583 N RADCLIFFE AVE 90272

Certificate Information: 583 N RADCLIFFE AVE 90272

Application / Permit
17010-20000-00842
Plan Check / Job No.
B17VN02822
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 70'-09" x 38'-10" 2- story SFD with attached 2- car garage and habitable Basement, Max. Envelope Height=25'-6". FULLY SPRINKLERED PER NFPA-13D.
Permit Issued
Issued on 3/1/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2017 APPLICANT
Assigned to Plan Check Engineer 4/6/2017 JOHNNY WU
Green Plans Picked Up 4/17/2017 APPLICANT
Corrections Issued 4/18/2017 JOHNNY WU
Quality Review Completed 4/21/2017 GUANG MIN TUNG
Building Plans Picked Up 6/26/2017 APPLICANT
Applicant returned to address corrections 9/12/2017 JOHNNY WU
Applicant returned to address corrections 9/25/2017 JOHNNY WU
Applicant returned to address corrections 2/15/2019 JOHNNY WU
Applicant returned to address corrections 2/20/2019 JOHNNY WU
Applicant returned to address corrections 2/21/2019 JOHNNY WU
Plan Check Approved 2/28/2019 JOHNNY WU
Issued 3/1/2019 LADBS
CofO in Progress 2/4/2021 ANDREW NAVE
Permit Finaled 2/25/2021 KENNETH NAGLE
CofO Issued 2/25/2021 KENNETH NAGLE
Permit Finaled 2/25/2021 KENNETH NAGLE

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/3/2018 ROBERT DUFF
Address approval Cleared 2/11/2019 CHRISTOPHER LAW
Address approval Cleared 2/11/2019 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 2/11/2019 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 2/11/2019 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 2/11/2019 CHRISTOPHER LAW
Eng Process Fee Ord 176,300 Cleared 2/11/2019 KARAN PATEL
Green Code Cleared 2/11/2019 ROLLIN GETTLE III
Low Impact Development Cleared 2/11/2019 IDA MEISAMI-FARD
Miscellaneous Cleared 2/11/2019 CHRISTOPHER LAW
Permit Cleared 2/11/2019 KARAN PATEL
Roof/Waste drainage to street Cleared 2/11/2019 KARAN PATEL
Sewer availability Cleared 2/11/2019 CHRISTOPHER LAW
Coastal Zone Cleared 2/13/2019 NOAH MCCOY
ZA Case Cleared 2/13/2019 NOAH MCCOY
Grading Pre-Inspection Cleared 2/15/2019 JOHNNY WU
Excavation more than 5-ft deep Cleared 2/19/2019 CALOSHA APPROVED
GPI Written Notices Cleared 2/19/2019 JOHNNY WU
Miscellaneous Cleared 2/19/2019 JOHNNY WU

Contact Information

Contractor Rocon Sunset Development Inc; Lic. No.: 1050364-B 861 VIA DE LA PAZ   G    PACIFIC PALISADES, CA 90272
Engineer Shubeck,, Robert James; Lic. No.: GE773 60 HACKAMORE LANE      BELL CANYON, CA 91307
Engineer Vasquez, Luis Fernando; Lic. No.: C56232 1551 RANDALL ST      GLENDALE, CA 91201
Geologist Denison,, Frank Edmond; Lic. No.: EG1067 867 HARTGLEN AVENUE      WESTLAKE VILLAGE, CA 91361

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/30/2019 Corrections Issued ANDREW NAVE
Pre-Inspection 4/30/2019 Approved ANDREW NAVE
Piling/Pier/Caisson 5/8/2019 Partial Inspection ANDREW NAVE
Piling/Pier/Caisson 5/13/2019 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 6/4/2019 Partial Approval ANDREW NAVE
Piling/Pier/Caisson 6/6/2019 Partial Approval ANDREW NAVE
Piling/Pier/Caisson 7/19/2019 Partial Approval ANDREW NAVE
Piling/Pier/Caisson 7/23/2019 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 8/2/2019 Not Ready for Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 8/15/2019 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 8/16/2019 Conditional Approval ANDREW NAVE
Deputy Reinf. Concrete 8/30/2019 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 8/30/2019 Partial Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 9/5/2019 Partial Approval DAVID FEILER
Deputy Reinf. Concrete 9/6/2019 Conditional Approval ANDREW NAVE
Underground Mechanical 9/12/2019 Corrections Issued ANDREW NAVE
Underground Mechanical 9/16/2019 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 9/19/2019 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 9/25/2019 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 10/4/2019 Not Ready for Inspection ANDREW NAVE
Piling/Pier/Caisson 10/4/2019 Partial Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 10/7/2019 Corrections Issued ANDREW NAVE
Piling/Pier/Caisson 10/7/2019 Not Ready for Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 10/9/2019 Partial Approval ANDREW NAVE
Piling/Pier/Caisson 10/9/2019 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 10/18/2019 Partial Approval DAVID FEILER
PLUMBING-Rough 10/18/2019 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/22/2019 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 10/31/2019 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 11/8/2019 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 11/13/2019 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 11/20/2019 Conditional Approval ANDREW NAVE
Deputy Wood Construction 12/12/2019 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 12/12/2019 Corrections Issued ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 12/17/2019 Approved ANDREW NAVE
PLUMBING-Rough 12/20/2019 Approved ANDREW NAVE
HVAC-Rough 1/7/2020 Corrections Issued ANDREW NAVE
ELECTRICAL-Rough 1/8/2020 Approved ANDREW NAVE
HVAC-Rough 1/9/2020 Conditional Approval ANDREW NAVE
BUILDING-Rough-Frame 1/10/2020 Approved ANDREW NAVE
Green Building Rough 1/10/2020 Approved ANDREW NAVE
Verify Sprinkler Sign Off 1/10/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 1/15/2020 Not Ready for Inspection ANDREW NAVE
Insulation 1/17/2020 Not Ready for Inspection ANDREW NAVE
Interior/Exterior Lathing 1/17/2020 Not Ready for Inspection ANDREW NAVE
Insulation 1/22/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 1/22/2020 Partial Approval ANDREW NAVE
Drywall Nailing 1/28/2020 Approved ANDREW NAVE
Shower Pan 2/28/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 3/6/2020 Approved ANDREW NAVE
Deck 5/1/2020 Corrections Issued ANDREW NAVE
Excavation/Setback/Form/Re-Bar 5/18/2020 Approved ANDREW NAVE
Sewer 6/30/2020 Approved ANDREW NAVE
HVAC-Final 9/23/2020 Corrections Issued ANDREW NAVE
HVAC-Final 10/28/2020 Approved ANDREW NAVE
ELECTRICAL-Final 10/30/2020 Approved ANDREW NAVE
PLUMBING-Final 10/30/2020 Not Ready for Inspection ANDREW NAVE
PLUMBING-Final 11/4/2020 Corrections Issued ANDREW NAVE
Gas Test 11/10/2020 Approved ANDREW NAVE
PLUMBING-Final 11/13/2020 Approved ANDREW NAVE
Final 12/10/2020 Corrections Issued ANDREW NAVE
Footing/Foundation/Slab 12/10/2020 Approved ANDREW NAVE
Green Building Final 12/10/2020 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 12/10/2020 SGSOV Approved ANDREW NAVE
Service/Power Release 12/10/2020 Not Ready for Inspection ANDREW NAVE
Smoke Detectors 12/10/2020 Approved ANDREW NAVE
Final 2/4/2021 Conditional Approval ANDREW NAVE
Green Building Final 2/4/2021 Approved ANDREW NAVE
Service/Power Release 2/4/2021 Approved ANDREW NAVE