5305 N CAMPO ROAD 91364
Certificate Information: 5305 N CAMPO ROAD 91364
- Application / Permit
- 17010-20000-00183
- Plan Check / Job No.
- B17VN00708
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 43'-6"'-0"x 26'-3" Two-Story Single Family Dwelling with attached Two-Car Basement Garage, Type VB Construction.
- Permit Issued
- Issued on 7/18/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2017 | APPLICANT |
| Green Plans Picked Up | 3/1/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2017 | OMID HEDAYAT |
| Corrections Issued | 3/16/2017 | OMID HEDAYAT |
| Quality Review Completed | 3/24/2017 | CHON CHIO KUO |
| Building Plans Picked Up | 3/29/2017 | APPLICANT |
| Applicant returned to address corrections | 3/23/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/3/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/11/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 6/1/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 6/27/2018 | OMID HEDAYAT |
| Plan Check Approved | 7/17/2018 | OMID HEDAYAT |
| Issued | 7/18/2018 | LADBS |
| CofO in Progress | 3/8/2021 | DAVID SANDOVAL |
| Permit Finaled | 3/8/2021 | RONALD MYRICK |
| CofO Issued | 3/8/2021 | RONALD MYRICK |
| Permit Finaled | 3/8/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/10/2017 | OMID HEDAYAT |
| GPI Written Notices | Cleared | 4/11/2018 | OMID HEDAYAT |
| Grading Pre-Inspection | Cleared | 4/11/2018 | OMID HEDAYAT |
| Address approval | Cleared | 5/14/2018 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/14/2018 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/14/2018 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/14/2018 | LEE GUILBEAUX |
| Certificate of Compliance | Cleared | 5/14/2018 | RINA LARA |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2018 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 5/14/2018 | RINA LARA |
| Miscellaneous | Cleared | 5/14/2018 | RINA LARA |
| Miscellaneous | Cleared | 5/14/2018 | RINA LARA |
| Permit | Cleared | 5/14/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/14/2018 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/14/2018 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 5/25/2018 | JOHN DALLAS |
| Miscellaneous | Cleared | 6/27/2018 | OMID HEDAYAT |
| Low Impact Development | Cleared | 7/6/2018 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/6/2018 | FATIMA GUERRA |
| Green Code | Cleared | 7/17/2018 | DAVID MATSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Liu, Wen-Young; Lic. No.: C70729 | 6103 KAUFFMAN AVE TEMPLE CITY, CA 91780 |
| Engineer | Rybak, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/31/2018 | Partial Inspection | MICHAEL TEMPLE |
| Deputy Steel/Welding | 11/29/2018 | No Access for Inspection | ROBERT SHELLY |
| Masonry Wall/Backfill | 11/30/2018 | Corrections Issued | JOHN COLEMAN |
| Piling/Pier/Caisson | 1/24/2019 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 3/12/2019 | Corrections Issued | JOSEPH SAGEN |
| Footing/Foundation/Slab | 3/18/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| Footing/Foundation/Slab | 3/29/2019 | Partial Inspection | JOSEPH SAGEN |
| Deputy Shotcrete | 8/9/2019 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/12/2019 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 8/21/2019 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/27/2019 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/3/2019 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/9/2019 | Partial Approval | JOHN KIDWELL |
| Masonry Wall/Backfill | 9/16/2019 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 9/24/2019 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/25/2019 | Partial Approval | JOHN KIDWELL |
| Deputy Shotcrete | 10/1/2019 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/3/2019 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/7/2019 | Not Ready for Inspection | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 10/8/2019 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 10/24/2019 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 11/5/2019 | Not Ready for Inspection | JOHN KIDWELL |
| Underground Mechanical | 11/18/2019 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/19/2019 | Not Ready for Inspection | SEAN WIRCH |
| Footing/Foundation/Slab | 11/19/2019 | Partial Approval | SEAN WIRCH |
| Verify Sprinkler Sign Off | 11/19/2019 | Not Ready for Inspection | SEAN WIRCH |
| Footing/Foundation/Slab | 12/2/2019 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 1/7/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Shotcrete | 1/8/2020 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 1/8/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Reinforced Concrete Frame | 1/8/2020 | Partial Approval | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 1/8/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Wood Frame | 1/24/2020 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2020 | Corrections Issued | JOHN JANSON |
| Wood Frame | 2/3/2020 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 2/10/2020 | Not Ready for Inspection | DONALD SUNSERI |
| Footing/Foundation/Slab | 2/13/2020 | Approved | JOHN KIDWELL |
| Wood Frame | 2/18/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 2/24/2020 | Corrections Issued | PETER FOLLING |
| Green Building Rough | 2/24/2020 | Not Ready for Inspection | PETER FOLLING |
| Verify Sprinkler Sign Off | 2/24/2020 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2020 | Approved | PETER FOLLING |
| PLUMBING-Rough | 3/4/2020 | Partial Approval | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2020 | Approved | PETER FOLLING |
| Green Building Rough | 3/31/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 3/31/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Verify Sprinkler Sign Off | 3/31/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 4/7/2020 | Partial Approval | DAVID SANDOVAL |
| Sewer | 4/7/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Sewer | 4/9/2020 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/23/2020 | Corrections Issued | RONALD COWAN |
| ELECTRICAL-Rough | 5/6/2020 | Not Ready for Inspection | RONALD COWAN |
| Interior/Exterior Lathing | 5/6/2020 | Partial Approval | RONALD COWAN |
| HVAC-Rough | 5/19/2020 | Corrections Issued | RONALD COWAN |
| HVAC-Rough | 5/20/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 5/21/2020 | Approved | RONALD COWAN |
| PLUMBING-Rough | 5/26/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/27/2020 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Rough | 5/27/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Verify Sprinkler Sign Off | 5/27/2020 | Approved | MICHAEL TEMPLE |
| Wood Frame | 5/29/2020 | Corrections Issued | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 6/3/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Rough | 6/3/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 7/14/2020 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Rough | 7/14/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 7/17/2020 | Approved | RONALD COWAN |
| Green Building Rough | 7/17/2020 | Approved | RONALD COWAN |
| Insulation | 7/20/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 7/22/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 7/27/2020 | Approved | PAUL CHOPP |
| ELECTRICAL-Final | 11/16/2020 | Corrections Issued | DONALD SUNSERI |
| PLUMBING-Final | 11/16/2020 | Corrections Issued | DONALD SUNSERI |
| ELECTRICAL-Final | 11/20/2020 | Approved | DAVID SANDOVAL |
| HVAC-Final | 11/20/2020 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Final | 11/20/2020 | Approved | DAVID SANDOVAL |
| Final | 12/7/2020 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Final | 12/7/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Gas Test | 12/8/2020 | Approved | VINCENT HANLEY |
| HVAC-Final | 12/8/2020 | Approved | VINCENT HANLEY |
| Special/Order Compliance | 12/18/2020 | Approved | DAVID SANDOVAL |
| Green Building Final | 12/29/2020 | Approved | PAUL CHOPP |
| Final | 3/2/2021 | Corrections Issued | DAVID SANDOVAL |
| Reinforced Concrete Frame | 3/2/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/2/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Service/Power Release | 3/2/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Smoke Detectors | 3/2/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 3/5/2021 | OK to Issue CofO | DAVID SANDOVAL |
| Reinforced Concrete Frame | 3/5/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/5/2021 | SGSOV Approved | DAVID SANDOVAL |
| Service/Power Release | 3/5/2021 | Approved | DAVID SANDOVAL |
| Smoke Detectors | 3/5/2021 | Approved | DAVID SANDOVAL |