12524 W ARCHWOOD ST 91606
Certificate Information: 12524 W ARCHWOOD ST 91606
- Application / Permit
- 17010-20000-01024
- Plan Check / Job No.
- B17VN03227
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25'X48' ACCESSORY DWELLING UNIT PER AB 2299 & SB 1069. ALL WORK PER WFPP. NFPA-13D FIRE SPRINKLERS REQUIRED.
- Permit Issued
- Issued on 12/26/2017
- Issuing Office
- Valley
- Current Status
- Issued on 12/26/2017
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/9/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2017 | MARVEL DELACRUZ |
| Corrections Issued | 4/3/2017 | MARVEL DELACRUZ |
| Quality Review Completed | 4/5/2017 | ABDUL CHEGENI |
| Building Plans Picked Up | 4/6/2017 | APPLICANT |
| Green Plans Picked Up | 4/6/2017 | APPLICANT |
| Applicant returned to address corrections | 12/22/2017 | MARVEL DELACRUZ |
| Plan Check Approved | 12/22/2017 | MARVEL DELACRUZ |
| Issued | 12/26/2017 | LADBS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/20/2017 | SAM NAVID |
| Address approval | Cleared | 12/13/2017 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2017 | KENNETH PHAM |
| Hydrant and Access approval | Cleared | 12/13/2017 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 12/13/2017 | KENNETH PHAM |
| Sewer availability | Cleared | 12/13/2017 | KENNETH PHAM |
| Green Code | Cleared | 12/18/2017 | MICKEY YAMASHITA |
| Miscellaneous | Cleared | 12/22/2017 | HERMINIGILDO AGUSTIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/10/2019 | Partial Inspection | GREG ALLTON |
| Excavation/Setback/Form/Re-Bar | 4/30/2019 | Approved | GREG ALLTON |
| Footing/Foundation/Slab | 4/30/2019 | Approved | GREG ALLTON |
| BUILDING-Rough-Frame | 5/17/2019 | Partial Approval | GREG ALLTON |
| PLUMBING-Rough | 5/17/2019 | Partial Approval | GREG ALLTON |
| BUILDING-Rough-Frame | 6/24/2019 | No Access for Inspection | GREG ALLTON |
| Green Building Rough | 6/24/2019 | No Access for Inspection | GREG ALLTON |
| Verify Sprinkler Sign Off | 6/24/2019 | No Access for Inspection | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2019 | Partial Approval | GREG ALLTON |
| Green Building Rough | 7/8/2019 | Not Ready for Inspection | GREG ALLTON |
| Verify Sprinkler Sign Off | 7/8/2019 | Not Ready for Inspection | GREG ALLTON |
| BUILDING-Rough-Frame | 2/13/2020 | Partial Inspection | GREG ALLTON |
| Green Building Rough | 2/13/2020 | Not Ready for Inspection | GREG ALLTON |
| Verify Sprinkler Sign Off | 2/13/2020 | Approved | GREG ALLTON |
| Wood Frame | 2/13/2020 | Not Ready for Inspection | GREG ALLTON |
| Wood Frame | 2/21/2020 | Partial Approval | GREG ALLTON |
| Interior/Exterior Lathing | 3/2/2020 | Partial Approval | GREG ALLTON |
| PLUMBING-Rough | 7/10/2020 | Corrections Issued | BRENDAN LOONEY |
| Shower Pan | 7/22/2020 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 8/4/2020 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/1/2020 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 9/1/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/14/2020 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/14/2020 | Conditional Approval | BRENDAN LOONEY |
| Green Building Rough | 10/14/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 10/14/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/5/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 11/5/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 11/5/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 11/5/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 12/16/2020 | No Access for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 12/16/2020 | No Access for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 12/16/2020 | No Access for Inspection | BRENDAN LOONEY |
| Wood Frame | 12/16/2020 | No Access for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 12/23/2020 | No Access for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 12/23/2020 | No Access for Inspection | BRENDAN LOONEY |
| Wood Frame | 12/23/2020 | No Access for Inspection | BRENDAN LOONEY |
| Green Building Rough | 1/21/2021 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 1/21/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 1/21/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Rough-Elec/Plmb/HVAC | 1/21/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 1/21/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 2/19/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 2/19/2021 | No Access for Inspection | BRENDAN LOONEY |
| Green Building Rough | 2/19/2021 | No Access for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 2/19/2021 | No Access for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 5/6/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/6/2021 | Conditional Approval | MICHEL ABAJAN |
| Green Building Rough | 5/6/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 5/6/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/6/2021 | Conditional Approval | MICHEL ABAJAN |
| Insulation | 6/17/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 6/24/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/24/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/11/2023 | No Access for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 1/13/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 12/5/2023 | No Access for Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Not Ready | JOSE AVILA |
| Special/Order Compliance | 7/16/2024 | Corrections Issued | JUAN VALENZUELA |
| Pre-Inspection | 10/11/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 1/16/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 1/16/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 1/16/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 1/23/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Final | 1/23/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Final | 2/11/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 2/11/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 4/1/2026 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 5/19/2026 | Approved | WAYNE REGESTER |
| Final | 5/19/2026 | Corrections Issued | WAYNE REGESTER |
| Green Building Final | 5/19/2026 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 5/19/2026 | SGSOV Approved | WAYNE REGESTER |
| Service/Power Release | 5/19/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Smoke Detectors | 5/19/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 6/10/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Service/Power Release | 6/10/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Smoke Detectors | 6/10/2026 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Final | 6/16/2026 | Approved | WAYNE REGESTER |
| Final | 6/16/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 6/16/2026 | Approved | WAYNE REGESTER |
| HVAC-Final | 6/16/2026 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 6/16/2026 | Approved | WAYNE REGESTER |
| Service/Power Release | 6/16/2026 | Approved | WAYNE REGESTER |
| Smoke Detectors | 6/16/2026 | Approved | WAYNE REGESTER |