15235 W NURMI ST 91342

Certificate Information: 15235 W NURMI ST 91342

Application / Permit
17010-20000-01188
Plan Check / Job No.
B17VN03782
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 51'-0" x 32'-6" Irregular Shape Single Family Dwelling with attached 2-Car Garage.
Permit Issued
Issued on 3/17/2021
Issuing Office
Current Status
CofO Issued on 12/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2017 APPLICANT
Assigned to Plan Check Engineer 4/27/2017 OMID HEDAYAT
Plans on Hold 5/2/2017 GUANG MIN TUNG
Hold Released 5/4/2017 GUANG MIN TUNG
Corrections Issued 5/11/2017 OMID HEDAYAT
Quality Review Completed 5/16/2017 CHON CHIO KUO
Building Plans Picked Up 5/17/2017 APPLICANT
Green Plans Picked Up 5/17/2017 APPLICANT
Applicant returned to address corrections 1/9/2018 OMID HEDAYAT
Applicant returned to address corrections 10/24/2018 OMID HEDAYAT
Applicant returned to address corrections 9/4/2019 OMID HEDAYAT
Applicant returned to address corrections 2/24/2020 OMID HEDAYAT
Plan Check Approved 3/18/2020 OMID HEDAYAT
Issued 3/17/2021 APPLICANT
CofO in Progress 12/17/2025 RAUL OLAGI
Permit Finaled 12/23/2025 RUBEN SALAS
CofO Issued 12/23/2025 RUBEN SALAS
Permit Finaled 12/23/2025 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/19/2017 JOHN DALLAS
Low Impact Development Cleared 1/10/2018 MARTIN FRAGOSO
Address approval Cleared 4/12/2018 JOHN LIN
BHO/Hillside ordinance Cleared 4/12/2018 JOHN LIN
BHO/Hillside ordinance Cleared 4/12/2018 JOHN LIN
BHO/Hillside ordinance Cleared 4/12/2018 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 4/12/2018 JOHN LIN
Permit Cleared 4/12/2018 JOHN LIN
Roof/Waste drainage to street Cleared 4/12/2018 JOHN LIN
Sewer availability Cleared 4/12/2018 JOHN LIN
"T" removal Cleared 4/18/2018 RICK TORRES
Miscellaneous Cleared 4/18/2018 RICK TORRES
Miscellaneous Cleared 4/18/2018 RICK TORRES
Private street Cleared 4/18/2018 RICK TORRES
Tract Map conditions Cleared 4/18/2018 RICK TORRES
ZA Case Cleared 4/18/2018 RICK TORRES
Miscellaneous Cleared 1/13/2020 DAISY BENICIA
Miscellaneous Cleared 1/13/2020 DAISY BENICIA
GPI Written Notices Cleared 3/4/2020 OMID HEDAYAT
Grading Pre-Inspection Cleared 3/4/2020 OMID HEDAYAT
Green Code Cleared 3/4/2020 MICHAEL AYERS
"Q" conditions Cleared 10/1/2020 HERMINIGILDO AGUSTIN

Contact Information

Contractor Munoz Carlos Enrique; Lic. No.: 908224-B 2027 PHILLIPPI STREET      SAN FERNANDO, CA 91340
Engineer Basma, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303
Engineer Miller, Karen Lynn; Lic. No.: GE2257 5364 DORIS WY      TORRANCE, CA 90505

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/3/2021 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 12/3/2021 Corrections Issued MICHAEL TEMPLE
Underground Mechanical 12/3/2021 Corrections Issued MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 12/8/2021 Partial Inspection MICHAEL TEMPLE
PLUMBING-Rough 12/8/2021 Partial Approval JENNIFER RABUCHIN
Deputy Reinf. Concrete 12/20/2021 No Access for Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 12/20/2021 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 12/21/2021 Approved MICHAEL TEMPLE
Deputy Wood Construction 1/13/2022 Conditional Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 2/15/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/28/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 2/28/2022 Approved JENNIFER RABUCHIN
Green Building Rough 2/28/2022 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 2/28/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/28/2022 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 2/28/2022 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 3/10/2022 Partial Approval JENNIFER RABUCHIN
Insulation 3/23/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 4/1/2022 Partial Approval JENNIFER RABUCHIN
Shower Pan 4/29/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/9/2022 Partial Approval DEANDRE HOFFMAN
Sewer 7/20/2023 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 7/20/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/27/2023 Conditional Approval JENNIFER RABUCHIN
ELECTRICAL-Final 10/27/2023 Corrections Issued JENNIFER RABUCHIN
Final 10/27/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/27/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 10/27/2023 Approved JENNIFER RABUCHIN
HVAC-Final 10/27/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 10/27/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/27/2023 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 10/27/2023 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 10/27/2023 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 10/27/2023 Not Ready for Inspection JENNIFER RABUCHIN
Service/Power Release 2/13/2024 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 9/30/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/27/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 6/27/2025 Corrections Issued JENNIFER RABUCHIN
Final 6/27/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 6/27/2025 Approved JENNIFER RABUCHIN
HVAC-Final 6/27/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/27/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Not Required JENNIFER RABUCHIN
Service/Power Release 6/27/2025 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 6/27/2025 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/10/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/10/2025 Approved JENNIFER RABUCHIN
Final 11/10/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 11/10/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/10/2025 Approved JENNIFER RABUCHIN
Service/Power Release 11/10/2025 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 11/10/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/18/2025 Approved JENNIFER RABUCHIN
Final 11/18/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 11/18/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/18/2025 Approved JENNIFER RABUCHIN
Service/Power Release 11/18/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/17/2025 Approved JENNIFER RABUCHIN
Final 12/17/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 12/17/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 12/17/2025 Approved JENNIFER RABUCHIN