4630 W VANTAGE AVE 91607

Certificate Information: 4630 W VANTAGE AVE 91607

Application / Permit
17010-20000-01154
Plan Check / Job No.
B17VN03672
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 1-STORY TYPE V-A SFD W/ ATTACHED 2-CAR GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 3/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2017 APPLICANT
Assigned to Plan Check Engineer 4/20/2017 DOUGLAS NAKATANI
Disabled Access Plans Picked Up 4/20/2017 APPLICANT
Green Plans Picked Up 4/20/2017 APPLICANT
Corrections Issued 5/8/2017 DOUGLAS NAKATANI
Quality Review Completed 5/17/2017 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 5/31/2017 APPLICANT
Plan Check Approved 3/4/2020 NILOOFAR MEHRAIN
Issued 3/4/2020 LADBS
CofO in Progress 1/8/2021 ARAM AVEDISIAN
CofO Issued 1/29/2021 DANIEL ORRANTE
Permit Finaled 1/29/2021 DANIEL ORRANTE

Permit Application Clearance Information

DAS Clearance Cleared 4/12/2017 NORLITO MEDRANO
Address approval Cleared 1/9/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/9/2020 ADRIAN CASTRO
Permit Cleared 1/9/2020 ADRIAN CASTRO
Sewer availability Cleared 1/9/2020 ROSE MARIE SMITH
Hydrant and Access approval Cleared 2/7/2020 GEORGE SUCHAND
Green Code Cleared 2/25/2020 MICHAEL AYERS
Low Impact Development Cleared 2/26/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/28/2020 JOHN LIN
Specific Plan Cleared 3/2/2020 RICHARD REASER
ZA Case Cleared 3/2/2020 RICHARD REASER
ZI Cleared 3/2/2020 RICHARD REASER
ZI Cleared 3/2/2020 RICHARD REASER

Contact Information

Contractor Owner-Builder       ,
Engineer Naim, Soleiman Israel; Lic. No.: S2454 403 21ST ST      SANTA MONICA, CA 90402
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 4/15/2020 Approved DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 7/20/2020 Partial Inspection MATTHEW NELSON
PLUMBING-Rough 7/20/2020 Partial Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 7/29/2020 Approved BEAU COLLINS
Footing/Foundation/Slab 7/29/2020 Approved BEAU COLLINS
Sewer 8/14/2020 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/19/2020 Partial Approval ARAM AVEDISIAN
HVAC-Rough 9/2/2020 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 9/4/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 9/4/2020 Approved ARAM AVEDISIAN
Green Building Rough 9/4/2020 Approved ARAM AVEDISIAN
MERV13>=Rough 9/4/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 9/4/2020 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 9/4/2020 Not Ready for Inspection ARAM AVEDISIAN
Insulation 9/14/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/14/2020 Partial Approval ARAM AVEDISIAN
Shower Pan 9/14/2020 Approved ARAM AVEDISIAN
Drywall Nailing 9/22/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/22/2020 Partial Approval ARAM AVEDISIAN
Gas Test 11/5/2020 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/14/2020 Approved ARAM AVEDISIAN
Final 12/14/2020 Not Ready for Inspection ARAM AVEDISIAN
Green Building Final 12/14/2020 Not Ready for Inspection ARAM AVEDISIAN
MERV13>=Final 12/14/2020 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 12/14/2020 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 12/14/2020 Approved ARAM AVEDISIAN
Smoke Detectors 12/14/2020 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 12/14/2020 Approved ARAM AVEDISIAN
Final 12/24/2020 Corrections Issued ARAM AVEDISIAN
Green Building Final 12/24/2020 Approved ARAM AVEDISIAN
MERV13>=Final 12/24/2020 Approved ARAM AVEDISIAN
Final 1/8/2021 OK to Issue CofO ARAM AVEDISIAN