2438 N BEVERLY GLEN BLVD 90077

Certificate Information: 2438 N BEVERLY GLEN BLVD 90077

Application / Permit
17010-20000-00416
Plan Check / Job No.
B17VN01489
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 61'-6 1/2" x 33'-1/2", max height 30'-0" irregular shape building with 3-car garage. The proposed structure shall be fully sprinklered per NFPA-13D requirements.****1 of 4******
Permit Issued
Issued on 5/7/2018
Issuing Office
Valley
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2017 APPLICANT
Assigned to Plan Check Engineer 3/16/2017 JOHNNY WU
Corrections Issued 3/24/2017 JOHNNY WU
Quality Review Completed 3/24/2017 GUANG MIN TUNG
Building Plans Picked Up 3/29/2017 APPLICANT
Green Plans Picked Up 3/29/2017 APPLICANT
Applicant returned to address corrections 4/6/2017 JOHNNY WU
Applicant returned to address corrections 4/14/2017 JOHNNY WU
Applicant returned to address corrections 5/1/2017 JOHNNY WU
Applicant returned to address corrections 5/8/2017 JOHNNY WU
Applicant returned to address corrections 4/30/2018 JOHNNY WU
Applicant returned to address corrections 5/3/2018 JOHNNY WU
Applicant returned to address corrections 5/4/2018 JOHNNY WU
Plan Check Approved 5/4/2018 JOHNNY WU
Issued 5/7/2018 LADBS
CofO in Progress 7/23/2024 SEAN HAUPT
Permit Finaled 7/24/2024 DANIEL ORRANTE
CofO Issued 7/24/2024 DANIEL ORRANTE
Permit Finaled 7/24/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/6/2017 IRENE CHIA
Address approval Cleared 4/6/2017 IRENE CHIA
Eng Process Fee Ord 176,300 Cleared 4/6/2017 IRENE CHIA
Hydrant and Access approval Cleared 4/6/2017 GILBERT URREA
Sewer availability Cleared 4/6/2017 IRENE CHIA
Public Works-Highway Ded. Cleared 4/10/2017 ANDREW SLUSSER
Low Impact Development Cleared 4/11/2017 SAM NAVID
Permit Cleared 4/13/2017 CARLA VALLADARES
Roof/Waste drainage to street Cleared 4/13/2017 CARLA VALLADARES
BHO/Hillside ordinance Cleared 5/3/2017 JAMES KHO
BHO/Hillside ordinance Cleared 5/3/2017 JAMES KHO
BHO/Hillside ordinance Cleared 5/3/2017 JAMES KHO
Grading Pre-Inspection Cleared 4/30/2018 JOHNNY WU
Green Code Cleared 5/4/2018 ROLLIN GETTLE III

Contact Information

Contractor Under Construction; Lic. No.: 883832-B 111 W BEACH AVENUE      INGLEWOOD, CA 90302
Engineer Lam, Chsung Say; Lic. No.: C78287 6919 THELMA AVE      BUENA PARK, CA 90620
Engineer Moon, Samuel Sukjoon; Lic. No.: C49445 2825 PLAZA DEL AMO #170      TORRANCE, CA 90503
Geologist Miller, Jonathan Steven; Lic. No.: EG2391 2800 NEILSON WAY #210      SANTA MONICA, CA 90405

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 9/22/2018 Partial Inspection CHRISTOPHER WILSON
Pre-Inspection 6/11/2019 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 7/24/2020 Not Ready for Inspection ANTHONY MCDOWALL
Pre-Inspection 7/30/2020 Corrections Issued ANTHONY MCDOWALL
Piling/Pier/Caisson 9/21/2020 Partial Approval ANTHONY MCDOWALL
Piling/Pier/Caisson 9/29/2020 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 11/4/2020 Not Ready for Inspection ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 12/2/2020 Corrections Issued ANTHONY MCDOWALL
Footing/Foundation/Slab 12/2/2020 Not Ready for Inspection ANTHONY MCDOWALL
Footing/Foundation/Slab 12/7/2020 Partial Approval ANTHONY MCDOWALL
Deputy Steel/Welding 2/4/2021 Conditional Approval ANTHONY MCDOWALL
Deputy Steel/Welding 3/1/2021 Conditional Approval ANTHONY MCDOWALL
Reinforced Concrete Frame 3/18/2021 Partial Approval ANTHONY MCDOWALL
Structural Steel Frame 3/18/2021 Partial Approval ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 4/20/2021 Partial Approval ANTHONY MCDOWALL
Deputy Steel/Welding 6/17/2021 Conditional Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Partial Approval ANTHONY MCDOWALL
Green Building Rough 7/22/2021 Not Ready for Inspection ANTHONY MCDOWALL
Structural Steel Frame 7/22/2021 Not Ready for Inspection ANTHONY MCDOWALL
Verify Sprinkler Sign Off 7/22/2021 Not Ready for Inspection ANTHONY MCDOWALL
Deputy Steel/Welding 8/9/2021 Conditional Approval ANTHONY MCDOWALL
Wood Frame 9/30/2021 Corrections Issued MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 10/12/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/1/2022 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/3/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 6/3/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 6/3/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/29/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 6/29/2022 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 6/29/2022 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 6/29/2022 Corrections Issued BRENDAN LOONEY
Verify Sprinkler Sign Off 6/29/2022 Approved BRENDAN LOONEY
Deputy Drilled-In Anchors 7/5/2022 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 7/5/2022 Conditional Approval MICHAEL PELHAM
Special/Order Compliance 7/5/2022 Partial Inspection MICHAEL PELHAM
Structural Steel Frame 7/5/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 7/5/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 7/7/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 7/7/2022 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 7/21/2022 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 7/21/2022 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 7/21/2022 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 7/21/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 7/29/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 8/3/2022 Approved GERMAN RODRIGUEZ MENDOZA
Shower Pan 9/15/2022 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 10/14/2022 Approved GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/23/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Reinforced Concrete Frame 12/23/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 6/27/2023 Conditional Approval MICHAEL PELHAM
Underground Mechanical 8/16/2023 Approved CARLOS MATAMOROS
HVAC-Final 2/8/2024 No Access for Inspection STEPHANIE SWANSON
HVAC-Final 2/12/2024 Corrections Issued SEAN HAUPT
HVAC-Final 2/15/2024 Partial Approval STEPHANIE SWANSON
Deputy Shotcrete 2/24/2024 Conditional Approval MICHAEL PELHAM
Special/Order Compliance 2/26/2024 Corrections Issued MICHAEL PELHAM
HVAC-Final 3/1/2024 Approved SEAN HAUPT
ELECTRICAL-Final 3/21/2024 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 3/21/2024 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 4/5/2024 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 4/11/2024 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 4/16/2024 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 5/20/2024 Approved SEAN HAUPT
Final 5/20/2024 Corrections Issued SEAN HAUPT
PLUMBING-Final 5/20/2024 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Approved SEAN HAUPT
Smoke Detectors 5/20/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 7/22/2024 Approved SEAN HAUPT
Final 7/22/2024 OK to Issue CofO SEAN HAUPT
Footing/Foundation/Slab 7/22/2024 Approved SEAN HAUPT
Green Building Final 7/22/2024 Approved SEAN HAUPT
Service/Power Release 7/22/2024 Approved SEAN HAUPT