Special/Order Compliance
|
12/19/2018
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Grading Pre-Inspection
|
2/12/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Pre-Inspection
|
2/12/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
6/6/2019
|
Partial Inspection
|
ANTHONY MCDOWALL
|
|
Pre-Inspection
|
6/6/2019
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
Piling/Pier/Caisson
|
6/13/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
6/14/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
6/24/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Special/Order Compliance
|
6/24/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Special/Order Compliance
|
7/11/2019
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
7/15/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Pre-Gunite
|
8/14/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Pre-Gunite
|
8/27/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
9/26/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
9/26/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
9/27/2019
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
9/27/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
9/30/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
10/2/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
10/3/2019
|
No Access for Inspection
|
ROBERT SHELLY
|
|
Footing/Foundation/Slab
|
11/12/2019
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Special/Order Compliance
|
11/15/2019
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Special/Order Compliance
|
11/22/2019
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
12/13/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
12/17/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
12/17/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Drilled-In Anchors
|
1/17/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
1/17/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Shotcrete
|
1/21/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Piling/Pier/Caisson
|
3/31/2020
|
Partial Inspection
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
4/2/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
5/15/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Piling/Pier/Caisson
|
5/22/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Excavation/Setback/Form/Re-Bar
|
5/28/2020
|
Partial Inspection
|
ANTHONY MCDOWALL
|
|
Piling/Pier/Caisson
|
5/28/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Masonry Wall/Backfill
|
6/18/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Piling/Pier/Caisson
|
6/18/2020
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
Grading Pre-Inspection
|
6/23/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Piling/Pier/Caisson
|
6/23/2020
|
No Access for Inspection
|
ANTHONY MCDOWALL
|
|
Piling/Pier/Caisson
|
6/29/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Reinforced Concrete Frame
|
9/18/2020
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Excavation/Setback/Form/Re-Bar
|
9/22/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
PLUMBING-Rough
|
1/11/2021
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
PLUMBING-Rough
|
1/14/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
2/25/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
2/26/2021
|
Conditional Approval
|
KEVIN SARGSYAN
|
|
Deputy Drilled-In Anchors
|
4/9/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/6/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
5/6/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
5/6/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/25/2021
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/28/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Pre-Inspection
|
4/3/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/20/2023
|
Partial Approval
|
MICHAEL PELHAM
|
|
Footing/Foundation/Slab
|
4/20/2023
|
Approved
|
MICHAEL PELHAM
|
|
Green Building Rough
|
4/20/2023
|
Not Ready for Inspection
|
MICHAEL PELHAM
|
|
Verify Sprinkler Sign Off
|
4/20/2023
|
Not Ready for Inspection
|
MICHAEL PELHAM
|
|
Deputy Drilled-In Anchors
|
3/29/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
BUILDING-Rough-Frame
|
4/23/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Special/Order Compliance
|
4/23/2024
|
Corrections Issued
|
SEAN HAUPT
|
|
Verify Sprinkler Sign Off
|
4/23/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Deputy Steel/Welding
|
4/29/2024
|
Approved
|
SEAN HAUPT
|
|
Special/Order Compliance
|
5/1/2024
|
Not Ready for Inspection
|
MICHAEL PELHAM
|
|
Deputy Drilled-In Anchors
|
5/8/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Steel/Welding
|
5/14/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/18/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/26/2024
|
Approved
|
SEAN HAUPT
|
|
Deputy Steel/Welding
|
9/17/2024
|
Partial Approval
|
SEAN HAUPT
|
|
PLUMBING-Rough
|
10/4/2024
|
Approved
|
SEAN HAUPT
|
|
ELECTRICAL-Rough
|
10/9/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Interior/Exterior Lathing
|
10/9/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
BUILDING-Rough-Frame
|
10/22/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
ELECTRICAL-Rough
|
10/22/2024
|
Corrections Issued
|
SEAN HAUPT
|
|
Green Building Rough
|
10/22/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
HVAC-Rough
|
10/22/2024
|
Corrections Issued
|
SEAN HAUPT
|
|
Interior/Exterior Lathing
|
10/22/2024
|
Approved
|
SEAN HAUPT
|
|
Verify Sprinkler Sign Off
|
10/22/2024
|
Approved
|
SEAN HAUPT
|
|
BUILDING-Rough-Frame
|
10/30/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
ELECTRICAL-Rough
|
10/30/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Green Building Rough
|
10/30/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
HVAC-Rough
|
10/30/2024
|
Approved
|
SEAN HAUPT
|
|
BUILDING-Rough-Frame
|
11/7/2024
|
Approved
|
SEAN HAUPT
|
|
ELECTRICAL-Rough
|
11/7/2024
|
Approved
|
SEAN HAUPT
|
|
Green Building Rough
|
11/7/2024
|
Approved
|
SEAN HAUPT
|
|
Insulation
|
11/19/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
12/20/2024
|
Approved
|
SEAN HAUPT
|
|
Interior/Exterior Lathing
|
1/27/2025
|
Approved
|
SEAN HAUPT
|
|
Shower Pan
|
1/27/2025
|
Approved
|
SEAN HAUPT
|
|
ELECTRICAL-Final
|
7/22/2025
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Service/Power Release
|
7/22/2025
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
ELECTRICAL-Final
|
7/28/2025
|
Approved
|
SEAN HAUPT
|
|
Service/Power Release
|
7/28/2025
|
Approved
|
SEAN HAUPT
|
|
PLUMBING-Final
|
2/3/2026
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Underground Mechanical
|
2/25/2026
|
Approved
|
CARLOS MATAMOROS
|