9227 N TUJUNGA AVE 91352

Certificate Information: 9227 N TUJUNGA AVE 91352

Application / Permit
17010-10010-04979
Plan Check / Job No.
B19LA19821
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(15) Refuse Transfer Station
Work Description
SUPPLEMENTAL PERMIT TO #17010-10000-04979 FOR THE INSTALLATION OF RECYCLING SORTING EQUIPMENT PLATFORM
Permit Issued
Issued on 1/29/2020
Issuing Office
Metro
Current Status
Permit Finaled on 3/15/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/24/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 KESETE HAREGOT
Corrections Issued 10/7/2019 KESETE HAREGOT
Quality Review Completed 10/10/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 10/17/2019 APPLICANT
Applicant returned to address corrections 11/21/2019 KESETE HAREGOT
Plan Check Approved 11/21/2019 KESETE HAREGOT
No Progress 11/21/2019 KESETE HAREGOT
Plan Check Approved 1/10/2020 KESETE HAREGOT
Issued 1/29/2020 LADBS
Permit Finaled 3/15/2021 DANNY RODRIGUEZ

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Kleiner,, Eric L; Lic. No.: C18874 1708 41ST STREET      SACRAMENTO, CA 95819
Contractor E T Environmental California Inc; Lic. No.: 921054-B 3424 PEACHTREE ROAD NE   SUITE 150    ATLANTA, GA 30326
Engineer , ; Lic. No.: C89670 13628 FREEPORT RD      SAN DIEGO, CA 92129
Engineer Burkhart,, Thomas Alfred; Lic. No.: S4378 4080 PLAZA GOLDORADO CIRCLE SUITE B      CAMERON PARK, CA 95682
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384
Engineer King,, Brett Wayne; Lic. No.: S4867 7555 SW CHERYL LN      BEAVERTON, OR 97008
Engineer Welschmeyer,, Jeremy Landrum; Lic. No.: C82293 2708 NW 86TH ST      KANSAS CITY, MO 64154

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 1/28/2021 Not Ready for Inspection DANNY RODRIGUEZ
Smoke Detectors 1/28/2021 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 1/28/2021 Not Ready for Inspection DANNY RODRIGUEZ
Final 2/2/2021 Partial Inspection DANNY RODRIGUEZ
Smoke Detectors 2/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 2/2/2021 Approved DANNY RODRIGUEZ