6653 N GENTRY AVE 91606

Certificate Information: 6653 N GENTRY AVE 91606

Application / Permit
17010-20000-01215
Plan Check / Job No.
B17VN03896
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW 2-STORY SFD W/ ATT 2- CAR GARAGE. SEE COMMENTS. <sprinklers req'd throughout>
Permit Issued
Issued on 10/3/2017
Issuing Office
Valley
Current Status
CofO Issued on 1/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2017 APPLICANT
Assigned to Plan Check Engineer 4/27/2017 HAYATO TSUCHIYA
Green Plans Picked Up 5/5/2017 APPLICANT
Corrections Issued 5/9/2017 HAYATO TSUCHIYA
Quality Review Completed 5/10/2017 ABDUL CHEGENI
Building Plans Picked Up 5/10/2017 APPLICANT
Applicant returned to address corrections 7/6/2017 HAYATO TSUCHIYA
Plan Check Approved 9/12/2017 HAYATO TSUCHIYA
Issued 10/3/2017 LADBS
CofO in Progress 12/16/2025 JOSE AVILA
Permit Finaled 1/29/2026 RUBEN SALAS
CofO Issued 1/29/2026 RUBEN SALAS
Permit Finaled 1/29/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/6/2017 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/6/2017 MARKOS PEREZ-BRAN
Frnt yard landscape/Water mgmt Cleared 8/21/2017 DAISY BENICIA
Hydrant and Access approval Cleared 8/21/2017 JOHN DALLAS
Green Code Cleared 9/5/2017 DAVID MATSON
Low Impact Development Cleared 9/11/2017 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 9/12/2017 EDUARDO PEDROZA

Contact Information

Contractor Apple Home Developer Inc; Lic. No.: 955331-B 18921 DUKAS STREET      PORTER RANCH, CA 91326
Engineer Babakhanian, Oksen; Lic. No.: S3500 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/1/2017 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 12/5/2017 Not Ready for Inspection KEVIN BEAULIEU
Green Building Rough 12/5/2017 Not Ready for Inspection KEVIN BEAULIEU
Verify Sprinkler Sign Off 12/5/2017 Not Ready for Inspection KEVIN BEAULIEU
Footing/Foundation/Slab 12/11/2017 Approved KEVIN BEAULIEU
PLUMBING-Rough 12/14/2017 Partial Inspection WILLIAM KUEHN
Excavation/Setback/Form/Re-Bar 12/18/2017 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 12/20/2017 Not Ready for Inspection KEVIN BEAULIEU
Green Building Rough 12/20/2017 Approved KEVIN BEAULIEU
Verify Sprinkler Sign Off 12/20/2017 Not Ready for Inspection KEVIN BEAULIEU
BUILDING-Rough-Frame 12/27/2017 Not Ready for Inspection KEVIN BEAULIEU
PLUMBING-Rough 12/27/2017 Not Ready for Inspection KEVIN BEAULIEU
Verify Sprinkler Sign Off 12/27/2017 Not Ready for Inspection KEVIN BEAULIEU
PLUMBING-Rough 12/28/2017 Conditional Approval KEVIN BEAULIEU
Pre-Inspection 12/28/2017 Conditional Approval KEVIN BEAULIEU
BUILDING-Rough-Frame 2/2/2018 Partial Approval KEVIN BEAULIEU
Verify Sprinkler Sign Off 2/2/2018 Not Ready for Inspection KEVIN BEAULIEU
BUILDING-Rough-Frame 5/1/2018 Partial Approval KEVIN BEAULIEU
Verify Sprinkler Sign Off 5/1/2018 Not Ready for Inspection KEVIN BEAULIEU
BUILDING-Rough-Frame 6/4/2018 Partial Approval KEVIN BEAULIEU
ELECTRICAL-Rough 6/4/2018 Partial Approval KEVIN BEAULIEU
HVAC-Rough 6/4/2018 Partial Approval KEVIN BEAULIEU
PLUMBING-Rough 6/4/2018 Partial Approval KEVIN BEAULIEU
Verify Sprinkler Sign Off 6/4/2018 Partial Approval KEVIN BEAULIEU
BUILDING-Rough-Frame 6/14/2018 Not Ready for Inspection KEVIN BEAULIEU
Interior/Exterior Lathing 6/14/2018 Not Ready for Inspection KEVIN BEAULIEU
PLUMBING-Rough 6/14/2018 Approved KEVIN BEAULIEU
Shower Pan 6/14/2018 Approved KEVIN BEAULIEU
Verify Sprinkler Sign Off 6/14/2018 Not Ready for Inspection KEVIN BEAULIEU
BUILDING-Rough-Frame 6/19/2018 Conditional Approval KEVIN BEAULIEU
PLUMBING-Rough 6/19/2018 Approved KEVIN BEAULIEU
Drywall Nailing 7/6/2018 Approved KEVIN BEAULIEU
Interior/Exterior Lathing 8/1/2018 Approved KEVIN BEAULIEU
ELECTRICAL-Final 11/28/2018 Not Ready for Inspection KEVIN BEAULIEU
HVAC-Final 12/12/2018 Not Ready for Inspection BEAU COLLINS
PLUMBING-Final 12/12/2018 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 1/24/2019 Approved KEVIN BEAULIEU
Final 1/24/2019 Not Ready for Inspection KEVIN BEAULIEU
Green Building Final 1/24/2019 Approved KEVIN BEAULIEU
HVAC-Final 1/24/2019 Not Ready for Inspection KEVIN BEAULIEU
PLUMBING-Final 1/24/2019 Not Ready for Inspection KEVIN BEAULIEU
Reinforced Masonry Frame 1/24/2019 Approved KEVIN BEAULIEU
SGSOV-Seismic Gas S/O Valve 1/24/2019 SGSOV Approved KEVIN BEAULIEU
Service/Power Release 1/24/2019 Not Ready for Inspection KEVIN BEAULIEU
Smoke Detectors 1/24/2019 Approved KEVIN BEAULIEU
Verify Sprinkler Sign Off 1/24/2019 Approved KEVIN BEAULIEU
Service/Power Release 1/29/2019 Not Ready for Inspection KEVIN BEAULIEU
ELECTRICAL-Final 2/4/2019 Not Ready for Inspection KEVIN BEAULIEU
Service/Power Release 2/4/2019 Approved KEVIN BEAULIEU
Final 12/17/2019 Corrections Issued MISAEL ESPARZA
Final 8/18/2025 Partial Inspection JOSE AVILA
Final 10/30/2025 Corrections Issued JOSE AVILA
Final 12/9/2025 OK to Issue CofO JOSE AVILA