8548 N RESEDA BLVD 91324

Certificate Information: 8548 N RESEDA BLVD 91324

Application / Permit
17010-20000-00222
Plan Check / Job No.
B17VN00814
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3 STORY 39 UNITS TYPE V-A APARTMENT BUILDING OVER ONE LEVEL TYPE I-A PARKING. (TOC - TIER 1 WITH 11% -5 VLI UNITS)
Permit Issued
Issued on 6/19/2019
Issuing Office
Valley
Current Status
CofO Issued on 1/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2017 APPLICANT
Disabled Access Plans Picked Up 3/6/2017 APPLICANT
Green Plans Picked Up 3/6/2017 APPLICANT
Assigned to Plan Check Engineer 3/9/2017 KAMRAN GHOTBI RAVANDI
Corrections Issued 3/13/2017 KAMRAN GHOTBI RAVANDI
Quality Review Completed 3/17/2017 TIEN JEN WANG
Building Plans Picked Up 3/23/2017 APPLICANT
Applicant returned to address corrections 5/23/2017 KAMRAN GHOTBI RAVANDI
Plan Check Approved 2/14/2019 KAMRAN GHOTBI RAVANDI
Issued 6/19/2019 LADBS
CofO in Progress 1/21/2022 JOHN KITCKO
Permit Finaled 1/25/2022 RICKEY JACKSON
CofO Issued 1/25/2022 RICKEY JACKSON
Permit Finaled 1/25/2022 RICKEY JACKSON

Permit Application Clearance Information

Miscellaneous Cleared 5/8/2018 EDBER MACEDO
ZA Case Cleared 5/8/2018 EDBER MACEDO
ZA Case Cleared 5/8/2018 EDBER MACEDO
Address approval Cleared 6/12/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 6/12/2018 MICHAEL CASTILLO
Opn space landscape/Water mgmt Cleared 6/12/2018 IVORY CHAMBESHI
Permit Cleared 6/12/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 7/10/2018 GILBERT URREA
Driveway location Cleared 7/19/2018 KEN AITCHISON
Internal circulation Cleared 7/19/2018 KEN AITCHISON
DAS Clearance Cleared 9/14/2018 NORLITO MEDRANO
Highway dedication Cleared 9/21/2018 JOSEPH RHYU
Sewer availability Cleared 9/27/2018 JEANETTE VONG
Building over 3-story or 36-ft Cleared 10/19/2018 CALOSHA APPROVED
Fire Marshall Fire Life Safety Cleared 11/7/2018 VIDAL GARCIA
Low Impact Development Cleared 11/30/2018 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 11/30/2018 JEANETTE VONG
Green Code Cleared 1/7/2019 DAVID MATSON
Density Bonus 12.22.A.31 Cleared 1/30/2019 KENNETH LE

Contact Information

Contractor Owner-Builder       ,
Engineer Bozorgnia, Behrouz; Lic. No.: C79581 1557 WESTWOOD BLVD 145      LOS ANGELES, CA 90024

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/16/2020 Partial Inspection ROBERT COLE
Drywall Nailing 2/12/2020 Not Ready for Inspection ROBERT COLE
Final 2/12/2020 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 2/12/2020 Partial Inspection ROBERT COLE
Green Building Final 2/12/2020 Not Ready for Inspection ROBERT COLE
Green Building Rough 2/12/2020 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 2/12/2020 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 2/12/2020 SGSOV Not Ready ROBERT COLE
Smoke Detectors 2/12/2020 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 2/12/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 2/12/2020 Not Ready for Inspection ROBERT COLE
Structural Steel Frame 4/27/2020 Partial Approval ROBERT COLE
Footing/Foundation/Slab 5/18/2020 Not Ready for Inspection ROBERT COLE
Green Building Rough 5/18/2020 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 5/18/2020 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 5/18/2020 Not Ready for Inspection ROBERT COLE
Excavation/Setback/Form/Re-Bar 5/20/2020 Partial Approval ROBERT COLE
Excavation/Setback/Form/Re-Bar 6/2/2020 Not Ready for Inspection ROBERT COLE
Green Building Rough 6/2/2020 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 6/2/2020 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 6/2/2020 Not Ready for Inspection ROBERT COLE
Excavation/Setback/Form/Re-Bar 7/21/2020 Not Ready for Inspection RONALD PACHECO
Excavation/Setback/Form/Re-Bar 7/23/2020 Corrections Issued JEFFREY FULTON
Deputy Reinf. Concrete 7/24/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/24/2020 No Result Entered ROBERT COLE
Special/Order Compliance 8/3/2020 Corrections Issued JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/10/2020 Corrections Issued DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Corrections Issued DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 9/1/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 9/2/2020 Approved HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 9/17/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 9/18/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/13/2020 Conditional Approval DANNY RODRIGUEZ
Insulation 12/9/2020 Partial Approval HAMID PISHEHVAR
Interior/Exterior Lathing 12/9/2020 Partial Approval HAMID PISHEHVAR
Insulation 12/11/2020 Partial Approval DANNY RODRIGUEZ
Insulation 12/15/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 12/22/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 12/22/2020 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 12/22/2020 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/22/2020 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/22/2020 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 12/23/2020 Partial Inspection JEFFREY FULTON
Insulation 1/14/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 1/28/2021 Partial Approval DANNY RODRIGUEZ
Green Building Rough 1/28/2021 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 1/28/2021 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 1/28/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 1/29/2021 Corrections Issued ANDREW DORSO
Drywall Nailing 2/3/2021 Partial Approval DANNY RODRIGUEZ
Green Building Rough 2/3/2021 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 2/3/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/10/2021 Partial Approval DANNY RODRIGUEZ
Green Building Rough 2/10/2021 Partial Approval DANNY RODRIGUEZ
Insulation 2/10/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 2/19/2021 Partial Inspection JEFFREY FULTON
Green Building Rough 2/19/2021 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 2/23/2021 Not Ready for Inspection HAMID PISHEHVAR
Green Building Rough 2/23/2021 Not Ready for Inspection HAMID PISHEHVAR
Drywall Nailing 3/1/2021 Partial Approval HAMID PISHEHVAR
Green Building Rough 3/1/2021 Partial Approval HAMID PISHEHVAR
Drywall Nailing 3/3/2021 Partial Approval DANNY RODRIGUEZ
Green Building Rough 3/3/2021 Approved DANNY RODRIGUEZ
Interior/Exterior Lathing 3/3/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 3/10/2021 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 3/10/2021 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 3/25/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/6/2021 Approved JOHN KITCKO
Final 12/6/2021 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 12/6/2021 Approved JOHN KITCKO
Green Building Final 12/6/2021 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 12/6/2021 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 12/6/2021 SGSOV Approved JOHN KITCKO
Smoke Detectors 12/6/2021 Approved JOHN KITCKO
Verify Sprinkler Sign Off 12/6/2021 Approved JOHN KITCKO
Wood Frame 12/6/2021 Approved JOHN KITCKO
Final 12/10/2021 Conditional Approval JOHN KITCKO
Green Building Final 12/10/2021 Approved JOHN KITCKO
Final 1/21/2022 OK to Issue CofO JOHN KITCKO