583 N RADCLIFFE AVE 90272
Certificate Information: 583 N RADCLIFFE AVE 90272
- Application / Permit
- 17010-20000-00842
- Plan Check / Job No.
- B17VN02822
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 70'-09" x 38'-10" 2- story SFD with attached 2- car garage and habitable Basement, Max. Envelope Height=25'-6". FULLY SPRINKLERED PER NFPA-13D.
- Permit Issued
- Issued on 3/1/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2017 | JOHNNY WU |
| Green Plans Picked Up | 4/17/2017 | APPLICANT |
| Corrections Issued | 4/18/2017 | JOHNNY WU |
| Quality Review Completed | 4/21/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 6/26/2017 | APPLICANT |
| Applicant returned to address corrections | 9/12/2017 | JOHNNY WU |
| Applicant returned to address corrections | 9/25/2017 | JOHNNY WU |
| Applicant returned to address corrections | 2/15/2019 | JOHNNY WU |
| Applicant returned to address corrections | 2/20/2019 | JOHNNY WU |
| Applicant returned to address corrections | 2/21/2019 | JOHNNY WU |
| Plan Check Approved | 2/28/2019 | JOHNNY WU |
| Issued | 3/1/2019 | LADBS |
| CofO in Progress | 2/4/2021 | ANDREW NAVE |
| Permit Finaled | 2/25/2021 | KENNETH NAGLE |
| CofO Issued | 2/25/2021 | KENNETH NAGLE |
| Permit Finaled | 2/25/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/3/2018 | ROBERT DUFF |
| Address approval | Cleared | 2/11/2019 | CHRISTOPHER LAW |
| Address approval | Cleared | 2/11/2019 | CHRISTOPHER LAW |
| BHO/Hillside ordinance | Cleared | 2/11/2019 | CHRISTOPHER LAW |
| BHO/Hillside ordinance | Cleared | 2/11/2019 | CHRISTOPHER LAW |
| BHO/Hillside ordinance | Cleared | 2/11/2019 | CHRISTOPHER LAW |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2019 | KARAN PATEL |
| Green Code | Cleared | 2/11/2019 | ROLLIN GETTLE III |
| Low Impact Development | Cleared | 2/11/2019 | IDA MEISAMI-FARD |
| Miscellaneous | Cleared | 2/11/2019 | CHRISTOPHER LAW |
| Permit | Cleared | 2/11/2019 | KARAN PATEL |
| Roof/Waste drainage to street | Cleared | 2/11/2019 | KARAN PATEL |
| Sewer availability | Cleared | 2/11/2019 | CHRISTOPHER LAW |
| Coastal Zone | Cleared | 2/13/2019 | NOAH MCCOY |
| ZA Case | Cleared | 2/13/2019 | NOAH MCCOY |
| Grading Pre-Inspection | Cleared | 2/15/2019 | JOHNNY WU |
| Excavation more than 5-ft deep | Cleared | 2/19/2019 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 2/19/2019 | JOHNNY WU |
| Miscellaneous | Cleared | 2/19/2019 | JOHNNY WU |
Contact Information
| Contractor | Rocon Sunset Development Inc; Lic. No.: 1050364-B | 861 VIA DE LA PAZ G PACIFIC PALISADES, CA 90272 |
| Engineer | Shubeck,, Robert James; Lic. No.: GE773 | 60 HACKAMORE LANE BELL CANYON, CA 91307 |
| Engineer | Vasquez, Luis Fernando; Lic. No.: C56232 | 1551 RANDALL ST GLENDALE, CA 91201 |
| Geologist | Denison,, Frank Edmond; Lic. No.: EG1067 | 867 HARTGLEN AVENUE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/30/2019 | Corrections Issued | ANDREW NAVE |
| Pre-Inspection | 4/30/2019 | Approved | ANDREW NAVE |
| Piling/Pier/Caisson | 5/8/2019 | Partial Inspection | ANDREW NAVE |
| Piling/Pier/Caisson | 5/13/2019 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 6/4/2019 | Partial Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 6/6/2019 | Partial Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 7/19/2019 | Partial Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 7/23/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 8/2/2019 | Not Ready for Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 8/15/2019 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 8/16/2019 | Conditional Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 8/30/2019 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 8/30/2019 | Partial Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 9/5/2019 | Partial Approval | DAVID FEILER |
| Deputy Reinf. Concrete | 9/6/2019 | Conditional Approval | ANDREW NAVE |
| Underground Mechanical | 9/12/2019 | Corrections Issued | ANDREW NAVE |
| Underground Mechanical | 9/16/2019 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 9/19/2019 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 9/25/2019 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 10/4/2019 | Not Ready for Inspection | ANDREW NAVE |
| Piling/Pier/Caisson | 10/4/2019 | Partial Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 10/7/2019 | Corrections Issued | ANDREW NAVE |
| Piling/Pier/Caisson | 10/7/2019 | Not Ready for Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 10/9/2019 | Partial Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 10/9/2019 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2019 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 10/18/2019 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2019 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2019 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 11/8/2019 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2019 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 11/20/2019 | Conditional Approval | ANDREW NAVE |
| Deputy Wood Construction | 12/12/2019 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2019 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2019 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 12/20/2019 | Approved | ANDREW NAVE |
| HVAC-Rough | 1/7/2020 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 1/8/2020 | Approved | ANDREW NAVE |
| HVAC-Rough | 1/9/2020 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 1/10/2020 | Approved | ANDREW NAVE |
| Green Building Rough | 1/10/2020 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 1/10/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 1/15/2020 | Not Ready for Inspection | ANDREW NAVE |
| Insulation | 1/17/2020 | Not Ready for Inspection | ANDREW NAVE |
| Interior/Exterior Lathing | 1/17/2020 | Not Ready for Inspection | ANDREW NAVE |
| Insulation | 1/22/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 1/22/2020 | Partial Approval | ANDREW NAVE |
| Drywall Nailing | 1/28/2020 | Approved | ANDREW NAVE |
| Shower Pan | 2/28/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 3/6/2020 | Approved | ANDREW NAVE |
| Deck | 5/1/2020 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 5/18/2020 | Approved | ANDREW NAVE |
| Sewer | 6/30/2020 | Approved | ANDREW NAVE |
| HVAC-Final | 9/23/2020 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 10/28/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 10/30/2020 | Approved | ANDREW NAVE |
| PLUMBING-Final | 10/30/2020 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Final | 11/4/2020 | Corrections Issued | ANDREW NAVE |
| Gas Test | 11/10/2020 | Approved | ANDREW NAVE |
| PLUMBING-Final | 11/13/2020 | Approved | ANDREW NAVE |
| Final | 12/10/2020 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 12/10/2020 | Approved | ANDREW NAVE |
| Green Building Final | 12/10/2020 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Approved | ANDREW NAVE |
| Service/Power Release | 12/10/2020 | Not Ready for Inspection | ANDREW NAVE |
| Smoke Detectors | 12/10/2020 | Approved | ANDREW NAVE |
| Final | 2/4/2021 | Conditional Approval | ANDREW NAVE |
| Green Building Final | 2/4/2021 | Approved | ANDREW NAVE |
| Service/Power Release | 2/4/2021 | Approved | ANDREW NAVE |