10146 N FERNGLEN AVE 1-5 91042

Certificate Information: 10146 N FERNGLEN AVE 1-5 91042

Application / Permit
17010-20000-00005
Plan Check / Job No.
B17VN00022
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
3-STORY 5-UNIT APT BLDG WITH ATTACHED GARAGE (TOWN HOME STYLE).
Permit Issued
Issued on 11/26/2018
Issuing Office
Valley
Current Status
CofO Issued on 11/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2017 APPLICANT
Green Plans Picked Up 2/15/2017 APPLICANT
Assigned to Plan Check Engineer 2/23/2017 RODNEY SAMIIAN
Corrections Issued 2/25/2017 RODNEY SAMIIAN
Quality Review Completed 3/3/2017 GUANG MIN TUNG
Building Plans Picked Up 3/3/2017 APPLICANT
Disabled Access Plans Picked Up 3/3/2017 APPLICANT
Applicant returned to address corrections 8/29/2018 RODNEY SAMIIAN
Applicant returned to address corrections 9/13/2018 RODNEY SAMIIAN
Applicant returned to address corrections 10/1/2018 RODNEY SAMIIAN
Applicant returned to address corrections 10/19/2018 RODNEY SAMIIAN
Applicant returned to address corrections 11/13/2018 RODNEY SAMIIAN
Applicant returned to address corrections 11/15/2018 RODNEY SAMIIAN
Plan Check Approved 11/26/2018 RODNEY SAMIIAN
Issued 11/26/2018 LADBS
CofO in Progress 11/14/2023 DANNY RODRIGUEZ
Permit Finaled 11/14/2023 RICKEY JACKSON
CofO Issued 11/14/2023 RICKEY JACKSON
Permit Finaled 11/14/2023 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 1/31/2018 KAYLA PEJI
Eng Process Fee Ord 176,300 Cleared 1/31/2018 KAYLA PEJI
Permit Cleared 1/31/2018 KAYLA PEJI
Highway dedication Cleared 6/25/2018 JOHN LIN
Sewer availability Cleared 6/25/2018 JOHN LIN
Specific Plan Cleared 8/8/2018 LAURA FRAZIN-STEELE
Green Code Cleared 8/13/2018 ROLLIN GETTLE III
Hydrant and Access approval Cleared 8/13/2018 GILBERT URREA
Low Impact Development Cleared 8/15/2018 SAM NAVID
Frnt yard landscape/Water mgmt Cleared 8/29/2018 RICK TORRES
Roof/Waste drainage to street Cleared 9/5/2018 RUDY TERRIQUEZ.
DAS Clearance Cleared 10/19/2018 HAYATO TSUCHIYA

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/7/2019 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 5/10/2019 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 5/13/2019 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/10/2019 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 8/30/2019 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/12/2019 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 11/4/2019 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 11/19/2019 Partial Approval DANNY RODRIGUEZ
Green Building Rough 1/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 1/6/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 1/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 1/8/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/8/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 1/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/3/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 3/24/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/1/2020 Partial Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/29/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Partial Approval DANNY RODRIGUEZ
Insulation 7/2/2020 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 8/3/2020 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 9/11/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 9/16/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 10/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 10/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 11/4/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/4/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 11/4/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 12/18/2020 No Access for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/18/2020 No Access for Inspection DANNY RODRIGUEZ
Wood Frame 12/18/2020 No Access for Inspection DANNY RODRIGUEZ
Green Building Rough 12/23/2020 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 12/23/2020 Approved JOHN KITCKO
Wood Frame 12/23/2020 Partial Inspection JOHN KITCKO
Green Building Rough 1/13/2021 No Access for Inspection DANNY RODRIGUEZ
Insulation 1/13/2021 No Access for Inspection DANNY RODRIGUEZ
Wood Frame 1/13/2021 No Access for Inspection DANNY RODRIGUEZ
Insulation 1/14/2021 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 1/15/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 1/19/2021 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 1/19/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 1/19/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 2/4/2021 Partial Approval DANNY RODRIGUEZ
Wood Frame 2/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/11/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 2/11/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/17/2021 Approved DANNY RODRIGUEZ
Wood Frame 2/17/2021 Corrections Issued DANNY RODRIGUEZ
Wood Frame 3/9/2021 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 4/13/2021 Partial Approval DANNY RODRIGUEZ
Wood Frame 4/19/2021 Not Ready for Inspection RICKEY JACKSON
Wood Frame 4/20/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/27/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 5/18/2021 Partial Approval DANNY RODRIGUEZ
Insulation 5/25/2021 Approved ROBERT DAVIS
Wood Frame 6/4/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/19/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/27/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/27/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/3/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/28/2021 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/7/2022 Partial Approval KENNETH ROBERTS
Excavation/Setback/Form/Re-Bar 4/20/2022 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/27/2022 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 6/1/2022 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/21/2022 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/16/2022 Corrections Issued BRUCE CAMPBELL
Excavation/Setback/Form/Re-Bar 8/23/2022 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 8/25/2022 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 3/14/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 6/16/2023 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 6/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 6/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/16/2023 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 6/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 6/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 6/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 7/7/2023 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 7/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 7/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 7/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 7/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 8/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 8/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/1/2023 SGSOV Approved DANNY RODRIGUEZ
Smoke Detectors 8/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 8/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 8/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 8/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 8/8/2023 Approved DANNY RODRIGUEZ
Smoke Detectors 8/8/2023 Approved DANNY RODRIGUEZ
Structural Steel Frame 8/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 8/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 8/10/2023 OK to Issue CofO DANNY RODRIGUEZ
Footing/Foundation/Slab 8/10/2023 Approved DANNY RODRIGUEZ
Structural Steel Frame 8/10/2023 Approved DANNY RODRIGUEZ
Wood Frame 8/10/2023 Approved DANNY RODRIGUEZ