4208 N BELLINGHAM AVE 91604

Certificate Information: 4208 N BELLINGHAM AVE 91604

Application / Permit
17010-20000-00808
Plan Check / Job No.
B17VN02728
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 38' X 76'4" 2 STORY SFD WITH 19' X 21' ATTACHED 2 CAR GARAGE WITH 5'2" X 6'0" PORCH AND 24'6" X 10' REAR PATIO COVER . FIRE SPRINKLERS REQUIRED NFPA-13D . ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/21/2018
Issuing Office
Valley
Current Status
CofO Issued on 4/6/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2017 APPLICANT
Assigned to Plan Check Engineer 3/30/2017 RARES BODEA
Corrections Issued 4/5/2017 RARES BODEA
Quality Review Completed 4/7/2017 DOUGLAS NAKATANI
Building Plans Picked Up 4/14/2017 APPLICANT
Green Plans Picked Up 4/14/2017 APPLICANT
Applicant returned to address corrections 6/25/2018 RARES BODEA
Plan Check Approved 8/21/2018 RARES BODEA
Issued 8/21/2018 LADBS
CofO in Progress 3/9/2020 ARAM AVEDISIAN
CofO Issued 4/6/2020 MICHAEL SMITH
Permit Finaled 4/6/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/6/2018 LEE GUILBEAUX
Drainage to Storm Drain Cleared 6/6/2018 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/6/2018 LEE GUILBEAUX
Permit Cleared 6/6/2018 LEE GUILBEAUX
Sewer availability Cleared 6/6/2018 LEE GUILBEAUX
Low Impact Development Cleared 6/11/2018 SAM NAVID
Roof/Waste drainage to street Cleared 6/11/2018 CHRISTINE REUSCH
Hydrant and Access approval Cleared 6/15/2018 JOHN DALLAS
Green Code Cleared 6/18/2018 MICHAEL AYERS
ZI Cleared 6/18/2018 DAISY BENICIA
ZI Cleared 6/18/2018 DAISY BENICIA

Contact Information

Contractor Owner-Builder       ,
Engineer Wang, Hongyu; Lic. No.: C72679 10530 HOPE MILLS DR      LAS VEGAS, NV 89135

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/22/2019 Approved RAYMOND KEHOE
Footing/Foundation/Slab 3/4/2019 Approved COREY HUPP
BUILDING-Rough-Frame 3/18/2019 Not Ready for Inspection RAYMOND KEHOE
Footing/Foundation/Slab 3/18/2019 Approved RAYMOND KEHOE
Verify Sprinkler Sign Off 3/18/2019 Not Ready for Inspection RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 4/4/2019 Partial Approval ROBERT MINASSIANS
Green Building Rough 4/4/2019 Not Ready for Inspection ROBERT MINASSIANS
Verify Sprinkler Sign Off 4/4/2019 Not Ready for Inspection ROBERT MINASSIANS
ELECTRICAL-Rough 6/6/2019 Approved CHRISTOPHE COCHRAN
HVAC-Rough 6/6/2019 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/12/2019 Partial Approval RAYMOND KEHOE
PLUMBING-Rough 6/12/2019 Approved RAYMOND KEHOE
BUILDING-Rough-Frame 6/19/2019 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 6/19/2019 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 6/19/2019 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 6/21/2019 Approved RAYMOND KEHOE
Interior/Exterior Lathing 6/27/2019 Partial Approval RAYMOND KEHOE
Insulation 7/3/2019 Approved RAYMOND KEHOE
Shower Pan 7/9/2019 Approved RAYMOND KEHOE
Drywall Nailing 7/18/2019 Approved RAYMOND KEHOE
Gas Test 1/6/2020 Approved RAYMOND KEHOE
Green Building Final 2/20/2020 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 2/25/2020 Approved ARAM AVEDISIAN
Final 2/25/2020 Corrections Issued ARAM AVEDISIAN
HVAC-Final 2/25/2020 Partial Approval ARAM AVEDISIAN
PLUMBING-Final 2/25/2020 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/25/2020 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 2/25/2020 Approved ARAM AVEDISIAN
Smoke Detectors 2/25/2020 Approved ARAM AVEDISIAN
Final 3/9/2020 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 3/9/2020 Approved ARAM AVEDISIAN