4415 N PETIT AVE 91436
Certificate Information: 4415 N PETIT AVE 91436
- Application / Permit
- 17010-20000-01010
- Plan Check / Job No.
- B17VN03179
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 78'-0" x 62'-5" 2-STORY SFD W/ ATTACHED GARAGE
- Permit Issued
- Issued on 12/6/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/1/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2017 | ARTIN ZARUKIAN |
| Green Plans Picked Up | 4/13/2017 | APPLICANT |
| Corrections Issued | 4/24/2017 | ARTIN ZARUKIAN |
| Quality Review Completed | 4/28/2017 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 4/28/2017 | APPLICANT |
| Applicant returned to address corrections | 7/7/2017 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 9/27/2017 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 10/26/2017 | ARTIN ZARUKIAN |
| Plan Check Approved | 12/4/2017 | ARTIN ZARUKIAN |
| Issued | 12/6/2017 | LADBS |
| CofO in Progress | 6/29/2020 | MICHAEL SMITH |
| Permit Finaled | 7/1/2020 | DONALD SUNSERI |
| CofO Issued | 7/1/2020 | DONALD SUNSERI |
| Permit Finaled | 7/1/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2017 | ROCHELLE DUNGCA |
| BHO/Hillside ordinance | Cleared | 5/24/2017 | ROCHELLE DUNGCA |
| BHO/Hillside ordinance | Cleared | 5/24/2017 | ROCHELLE DUNGCA |
| BHO/Hillside ordinance | Cleared | 5/24/2017 | ROCHELLE DUNGCA |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2017 | ROCHELLE DUNGCA |
| Permit | Cleared | 5/24/2017 | ROCHELLE DUNGCA |
| Sewer availability | Cleared | 5/24/2017 | ROCHELLE DUNGCA |
| Hydrant and Access approval | Cleared | 5/25/2017 | OSCAR SALGADO JR |
| Low Impact Development | Cleared | 5/25/2017 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/25/2017 | IRENE CHIA |
| Green Code | Cleared | 7/14/2017 | ROLLIN GETTLE III |
| Construction near power lines | Cleared | 8/24/2017 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 9/27/2017 | ARTIN ZARUKIAN |
| Grading Pre-Inspection | Cleared | 9/27/2017 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang, Hongyu; Lic. No.: C72679 | 10530 HOPE MILLS DR LAS VEGAS, NV 89135 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/20/2018 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 4/23/2018 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2018 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 9/18/2018 | Not Ready for Inspection | MICHAEL YOUNG |
| ELECTRICAL-Rough | 9/18/2018 | Approved | MICHAEL YOUNG |
| Green Building Rough | 9/18/2018 | Not Ready for Inspection | MICHAEL YOUNG |
| HVAC-Rough | 9/18/2018 | Partial Approval | MICHAEL YOUNG |
| PLUMBING-Rough | 9/18/2018 | Not Ready for Inspection | MICHAEL YOUNG |
| Verify Sprinkler Sign Off | 9/18/2018 | Not Ready for Inspection | MICHAEL YOUNG |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2018 | Not Ready for Inspection | MICHAEL YOUNG |
| HVAC-Rough | 9/21/2018 | Not Ready for Inspection | MICHAEL YOUNG |
| PLUMBING-Rough | 9/21/2018 | Approved | MICHAEL YOUNG |
| BUILDING-Rough-Frame | 10/22/2018 | Not Ready for Inspection | MICHAEL YOUNG |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2018 | Not Ready for Inspection | MICHAEL YOUNG |
| Green Building Rough | 10/22/2018 | Not Ready for Inspection | MICHAEL YOUNG |
| Verify Sprinkler Sign Off | 10/22/2018 | Approved | MICHAEL YOUNG |
| Wood Frame | 10/22/2018 | Not Ready for Inspection | MICHAEL YOUNG |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2018 | Approved | MICHAEL YOUNG |
| HVAC-Final | 11/5/2018 | Approved | MICHAEL YOUNG |
| PLUMBING-Final | 11/5/2018 | Approved | MICHAEL YOUNG |
| Wood Frame | 11/5/2018 | Approved | MICHAEL YOUNG |
| Masonry Wall/Backfill | 11/9/2018 | Approved | MICHAEL YOUNG |
| Interior/Exterior Lathing | 12/13/2018 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 2/6/2019 | Approved | MICHAEL YOUNG |
| Wood Frame | 2/6/2019 | Approved | MICHAEL YOUNG |
| Insulation | 2/12/2019 | Approved | MICHAEL YOUNG |
| Interior/Exterior Lathing | 3/4/2019 | Approved | MICHAEL YOUNG |
| BUILDING-Rough-Frame | 1/30/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 1/30/2020 | Approved | RONALD COWAN |
| Final | 1/30/2020 | Not Ready for Inspection | RONALD COWAN |
| Green Building Final | 1/30/2020 | Approved | RONALD COWAN |
| Green Building Rough | 1/30/2020 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 1/30/2020 | SGSOV Approved | RONALD COWAN |
| Service/Power Release | 1/30/2020 | Approved | RONALD COWAN |
| Smoke Detectors | 1/30/2020 | Approved | RONALD COWAN |
| Final | 4/7/2020 | Not Ready for Inspection | RONALD COWAN |
| Final | 4/15/2020 | Not Ready for Inspection | RONALD COWAN |
| Final | 6/22/2020 | Not Ready for Inspection | RONALD COWAN |
| Final | 6/26/2020 | OK to Issue CofO | RONALD COWAN |