433 N ROSENELL TER 90026

Certificate Information: 433 N ROSENELL TER 90026

Application / Permit
17010-20000-00071
Plan Check / Job No.
B17VN00326
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
100% PDPP - NEW 47 UNITS, 4-STORY, TYPE III-A CONST APT OVER 1-LEVEL TYPE 1-A SUBTERR PKG GARAGE (complete Zoning, fire life safety, DAS, Green plan check, Structural plan check). with TOC Tier-1 per DIR-2018-2918-TOC for density bonus to 47 units, & increase building height to 53'-H.
Permit Issued
Issued on 5/26/2021
Issuing Office
Valley
Current Status
CofO Issued on 12/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2017 APPLICANT
Disabled Access Plans Picked Up 1/23/2017 APPLICANT
Assigned to Plan Check Engineer 2/9/2017 GUANG MIN TUNG
Green Plans Picked Up 2/13/2017 APPLICANT
Corrections Issued 2/15/2017 GUANG MIN TUNG
Quality Review Completed 2/15/2017 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 4/24/2017 APPLICANT
Applicant returned to address corrections 11/1/2019 CHON CHIO KUO
Applicant returned to address corrections 11/20/2019 CHON CHIO KUO
Applicant returned to address corrections 5/5/2020 CHON CHIO KUO
Plan Check Approved 12/22/2020 CHON CHIO KUO
Issued 5/26/2021 APPLICANT
TCO Issued (Expire Date: 01-19-2026) 7/23/2025 ERNESTO CORRAL
CofO in Progress 12/19/2025 JEFFREY FULTON
Permit Finaled 12/22/2025 ERNESTO CORRAL
CofO Issued 12/22/2025 ERNESTO CORRAL
Permit Finaled 12/22/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/26/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/26/2018 ADRIAN SANCHEZ
Green Code Cleared 11/8/2018 MICHAEL AYERS
Low Impact Development Cleared 12/3/2018 ANDRES COVARRUBIAS
DAS Clearance Cleared 12/18/2018 NORLITO MEDRANO
Highway dedication Cleared 12/21/2018 JEANETTE VONG
Permit Cleared 3/28/2019 JEANIE LAM
Roof/Waste drainage to street Cleared 4/29/2019 JEANIE LAM
Hydrant and Access approval Cleared 4/30/2019 GILBERT URREA
Disturb/Remove Protected Trees Cleared 5/14/2019 ADRIAN SANCHEZ
Trees in Parkway Cleared 5/14/2019 ADRIAN SANCHEZ
Fire Marshall Fire Life Safety Cleared 6/17/2019 ANDREW KO
Work Adjacent to Public Way Cleared 8/5/2019 MICHAEL CASTILLO
Housing density bonus Cleared 10/2/2019 NICHOLAS KAWAZOE
"Q" conditions Cleared 10/21/2019 LATANYA ROUX
CPC Cleared 10/21/2019 LATANYA ROUX
CPC Cleared 10/21/2019 LATANYA ROUX
Frnt yard landscape/Water mgmt Cleared 10/21/2019 LATANYA ROUX
Miscellaneous Cleared 10/21/2019 LATANYA ROUX
Opn space landscape/Water mgmt Cleared 10/21/2019 LATANYA ROUX
ZA Case Cleared 10/21/2019 LATANYA ROUX
ZA Case Cleared 10/21/2019 LATANYA ROUX
Grading Pre-Inspection Cleared 10/24/2019 GUANG MIN TUNG
Building over 3-story or 36-ft Cleared 11/20/2019 CALOSHA APPROVED
GPI Written Notices Cleared 11/20/2019 GUANG MIN TUNG
"T" removal Cleared 5/27/2020 JOE LUCKEY

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 2/11/2022 Approved SORIN CIRSTOIU
Pre-Inspection 3/30/2022 Partial Inspection SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 3/31/2022 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 3/31/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 4/1/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 4/5/2022 Approved SORIN CIRSTOIU
Footing/Foundation/Slab 4/5/2022 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 4/6/2022 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 4/6/2022 Partial Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 4/7/2022 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 4/8/2022 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 4/8/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 4/11/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 4/12/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 4/13/2022 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 4/14/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 4/15/2022 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 4/15/2022 Partial Approval SORIN CIRSTOIU
Green Building Rough 4/18/2022 Partial Inspection SORIN CIRSTOIU
MERV13>=Rough 4/18/2022 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 4/18/2022 Partial Approval SORIN CIRSTOIU
Verify Sprinkler Sign Off 4/18/2022 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Masonry 4/19/2022 Approved SORIN CIRSTOIU
Deputy Shotcrete 4/19/2022 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 4/19/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 4/20/2022 Approved SORIN CIRSTOIU
Deputy Shotcrete 4/20/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Masonry 4/21/2022 Approved SORIN CIRSTOIU
Deputy Shotcrete 4/21/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Masonry 4/22/2022 Approved SORIN CIRSTOIU
Deputy Shotcrete 4/22/2022 Approved SORIN CIRSTOIU
Masonry Wall/Backfill 4/22/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 4/25/2022 Conditional Approval JONATHAN QUACH
Deputy Shotcrete 4/25/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 6/7/2022 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 6/8/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/16/2022 Partial Approval TED RIES
Deputy Reinf. Concrete 6/21/2022 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 7/19/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 7/19/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 7/19/2022 Conditional Approval WINSTON DUNNING
Masonry Wall/Backfill 7/20/2022 Partial Approval TED RIES
Footing/Foundation/Slab 8/1/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/2/2022 Conditional Approval WINSTON DUNNING
Deputy Shotcrete 8/12/2022 Conditional Approval TED RIES
Green Building Rough 8/15/2022 Not Ready for Inspection TED RIES
MERV13>=Rough 8/15/2022 Not Ready for Inspection TED RIES
Pre-Inspection 8/15/2022 Approved TED RIES
Reinforced Concrete Frame 8/15/2022 Partial Approval TED RIES
Verify Sprinkler Sign Off 8/15/2022 Not Ready for Inspection TED RIES
Deputy Reinf. Masonry 8/17/2022 Conditional Approval TED RIES
Masonry Wall/Backfill 8/18/2022 Partial Approval GREGORY POMISH
Deputy Other (see comments) 8/25/2022 Conditional Approval WINSTON DUNNING
Footing/Foundation/Slab 9/26/2022 Not Ready for Inspection TED RIES
Pre-Inspection 10/7/2022 Approved DAVID BURKHEAD
Wood Frame 10/28/2022 Corrections Issued RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 11/2/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Partial Inspection TED RIES
Deputy Wood Construction 11/7/2022 Conditional Approval MICHAEL ROSENBERG
Wood Frame 11/23/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 11/29/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Corrections Issued RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/23/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 1/20/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/2/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/8/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Corrections Issued RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 3/2/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 3/2/2023 Partial Inspection RAFAEL ESPINOZA
Deputy Wood Construction 3/7/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 3/8/2023 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Partial Approval GREGORY POMISH
Wood Frame 3/9/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 3/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 3/17/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 3/22/2023 Partial Inspection GREGORY POMISH
Wood Frame 3/22/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 3/23/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 4/5/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 4/14/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 4/24/2023 Approved RAFAEL ESPINOZA
MERV13>=Rough 4/24/2023 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 4/24/2023 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/24/2023 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/25/2023 Conditional Approval LARRY ARNICK
Insulation 4/28/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 4/28/2023 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 5/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 5/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 5/12/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/12/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 5/17/2023 Conditional Approval MICHAEL ROSENBERG
Insulation 5/19/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/26/2023 Partial Approval LARRY ARNICK
Insulation 5/26/2023 Partial Approval LARRY ARNICK
Special/Order Compliance 5/26/2023 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 5/30/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/31/2023 Partial Approval RAFAEL ESPINOZA
Insulation 6/6/2023 Partial Approval RAFAEL ESPINOZA
Insulation 6/8/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/12/2023 Partial Inspection RAFAEL ESPINOZA
Verify Rec and Parks Fee Memo 6/12/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 6/12/2023 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 6/14/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 6/14/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/16/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/26/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/26/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/30/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 7/5/2023 Partial Approval RAFAEL ESPINOZA
Insulation 7/11/2023 Partial Approval RAFAEL ESPINOZA
Insulation 7/12/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 7/12/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/18/2023 Partial Approval RAFAEL ESPINOZA
Insulation 7/19/2023 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/20/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/21/2023 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Partial Approval LARRY ARNICK
Wood Frame 8/30/2023 Not Ready for Inspection LARRY ARNICK
Insulation 9/6/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 9/22/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 9/28/2023 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 11/16/2023 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 11/20/2023 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 12/4/2023 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 12/6/2023 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 12/7/2023 Partial Approval LARRY ARNICK
Drywall Nailing 12/11/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/12/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 12/22/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 1/5/2024 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 1/16/2024 Partial Approval GREGORY POMISH
Light Gage Steel Frame 1/22/2024 Partial Approval GREGORY POMISH
Drywall Nailing 2/6/2024 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 2/20/2024 Partial Approval GREGORY POMISH
Drywall Nailing 2/28/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 3/4/2024 Partial Approval LARRY ARNICK
Drywall Nailing 3/6/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/12/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/15/2024 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 3/18/2024 Partial Inspection JEFFREY FULTON
Reinforced Masonry Frame 5/13/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 5/13/2024 Not Ready for Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 5/17/2024 Conditional Approval JEFFREY FULTON
Reinforced Concrete Frame 5/17/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 5/17/2024 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 5/21/2024 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 5/22/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 5/22/2024 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 5/30/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 10/10/2024 Partial Approval LARRY ARNICK
Light Gage Steel Frame 2/21/2025 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 3/6/2025 Partial Inspection JEFFREY FULTON
Final 3/19/2025 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 3/19/2025 Approved JEFFREY FULTON
Green Building Final 3/19/2025 Not Ready for Inspection JEFFREY FULTON
MERV13>=Final 3/19/2025 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 3/19/2025 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 3/19/2025 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Approved JEFFREY FULTON
Smoke Detectors 3/19/2025 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 3/19/2025 Not Ready for Inspection JEFFREY FULTON
Final 3/21/2025 Partial Inspection JEFFREY FULTON
Green Building Final 3/21/2025 Not Ready for Inspection JEFFREY FULTON
MERV13>=Final 3/21/2025 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 3/21/2025 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 3/21/2025 Not Ready for Inspection JEFFREY FULTON
Smoke Detectors 3/21/2025 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 3/21/2025 Not Ready for Inspection JEFFREY FULTON
Final 3/25/2025 Not Ready for Inspection JEFFREY FULTON
Pre-Inspection 3/25/2025 Not Ready for Inspection JEFFREY FULTON
Pre-Inspection 4/2/2025 Partial Approval LARRY ARNICK
Special/Order Compliance 4/2/2025 Not Ready for Inspection LARRY ARNICK
Final 5/30/2025 Not Ready for Inspection JEFFREY FULTON
Green Building Final 5/30/2025 Not Ready for Inspection JEFFREY FULTON
MERV13>=Final 5/30/2025 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 5/30/2025 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 5/30/2025 Not Ready for Inspection JEFFREY FULTON
Smoke Detectors 5/30/2025 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 5/30/2025 Not Ready for Inspection JEFFREY FULTON
Final 6/10/2025 Not Ready for Inspection JEFFREY FULTON
Green Building Final 6/10/2025 Not Ready for Inspection JEFFREY FULTON
MERV13>=Final 6/10/2025 Approved JEFFREY FULTON
Reinforced Concrete Frame 6/10/2025 Approved JEFFREY FULTON
Reinforced Masonry Frame 6/10/2025 Approved JEFFREY FULTON
Smoke Detectors 6/10/2025 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 6/10/2025 Approved JEFFREY FULTON
Final 6/16/2025 Corrections Issued JEFFREY FULTON
Green Building Final 6/16/2025 Partial Inspection JEFFREY FULTON
Smoke Detectors 6/16/2025 Approved JEFFREY FULTON
Final 6/23/2025 Not Ready for Inspection JEFFREY FULTON
Green Building Final 6/23/2025 Approved JEFFREY FULTON
Final 6/30/2025 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 7/2/2025 Partial Inspection JEFFREY FULTON
Final 8/11/2025 Not Ready for Inspection LARRY ARNICK
Final 10/15/2025 Partial Inspection JEFFREY FULTON
Final 10/28/2025 Not Ready for Inspection JEFFREY FULTON
Final 12/17/2025 Partial Inspection JEFFREY FULTON
Final 12/19/2025 OK to Issue CofO JEFFREY FULTON