12515 N HALEH LANE 91342

Certificate Information: 12515 N HALEH LANE 91342

Application / Permit
17010-20000-01186
Plan Check / Job No.
B17VN03782
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 32'-0" x 55'-6" Irregular shape Single Family Dwelling w/ attached 2- Car Garage.
Permit Issued
Issued on 3/17/2021
Issuing Office
Current Status
Issued on 3/17/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/20/2017 APPLICANT
Assigned to Plan Check Engineer 4/27/2017 OMID HEDAYAT
Plans on Hold 5/2/2017 GUANG MIN TUNG
Hold Released 5/4/2017 GUANG MIN TUNG
Corrections Issued 5/11/2017 OMID HEDAYAT
Quality Review Completed 5/16/2017 CHON CHIO KUO
Building Plans Picked Up 5/17/2017 APPLICANT
Green Plans Picked Up 5/17/2017 APPLICANT
Applicant returned to address corrections 1/9/2018 OMID HEDAYAT
Applicant returned to address corrections 10/24/2018 OMID HEDAYAT
Applicant returned to address corrections 9/4/2019 OMID HEDAYAT
Applicant returned to address corrections 2/24/2020 OMID HEDAYAT
Plan Check Approved 10/6/2020 OMID HEDAYAT
Issued 3/17/2021 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/19/2017 JOHN DALLAS
Low Impact Development Cleared 1/10/2018 MARTIN FRAGOSO
Address approval Cleared 4/12/2018 JOHN LIN
BHO/Hillside ordinance Cleared 4/12/2018 JOHN LIN
BHO/Hillside ordinance Cleared 4/12/2018 JOHN LIN
BHO/Hillside ordinance Cleared 4/12/2018 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 4/12/2018 JOHN LIN
Permit Cleared 4/12/2018 JOHN LIN
Roof/Waste drainage to street Cleared 4/12/2018 JOHN LIN
Sewer availability Cleared 4/12/2018 JOHN LIN
"T" removal Cleared 4/18/2018 RICK TORRES
Miscellaneous Cleared 4/18/2018 RICK TORRES
Miscellaneous Cleared 4/18/2018 RICK TORRES
Private street Cleared 4/18/2018 RICK TORRES
Tract Map conditions Cleared 4/18/2018 RICK TORRES
ZA Case Cleared 4/18/2018 RICK TORRES
Miscellaneous Cleared 1/13/2020 DAISY BENICIA
Miscellaneous Cleared 1/13/2020 DAISY BENICIA
Green Code Cleared 3/4/2020 MICHAEL AYERS
GPI Written Notices Cleared 3/24/2020 OMID HEDAYAT
Grading Pre-Inspection Cleared 3/24/2020 OMID HEDAYAT
"Q" conditions Cleared 10/1/2020 HERMINIGILDO AGUSTIN

Contact Information

Contractor Munoz Carlos Enrique; Lic. No.: 908224-B 2027 PHILLIPPI STREET      SAN FERNANDO, CA 91340
Engineer Basma, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303
Engineer Miller, Karen Lynn; Lic. No.: GE2257 5364 DORIS WY      TORRANCE, CA 90505

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/28/2021 Partial Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 11/22/2021 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 12/3/2021 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 12/8/2021 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 12/8/2021 Partial Inspection MICHAEL TEMPLE
Reinforced Masonry Frame 12/17/2021 Approved JENNIFER RABUCHIN
Masonry Wall/Backfill 1/13/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 1/28/2022 Partial Approval JENNIFER RABUCHIN
Deputy Reinf. Concrete 2/8/2022 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 2/8/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/1/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/19/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 4/19/2022 Approved JENNIFER RABUCHIN
Green Building Rough 4/19/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 4/19/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/19/2022 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 4/19/2022 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 4/26/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/9/2022 Approved JENNIFER RABUCHIN
Green Building Rough 5/9/2022 Approved JENNIFER RABUCHIN
Insulation 5/9/2022 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 5/9/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 5/23/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/8/2022 Partial Approval JENNIFER RABUCHIN
Shower Pan 6/8/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/15/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/6/2022 Partial Approval JENNIFER RABUCHIN
Reinforced Concrete Frame 3/9/2023 Approved JENNIFER RABUCHIN
Underground Mechanical 4/18/2023 Partial Approval JENNIFER RABUCHIN
Service/Power Release 2/13/2024 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 9/30/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/13/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 6/13/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Final 6/13/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Final 6/13/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Final 6/13/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Service/Power Release 6/13/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 6/13/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Final 6/17/2025 Approved JENNIFER RABUCHIN
HVAC-Final 6/17/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/17/2025 Approved JENNIFER RABUCHIN
Service/Power Release 6/17/2025 Not Ready for Inspection JENNIFER RABUCHIN
Service/Power Release 6/25/2025 Approved JENNIFER RABUCHIN