3217 N LEDGEWOOD DR 90068

Certificate Information: 3217 N LEDGEWOOD DR 90068

Application / Permit
17010-20000-01431
Plan Check / Job No.
B17VN05011
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 12/19/2017
Issuing Office
Valley
Current Status
Issued on 12/19/2017
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/11/2017 APPLICANT
Assigned to Plan Check Engineer 5/4/2017 NILOOFAR MEHRAIN
Green Plans Picked Up 5/17/2017 APPLICANT
Corrections Issued 5/26/2017 NILOOFAR MEHRAIN
Quality Review Completed 5/26/2017 GUANG MIN TUNG
Building Plans Picked Up 5/30/2017 APPLICANT
Applicant returned to address corrections 7/25/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/2/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/21/2017 NILOOFAR MEHRAIN
Plan Check Approved 12/19/2017 NILOOFAR MEHRAIN
Issued 12/19/2017 LADBS

Permit Application Clearance Information

Green Code Cleared 6/28/2017 ROLLIN GETTLE III
Address approval Cleared 7/3/2017 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/3/2017 CELINA MORENO
Hydrant and Access approval Cleared 7/3/2017 ROBERT DUFF
Low Impact Development Cleared 7/3/2017 MATTHEW JIMENEZ
BHO/Hillside ordinance Cleared 7/7/2017 CARLA VALLADARES
Sewer availability Cleared 7/10/2017 CELINA MORENO
BHO/Hillside ordinance Cleared 7/11/2017 ADRIAN SANCHEZ
Miscellaneous Cleared 7/13/2017 JESSE RAMOS
Miscellaneous Cleared 7/13/2017 JESSE RAMOS
Specific Plan Cleared 7/13/2017 JESSE RAMOS
ZI Cleared 7/13/2017 JESSE RAMOS
BHO/Hillside ordinance Cleared 10/30/2017 KAYLA PEJI
GPI Written Notices Cleared 10/30/2017 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 10/30/2017 NILOOFAR MEHRAIN
Roof/Waste drainage to street Cleared 10/30/2017 KAYLA PEJI
Permit Cleared 11/1/2017 KAYLA PEJI
Miscellaneous Cleared 11/2/2017 JOSEPH RHYU
Excavation more than 5-ft deep Cleared 12/19/2017 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Farag, Amgad N; Lic. No.: C74076 20833 KINGSCREST DR      SAUGUS, CA 91350
Engineer Salehipour, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Geologist Hill, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/31/2018 Partial Approval LUIS BARRALES
Excavation/Setback/Form/Re-Bar 9/10/2018 Partial Approval LUIS BARRALES
Footing/Foundation/Slab 10/12/2018 Partial Approval LUIS BARRALES
Footing/Foundation/Slab 10/23/2018 Partial Approval RONALD COWAN
PLUMBING-Rough 10/23/2018 Partial Approval RONALD COWAN
Footing/Foundation/Slab 11/15/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 11/27/2018 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 12/26/2018 Partial Approval LUIS BARRALES
Green Building Rough 12/26/2018 Not Ready for Inspection LUIS BARRALES
Verify Sprinkler Sign Off 12/26/2018 Not Ready for Inspection LUIS BARRALES
Excavation/Setback/Form/Re-Bar 1/10/2019 Partial Approval LUIS BARRALES
PLUMBING-Rough 1/11/2019 Partial Approval LUIS BARRALES
Floor/Roof Diaphrgm/Shear Wall 2/5/2019 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 2/20/2019 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/21/2019 Partial Approval RONALD COWAN
Special/Order Compliance 3/7/2019 No Access for Inspection RONALD COWAN
Special/Order Compliance 3/26/2019 Not Ready for Inspection RONALD COWAN
Rough-Elec/Plmb/HVAC 3/28/2019 Not Ready for Inspection RONALD COWAN
Special/Order Compliance 4/3/2019 Corrections Issued ELMER BLAND
PLUMBING-Rough 5/14/2019 No Access for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 6/17/2019 Conditional Approval LUIS BARRALES
ELECTRICAL-Rough 6/17/2019 Not Ready for Inspection LUIS BARRALES
Green Building Rough 6/17/2019 Not Ready for Inspection LUIS BARRALES
Interior/Exterior Lathing 6/17/2019 Not Ready for Inspection LUIS BARRALES
PLUMBING-Rough 6/17/2019 Not Ready for Inspection LUIS BARRALES
Verify Sprinkler Sign Off 6/17/2019 Not Ready for Inspection LUIS BARRALES
BUILDING-Rough-Frame 7/16/2019 Not Ready for Inspection LUIS BARRALES
Green Building Rough 7/16/2019 Not Ready for Inspection LUIS BARRALES
HVAC-Rough 7/16/2019 Approved LUIS BARRALES
PLUMBING-Rough 7/16/2019 Corrections Issued LUIS BARRALES
Rough-Elec/Plmb/HVAC 7/16/2019 Not Ready for Inspection LUIS BARRALES
Verify Sprinkler Sign Off 7/16/2019 Not Ready for Inspection LUIS BARRALES
BUILDING-Rough-Frame 8/6/2019 Not Ready for Inspection ROBERT CORNELL
Drywall Nailing 8/6/2019 Not Ready for Inspection ROBERT CORNELL
ELECTRICAL-Rough 8/6/2019 Not Ready for Inspection ROBERT CORNELL
Final 8/6/2019 Not Ready for Inspection ROBERT CORNELL
Footing/Foundation/Slab 8/6/2019 Not Ready for Inspection ROBERT CORNELL
Green Building Final 8/6/2019 Not Ready for Inspection ROBERT CORNELL
Green Building Rough 8/6/2019 Not Ready for Inspection ROBERT CORNELL
HVAC-Rough 8/6/2019 Not Ready for Inspection ROBERT CORNELL
Interior/Exterior Lathing 8/6/2019 Not Ready for Inspection ROBERT CORNELL
PLUMBING-Rough 8/6/2019 Not Ready for Inspection ROBERT CORNELL
Reinforced Concrete Frame 8/6/2019 Not Ready for Inspection ROBERT CORNELL
SGSOV-Seismic Gas S/O Valve 8/6/2019 SGSOV Not Ready ROBERT CORNELL
Service/Power Release 8/6/2019 Not Ready for Inspection ROBERT CORNELL
Smoke Detectors 8/6/2019 Not Ready for Inspection ROBERT CORNELL
Verify Sprinkler Sign Off 8/6/2019 Not Ready for Inspection ROBERT CORNELL
BUILDING-Rough-Frame 8/9/2019 Not Ready for Inspection ROBERT CORNELL
Drywall Nailing 8/9/2019 Not Ready for Inspection ROBERT CORNELL
ELECTRICAL-Final 8/9/2019 Not Ready for Inspection ROBERT CORNELL
Final 8/9/2019 Not Ready for Inspection ROBERT CORNELL
Footing/Foundation/Slab 8/9/2019 Not Ready for Inspection ROBERT CORNELL
Green Building Final 8/9/2019 Not Ready for Inspection ROBERT CORNELL
Green Building Rough 8/9/2019 Not Ready for Inspection ROBERT CORNELL
HVAC-Final 8/9/2019 Not Ready for Inspection ROBERT CORNELL
Interior/Exterior Lathing 8/9/2019 Not Ready for Inspection ROBERT CORNELL
PLUMBING-Final 8/9/2019 Not Ready for Inspection ROBERT CORNELL
Reinforced Concrete Frame 8/9/2019 Not Ready for Inspection ROBERT CORNELL
SGSOV-Seismic Gas S/O Valve 8/9/2019 SGSOV Not Ready ROBERT CORNELL
Service/Power Release 8/9/2019 Not Ready for Inspection ROBERT CORNELL
Smoke Detectors 8/9/2019 Not Ready for Inspection ROBERT CORNELL
Verify Sprinkler Sign Off 8/9/2019 Not Ready for Inspection ROBERT CORNELL
ELECTRICAL-Rough 8/14/2019 Not Ready for Inspection LUIS BARRALES
HVAC-Final 8/14/2019 Not Ready for Inspection LUIS BARRALES
PLUMBING-Rough 8/14/2019 Not Ready for Inspection LUIS BARRALES
Rough-Elec/Plmb/HVAC 8/15/2019 Not Ready for Inspection ROBERT CORNELL
PLUMBING-Rough 8/29/2019 Partial Inspection ROBERT CORNELL
ELECTRICAL-Rough 9/3/2019 Not Ready for Inspection LUIS BARRALES
Rough-Elec/Plmb/HVAC 9/3/2019 Not Ready for Inspection LUIS BARRALES
Rough-Elec/Plmb/HVAC 12/3/2019 Not Ready for Inspection LUIS BARRALES
BUILDING-Rough-Frame 12/27/2019 No Access for Inspection ROBERT CORNELL
Drywall Nailing 12/27/2019 No Access for Inspection ROBERT CORNELL
ELECTRICAL-Rough 12/27/2019 No Access for Inspection ROBERT CORNELL
Green Building Rough 12/27/2019 No Access for Inspection ROBERT CORNELL
Insulation 12/27/2019 No Access for Inspection ROBERT CORNELL
PLUMBING-Rough 12/27/2019 No Access for Inspection ROBERT CORNELL
Verify Sprinkler Sign Off 12/27/2019 No Access for Inspection ROBERT CORNELL
ELECTRICAL-Rough 1/14/2020 Not Ready for Inspection ROBERT CORNELL
HVAC-Rough 1/14/2020 Not Ready for Inspection ROBERT CORNELL
Interior/Exterior Lathing 1/14/2020 Corrections Issued ROBERT CORNELL
PLUMBING-Rough 1/14/2020 Not Ready for Inspection ROBERT CORNELL
Special/Order Compliance 3/25/2020 Approved ROBERT CORNELL
Special/Order Compliance 5/21/2020 Approved THOMAS LOGRASSO
Special/Order Compliance 6/5/2020 Approved BRAD BESCOS
Deputy Reinf. Concrete 9/8/2022 Conditional Approval JOAQUIN GREENOUGH
Special/Order Compliance 5/19/2025 Not Ready for Inspection CRAIG VAUGHAN
Special/Order Compliance 8/15/2025 Partial Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 9/17/2025 Corrections Issued BRIAN SULLIVAN
Pre-Inspection 9/17/2025 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 10/2/2025 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/6/2026 Partial Inspection SCOTT FINNILA
ELECTRICAL-Rough 4/6/2026 Partial Inspection SCOTT FINNILA
Green Building Rough 4/6/2026 Partial Inspection SCOTT FINNILA
HVAC-Rough 4/6/2026 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 4/6/2026 Partial Inspection SCOTT FINNILA
Special/Order Compliance 4/6/2026 Partial Inspection SCOTT FINNILA
Verify Sprinkler Sign Off 4/6/2026 Partial Inspection SCOTT FINNILA
ELECTRICAL-Rough 4/10/2026 Partial Inspection SCOTT FINNILA
HVAC-Rough 4/10/2026 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 4/10/2026 Partial Inspection SCOTT FINNILA
Pre-Inspection 4/10/2026 Partial Inspection SCOTT FINNILA
Special/Order Compliance 4/10/2026 Partial Inspection SCOTT FINNILA
Wood Frame 4/27/2026 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2026 Corrections Issued BRIAN SULLIVAN
Pre-Inspection 4/28/2026 Partial Inspection SCOTT FINNILA