2335 W TEMPLE ST #1 -#35 90026

Certificate Information: 2335 W TEMPLE ST #1 -#35 90026

Application / Permit
17010-20000-00068
Plan Check / Job No.
B17VN00318
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PDPP NEW 35 UNIT TYPE III-A CONSTRUCTION AND ON 1-LEVEL OF SUBTERRANEAN GARAGE TYPE I-A - (100% SUBMITTAL - T.O.C PROJECT. ZONING, LIFE SAFETY, GREEN, DISABLED ACCESS, STRUCTURAL CHECK, )TIER-1 .T.O.C PROJECT , WITH 50% DENSITY BONUS, INCRESE FROM 23 TO 35 UNITS, HEIGHT INCREASE 11', REDUCE 20% FRONT YARD & OPEN SPACE, & PARKING REDUCTION."
Permit Issued
Issued on 5/26/2021
Issuing Office
Valley
Current Status
CofO Issued on 4/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2017 APPLICANT
Disabled Access Plans Picked Up 1/23/2017 APPLICANT
Assigned to Plan Check Engineer 2/9/2017 CHON CHIO KUO
Corrections Issued 2/13/2017 CHON CHIO KUO
Green Plans Picked Up 2/13/2017 APPLICANT
Quality Review Completed 2/15/2017 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 4/24/2017 APPLICANT
Applicant returned to address corrections 12/28/2018 CHON CHIO KUO
Applicant returned to address corrections 6/5/2019 CHON CHIO KUO
Applicant returned to address corrections 11/12/2019 CHON CHIO KUO
Applicant returned to address corrections 12/17/2019 CHON CHIO KUO
Applicant returned to address corrections 5/5/2020 CHON CHIO KUO
Applicant returned to address corrections 11/30/2020 CHON CHIO KUO
Plan Check Approved 12/28/2020 CHON CHIO KUO
Issued 5/26/2021 APPLICANT
Permit Finaled 4/17/2026 ERNESTO CORRAL
CofO Issued 4/17/2026 ERNESTO CORRAL
Permit Finaled 4/17/2026 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/26/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/26/2018 ADRIAN SANCHEZ
Low Impact Development Cleared 10/2/2018 MITESH PATEL
DAS Clearance Cleared 12/11/2018 NORLITO MEDRANO
Highway dedication Cleared 12/21/2018 JEANETTE VONG
Permit Cleared 3/28/2019 JEANIE LAM
Work Adjacent to Public Way Cleared 6/6/2019 BOK GOH
Green Code Cleared 6/18/2019 DAVID MATSON
Sewer availability Cleared 8/1/2019 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 8/8/2019 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 8/16/2019 JEREMY CARTER
Fire Marshall Fire Life Safety Cleared 9/10/2019 ANDREW KO
Housing density bonus Cleared 10/2/2019 NICHOLAS KAWAZOE
"Q" conditions Cleared 10/21/2019 LATANYA ROUX
CPC Cleared 10/21/2019 LATANYA ROUX
Comm Cor/Mini-Mall Cleared 10/21/2019 LATANYA ROUX
Frnt yard landscape/Water mgmt Cleared 10/21/2019 LATANYA ROUX
Miscellaneous Cleared 10/21/2019 LATANYA ROUX
Opn space landscape/Water mgmt Cleared 10/21/2019 LATANYA ROUX
ZA Case Cleared 10/21/2019 LATANYA ROUX
ZA Case Cleared 10/21/2019 LATANYA ROUX
ZA Case Cleared 10/21/2019 LATANYA ROUX
ZA Case Cleared 10/21/2019 LATANYA ROUX
ZI Cleared 10/21/2019 LATANYA ROUX
GPI Written Notices Cleared 10/24/2019 CHON CHIO KUO
Grading Pre-Inspection Cleared 10/24/2019 CHON CHIO KUO
Building over 3-story or 36-ft Cleared 11/12/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/12/2019 CALOSHA APPROVED
Miscellaneous Cleared 11/12/2019 CHON CHIO KUO
"T" removal Cleared 5/27/2020 JOE LUCKEY
ZA Case Cleared 5/27/2020 JOE LUCKEY
Miscellaneous Cleared 12/28/2020 CHON CHIO KUO

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/13/2022 Approved SORIN CIRSTOIU
Pre-Inspection 5/13/2022 Approved TED RIES
Deputy Reinf. Concrete 5/16/2022 Conditional Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 5/16/2022 Not Ready for Inspection TED RIES
Deputy Reinf. Concrete 5/17/2022 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 5/17/2022 Partial Approval TED RIES
Deputy Reinf. Concrete 5/18/2022 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 5/20/2022 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/21/2022 Off-Hour Fees Due
Structural Steel Frame 5/21/2022 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 5/31/2022 Partial Approval TED RIES
Excavation/Setback/Form/Re-Bar 6/1/2022 Partial Approval TED RIES
Deputy Reinf. Concrete 6/2/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/2/2022 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/2/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/7/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/13/2022 Partial Approval TED RIES
Deputy Reinf. Masonry 6/24/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/27/2022 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 6/27/2022 Partial Approval DAVID BURKHEAD
Pre-Inspection 6/27/2022 Approved DAVID BURKHEAD
Deputy Drilled-In Anchors 7/22/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 7/22/2022 Conditional Approval WINSTON DUNNING
Footing/Foundation/Slab 7/25/2022 Partial Approval TED RIES
METHANE-Barrier 7/25/2022 Not Ready for Inspection TED RIES
METHANE-Subgrade 7/25/2022 Not Ready for Inspection TED RIES
Footing/Foundation/Slab 9/26/2022 Not Ready for Inspection TED RIES
METHANE-Barrier 9/26/2022 Conditional Approval TED RIES
METHANE-Subgrade 9/26/2022 Conditional Approval TED RIES
Reinforced Concrete Frame 9/27/2022 Partial Approval TED RIES
Deputy Reinf. Concrete 9/28/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 10/7/2022 Partial Approval DAVID BURKHEAD
Reinforced Masonry Frame 10/17/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 10/21/2022 Not Ready for Inspection TED RIES
MERV13>=Rough 10/21/2022 Not Ready for Inspection TED RIES
METHANE-Rough 10/21/2022 Not Ready for Inspection TED RIES
Verify Sprinkler Sign Off 10/21/2022 Not Ready for Inspection TED RIES
Footing/Foundation/Slab 11/4/2022 Not Ready for Inspection TED RIES
METHANE-Barrier 11/4/2022 Not Ready for Inspection TED RIES
METHANE-Subgrade 11/4/2022 Not Ready for Inspection TED RIES
Reinforced Concrete Frame 11/8/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/28/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 12/29/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/3/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 1/20/2023 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Pre-Inspection 2/14/2023 Corrections Issued RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/22/2023 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 5/22/2023 Approved RAFAEL ESPINOZA
METHANE-Subgrade 5/22/2023 Approved RAFAEL ESPINOZA
Deputy Wood Construction 5/30/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 5/31/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 6/9/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Partial Approval RAFAEL ESPINOZA
Green Building Rough 6/14/2023 Approved RAFAEL ESPINOZA
MERV13>=Rough 6/14/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 6/14/2023 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 6/14/2023 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/14/2023 Partial Inspection RAFAEL ESPINOZA
Deputy Wood Construction 1/4/2024 Conditional Approval MICHAEL ROSENBERG
Interior/Exterior Lathing 2/29/2024 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 3/6/2024 Approved LARRY ARNICK
Pre-Inspection 3/20/2024 Partial Approval LARRY ARNICK
Pre-Inspection 3/21/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 3/22/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 3/26/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 4/10/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 4/30/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/1/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/6/2024 Partial Approval JAMES POWERS
Drywall Nailing 5/8/2024 Partial Inspection JEFFREY FULTON
Insulation 5/8/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 5/14/2024 Partial Inspection JEFFREY FULTON
Wood Frame 5/14/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 5/17/2024 Partial Inspection JEFFREY FULTON
Wood Frame 5/22/2024 Corrections Issued JEFFREY FULTON
Drywall Nailing 5/30/2024 Partial Inspection JEFFREY FULTON
Wood Frame 5/30/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 6/4/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/11/2024 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 6/11/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/20/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/25/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 6/25/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 7/3/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 9/17/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 7/22/2025 Partial Approval LARRY ARNICK
Drywall Nailing 4/6/2026 Approved RONALD JIMENEZ
Final 4/6/2026 Not Ready for Inspection RONALD JIMENEZ
Footing/Foundation/Slab 4/6/2026 Approved RONALD JIMENEZ
Green Building Final 4/6/2026 Approved RONALD JIMENEZ
MERV13>=Final 4/6/2026 Approved RONALD JIMENEZ
MERV13>=Rough 4/6/2026 Approved RONALD JIMENEZ
METHANE-Final 4/6/2026 Approved RONALD JIMENEZ
METHANE-Rough 4/6/2026 Approved RONALD JIMENEZ
Reinforced Concrete Frame 4/6/2026 Approved RONALD JIMENEZ
Reinforced Masonry Frame 4/6/2026 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 4/6/2026 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 4/6/2026 Approved RONALD JIMENEZ
Verify Sprinkler Sign Off 4/6/2026 Approved RONALD JIMENEZ
Wood Frame 4/6/2026 Not Ready for Inspection RONALD JIMENEZ
Final 4/14/2026 Conditional Approval RONALD JIMENEZ
Wood Frame 4/14/2026 Approved RONALD JIMENEZ