3202 N OAKDELL ROAD 91604
Certificate Information: 3202 N OAKDELL ROAD 91604
- Application / Permit
- 17010-20000-00896
- Plan Check / Job No.
- B17VN02918
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODELING AND ADDITION TO SFD WITH 2 CAR GARAGE. ALL WORK PER ENGINEERED DETAILS. FULLY SPRINKLERED PER NFPA-13D.
- Permit Issued
- Issued on 8/13/2021
- Issuing Office
- Current Status
- Issued on 8/13/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/6/2017 | APPLICANT |
| Green Plans Picked Up | 4/5/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2017 | JOHNNY WU |
| Corrections Issued | 4/24/2017 | JOHNNY WU |
| Quality Review Completed | 4/28/2017 | GUANG MIN TUNG |
| Applicant returned to address corrections | 9/26/2018 | JOHNNY WU |
| Applicant returned to address corrections | 10/2/2018 | JOHNNY WU |
| Applicant returned to address corrections | 10/29/2019 | JOHNNY WU |
| Applicant returned to address corrections | 4/9/2021 | JOHNNY WU |
| Applicant returned to address corrections | 5/24/2021 | JOHNNY WU |
| Applicant returned to address corrections | 8/2/2021 | JOHNNY WU |
| Applicant returned to address corrections | 8/3/2021 | JOHNNY WU |
| Plan Check Approved | 8/3/2021 | JOHNNY WU |
| No Progress | 8/3/2021 | JOHNNY WU |
| Plan Check Approved | 8/3/2021 | JOHNNY WU |
| Building Plans Picked Up | 8/7/2021 | APPLICANT |
| Issued | 8/13/2021 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/26/2018 | RYAN HUDSON |
| Address approval | Cleared | 1/30/2018 | JOSEPH RHYU |
| Address approval | Cleared | 1/30/2018 | JOSEPH RHYU |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2018 | JOSEPH RHYU |
| Hydrant and Access approval | Cleared | 1/30/2018 | JOHN DALLAS |
| Roof/Waste drainage to street | Cleared | 1/30/2018 | JOSEPH RHYU |
| Sewer availability | Cleared | 1/30/2018 | JOSEPH RHYU |
| BHO/Hillside ordinance | Cleared | 2/1/2018 | KENNETH PHAM |
| Green Code | Cleared | 2/6/2018 | MICHAEL AYERS |
| Specific Plan | Cleared | 9/25/2018 | DENNIS CHEW |
| Grading Pre-Inspection | Cleared | 9/26/2018 | JOHNNY WU |
| BHO/Hillside ordinance | Cleared | 6/2/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 6/2/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 6/2/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Bar Design And Construction Inc; Lic. No.: 786816-B | 11009 1/2 HESBY ST NORTH HOLLYWOOD, CA 91601 |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Wang, Hongyu; Lic. No.: C72679 | 10530 HOPE MILLS DR LAS VEGAS, NV 89135 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 5/9/2022 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/23/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Sewer | 11/23/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 11/30/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Underground Mechanical | 11/30/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/7/2022 | Partial Approval | JACK KARGODORIAN |
| Sewer | 12/7/2022 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/25/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/25/2023 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 11/1/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 11/1/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 11/3/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 11/6/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/13/2024 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 9/9/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/14/2025 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 1/14/2025 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 1/14/2025 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 1/14/2025 | No Access for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/16/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 1/16/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 1/16/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 3/7/2025 | Conditional Approval | JUAN VALENZUELA |
| Wood Frame | 3/12/2025 | Corrections Issued | WILLIAM WREN |
| Deputy Shotcrete | 3/18/2025 | Conditional Approval | RAUL OLAGI |
| Wood Frame | 3/18/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 4/24/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 4/24/2025 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 4/24/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Wood Frame | 4/24/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/12/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 5/12/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 5/12/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 5/12/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/15/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 5/15/2025 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 5/15/2025 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 5/15/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/27/2025 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 5/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 5/27/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 5/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 8/8/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 8/11/2025 | Conditional Approval | JUAN VALENZUELA |
| Drywall Nailing | 8/15/2025 | Approved | JACK KARGODORIAN |
| Shower Pan | 12/2/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/24/2025 | Approved | CHRISTOPHE COCHRAN |