512 N RUSTIC DR 90065
Certificate Information: 512 N RUSTIC DR 90065
- Application / Permit
- 17010-20000-00746
- Plan Check / Job No.
- B17VN02565
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) SFD W/ ATTACHED 2 CAR GARAGE AND BASEMENT AND ROOF DECK. CONSTRUCTION ON PILES.
- Permit Issued
- Issued on 4/24/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2017 | RODNEY SAMIIAN |
| Corrections Issued | 4/7/2017 | RODNEY SAMIIAN |
| Quality Review Completed | 4/13/2017 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 4/18/2017 | APPLICANT |
| Green Plans Picked Up | 4/18/2017 | APPLICANT |
| Applicant returned to address corrections | 5/25/2017 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 6/2/2017 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 2/22/2018 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 7/16/2018 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 9/6/2018 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 9/20/2018 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 10/19/2018 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 10/31/2018 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 11/2/2018 | RODNEY SAMIIAN |
| Plan Check Approved | 1/10/2019 | RODNEY SAMIIAN |
| Issued | 4/24/2019 | LADBS |
| CofO in Progress | 2/20/2026 | ALIZAH MAYAGOITIA |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| CofO Issued | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/7/2018 | ALFREDO JARA |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2018 | ALFREDO JARA |
| Permit | Cleared | 2/7/2018 | ALFREDO JARA |
| Sewer availability | Cleared | 2/7/2018 | ALFREDO JARA |
| BHO/Hillside ordinance | Cleared | 3/21/2018 | MICHAEL CASTILLO |
| Highway dedication | Cleared | 3/21/2018 | MICHAEL CASTILLO |
| Low Impact Development | Cleared | 5/10/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/10/2018 | MICHAEL CASTILLO |
| Hydrant and Access approval | Cleared | 8/2/2018 | GILBERT URREA |
| Work Adjacent to Public Way | Cleared | 8/2/2018 | MARKOS PEREZ-BRAN |
| Excavation more than 5-ft deep | Cleared | 9/6/2018 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 9/20/2018 | RODNEY SAMIIAN |
| Grading Pre-Inspection | Cleared | 9/20/2018 | RODNEY SAMIIAN |
| Specific Plan | Cleared | 9/28/2018 | DENNIS CHEW |
| ZA Case | Cleared | 9/28/2018 | DENNIS CHEW |
| BHO/Hillside ordinance | Cleared | 10/22/2018 | APEKSHYA BAJRACHARYA |
| Green Code | Cleared | 11/6/2018 | MICHAEL AYERS |
| ZA Case | Cleared | 3/13/2019 | ANNA VAN |
| Specific Plan | Cleared | 3/14/2019 | HERMINIGILDO AGUSTIN |
| Hold | Cleared | 11/14/2019 | CYNTHIA RYAN |
Contact Information
| Contractor | New Coast Construction Management Inc; Lic. No.: 988008-B | 4416 E 57TH STREET MAYWOOD, CA 90270 |
| Engineer | Phukunhaphan, Apichart; Lic. No.: GE2156 | 19940 EAST SUNSET VISTA ROAD WALNUT, CA 91789 |
| Engineer | Tuchscher, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 8/6/2020 | Partial Approval | OSVALDO PARAMO |
| Deputy Methane Barrier | 7/19/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/2/2022 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 8/19/2022 | Partial Approval | OSVALDO PARAMO |
| Structural Steel Frame | 8/19/2022 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 10/17/2022 | Corrections Issued | OSVALDO PARAMO |
| Reinforced Concrete Frame | 10/17/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/21/2022 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/21/2022 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/17/2022 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 11/17/2022 | Partial Approval | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 12/9/2022 | Conditional Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 12/9/2022 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 12/20/2022 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/11/2023 | Approved | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 1/24/2023 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/25/2023 | Corrections Issued | AMY COLIN |
| Green Building Rough | 1/25/2023 | Not Ready for Inspection | AMY COLIN |
| Verify Sprinkler Sign Off | 1/25/2023 | Corrections Issued | AMY COLIN |
| Masonry Wall/Backfill | 2/1/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Partial Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Partial Approval | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 3/7/2023 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 3/31/2023 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/12/2023 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/12/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 4/12/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 4/12/2023 | Conditional Approval | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 4/12/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 4/27/2023 | Partial Inspection | OSVALDO PARAMO |
| Insulation | 4/27/2023 | Conditional Approval | OSVALDO PARAMO |
| Drywall Nailing | 5/9/2023 | Corrections Issued | OSVALDO PARAMO |
| Drywall Nailing | 7/17/2023 | Partial Inspection | OSVALDO PARAMO |
| Drywall Nailing | 8/11/2023 | Approved | JOSH MEISTER |
| HVAC-Rough | 8/15/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/11/2023 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/4/2023 | Approved | OSVALDO PARAMO |
| Final | 4/15/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 4/15/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Reinforced Concrete Frame | 4/15/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/15/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/15/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/15/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Structural Steel Frame | 4/15/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Pre-Inspection | 4/16/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 6/20/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 6/20/2025 | Approved | ALIZAH MAYAGOITIA |
| Reinforced Concrete Frame | 6/20/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/20/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/20/2025 | Approved | ALIZAH MAYAGOITIA |
| Structural Steel Frame | 6/20/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/8/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 7/8/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 7/28/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/18/2026 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 2/20/2026 | OK to Issue CofO | ALIZAH MAYAGOITIA |