640 S CURSON AVE 90036

Certificate Information: 640 S CURSON AVE 90036

Application / Permit
17010-10011-04785
Plan Check / Job No.
B20LA00706
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ATTN LARRY LEE*** SUPPLEMENTAL TO PERMIT #17010-10000-04785 FOR LIGHT GAGE INTERIOR FRAMING
Permit Issued
Issued on 2/19/2020
Issuing Office
Metro
Current Status
Permit Finaled on 3/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 LARRY LEE
Corrections Issued 1/28/2020 LARRY LEE
Quality Review Completed 1/31/2020 CHARLES CHANG
Building Plans Picked Up 2/4/2020 APPLICANT
Plan Check Approved 2/18/2020 LARRY LEE
Issued 2/19/2020 LADBS
Permit Finaled 3/19/2021 EDWIN GREGORYONA

Permit Application Clearance Information

No Data Available.

Contact Information

Architect , ; Lic. No.: C26306       ,
Contractor Martin Bros/Marcowall Inc; Lic. No.: 246274-B P O BOX 2089      GARDENA, CA 90247
Engineer Maingot, Martin Rex; Lic. No.: S5623 1605 ELMWOOD AVE      WILMETTE, IL 60091
Engineer Tacuri, Luis Pablo; Lic. No.: C56176 1562 FAIROAKS CT      FAIRFIELD, CA 94534
Engineer Waggoner,, Michael Alan; Lic. No.: S3738 10641 BENT TREE RD      SANTA ANA, CA 92705

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 2/27/2020 Partial Approval LARRY ARNICK
Drywall Nailing 3/4/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 3/9/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 3/18/2020 Partial Approval HAMID PISHEHVAR
Light Gage Steel Frame 4/2/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 4/9/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 4/10/2020 Partial Inspection LARRY ARNICK
Light Gage Steel Frame 4/14/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 4/20/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 4/27/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 4/29/2020 Partial Inspection JONATHAN QUACH
Light Gage Steel Frame 4/30/2020 No Access for Inspection LARRY ARNICK
Light Gage Steel Frame 5/1/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 5/8/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 5/19/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 6/2/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 6/3/2020 Partial Approval LARRY ARNICK
Drywall Nailing 6/5/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 6/9/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 6/17/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 6/26/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 6/30/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 7/6/2020 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 7/8/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 7/9/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 7/15/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 7/16/2020 Not Ready for Inspection JONATHAN QUACH
Light Gage Steel Frame 7/21/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 7/27/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 7/29/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 8/10/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 8/11/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 8/13/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 8/18/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 8/31/2020 Partial Approval LARRY ARNICK
Drywall Nailing 9/9/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 9/10/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 10/7/2020 Partial Approval LARRY ARNICK
Light Gage Steel Frame 10/9/2020 Partial Approval LARRY ARNICK
Insulation 10/26/2020 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 10/26/2020 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 11/10/2020 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 11/16/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 11/23/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 12/4/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 12/11/2020 Partial Approval LARRY ARNICK
Final 3/19/2021 Permit Finaled EDWIN GREGORYONA