Footing/Foundation/Slab | 12/14/2017 | Approved | JOHN COLEMAN |
| Green Building Final | 12/14/2017 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 12/14/2017 | SGSOV Approved | JOHN COLEMAN |
| Smoke Detectors | 12/14/2017 | Approved | JOHN COLEMAN |
| Final | 6/4/2026 | Corrections Issued | ARUTYUN MADATYAN |
| Service/Power Release | 6/4/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 6/8/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| Service/Power Release | 6/8/2026 | Approved | ARUTYUN MADATYAN |