12515 N HALEH LANE 91342
Certificate Information: 12515 N HALEH LANE 91342
- Application / Permit
- 17010-20000-01186
- Plan Check / Job No.
- B17VN03782
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 32'-0" x 55'-6" Irregular shape Single Family Dwelling w/ attached 2- Car Garage.
- Permit Issued
- Issued on 3/17/2021
- Issuing Office
- Current Status
- Issued on 3/17/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/20/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2017 | OMID HEDAYAT |
| Plans on Hold | 5/2/2017 | GUANG MIN TUNG |
| Hold Released | 5/4/2017 | GUANG MIN TUNG |
| Corrections Issued | 5/11/2017 | OMID HEDAYAT |
| Quality Review Completed | 5/16/2017 | CHON CHIO KUO |
| Building Plans Picked Up | 5/17/2017 | APPLICANT |
| Green Plans Picked Up | 5/17/2017 | APPLICANT |
| Applicant returned to address corrections | 1/9/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/24/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/4/2019 | OMID HEDAYAT |
| Applicant returned to address corrections | 2/24/2020 | OMID HEDAYAT |
| Plan Check Approved | 10/6/2020 | OMID HEDAYAT |
| Issued | 3/17/2021 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/19/2017 | JOHN DALLAS |
| Low Impact Development | Cleared | 1/10/2018 | MARTIN FRAGOSO |
| Address approval | Cleared | 4/12/2018 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 4/12/2018 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 4/12/2018 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 4/12/2018 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2018 | JOHN LIN |
| Permit | Cleared | 4/12/2018 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 4/12/2018 | JOHN LIN |
| Sewer availability | Cleared | 4/12/2018 | JOHN LIN |
| "T" removal | Cleared | 4/18/2018 | RICK TORRES |
| Miscellaneous | Cleared | 4/18/2018 | RICK TORRES |
| Miscellaneous | Cleared | 4/18/2018 | RICK TORRES |
| Private street | Cleared | 4/18/2018 | RICK TORRES |
| Tract Map conditions | Cleared | 4/18/2018 | RICK TORRES |
| ZA Case | Cleared | 4/18/2018 | RICK TORRES |
| Miscellaneous | Cleared | 1/13/2020 | DAISY BENICIA |
| Miscellaneous | Cleared | 1/13/2020 | DAISY BENICIA |
| Green Code | Cleared | 3/4/2020 | MICHAEL AYERS |
| GPI Written Notices | Cleared | 3/24/2020 | OMID HEDAYAT |
| Grading Pre-Inspection | Cleared | 3/24/2020 | OMID HEDAYAT |
| "Q" conditions | Cleared | 10/1/2020 | HERMINIGILDO AGUSTIN |
Contact Information
| Contractor | Munoz Carlos Enrique; Lic. No.: 908224-B | 2027 PHILLIPPI STREET SAN FERNANDO, CA 91340 |
| Engineer | Basma, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
| Engineer | Miller, Karen Lynn; Lic. No.: GE2257 | 5364 DORIS WY TORRANCE, CA 90505 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/28/2021 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/22/2021 | Approved | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 12/3/2021 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 12/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 12/8/2021 | Partial Inspection | MICHAEL TEMPLE |
| Reinforced Masonry Frame | 12/17/2021 | Approved | JENNIFER RABUCHIN |
| Masonry Wall/Backfill | 1/13/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/28/2022 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Reinf. Concrete | 2/8/2022 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 2/8/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/19/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/19/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/19/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 4/19/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/19/2022 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 4/19/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/26/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 5/9/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/9/2022 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 5/9/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 5/23/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/8/2022 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 6/8/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/15/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/6/2022 | Partial Approval | JENNIFER RABUCHIN |
| Reinforced Concrete Frame | 3/9/2023 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 4/18/2023 | Partial Approval | JENNIFER RABUCHIN |
| Service/Power Release | 2/13/2024 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 9/30/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/13/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 6/13/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Final | 6/13/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Final | 6/13/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 6/13/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 6/13/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Service/Power Release | 6/13/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 6/13/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 6/17/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 6/17/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/17/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 6/17/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Service/Power Release | 6/25/2025 | Approved | JENNIFER RABUCHIN |