100 S GRAND AVE 90012
Certificate Information: 100 S GRAND AVE 90012
- Application / Permit
- 17010-10010-01468
- Plan Check / Job No.
- B19LA15928
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- PROPOSED REVISIONS TO STRUCTURAL AND ARCHITECTURAL PLANS AND CALCS. CHANGING LEVEL 2, 3 AND 5 SECTION B FROM STEEL FRAMING WITH CONCRETE FILLED METAL DECK TO STRUCTURAL SLAB. THE HEIGHT OF THE SMALLER TOWER IS CHANGING BY 4' (TALLER). STRUCTURAL PLAN FOR GLASS CANOPIES AT LEVEL 4, QUADRANT B (GLASS IS DEFERRED). ORIG WORK DESC=MIXED USE HIGHRISE BUILDING CONSISTING OF 2 TOWERS OVER PARKING. 20 STORY HOTEL AND A 39 STORY APARTMENT BUILDING WHICH INCLUDES **** AFFORDABLE UNITS. THE COMMERCIAL SPACES WILL BE APPROVED AS A CORE AND SHELL, THE HOTEL ROOMS WILL BE REVIEWED AND APPROVED UNDER THE 10008 PERMIT and ISSUED CONCURRENTLY. THE TENANT IMPROVEMENTS TO BE APPROVED UNDER SEPARATE PLAN CHECK/PERMIT. THE TRELLIS STRUCTURES ARE DEFERRED AND TO BE MADE OF STEEL. STEEL STAIRS AND RAILS, CURTAIN WALLS- ALL DOORS AND WINDOWS/STORE FRONTS, GLASS COVERED STRUCTURES ARE DEFERRED STRUCTURALLY
- Permit Issued
- Issued on 6/10/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 8/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2019 | JOHN VASQUEZ |
| Green Plans Picked Up | 9/4/2019 | APPLICANT |
| Corrections Issued | 9/19/2019 | JOHN VASQUEZ |
| Quality Review Completed | 9/25/2019 | CHARLES CHANG |
| Building Plans Picked Up | 9/25/2019 | APPLICANT |
| Applicant returned to address corrections | 10/25/2019 | JOHN VASQUEZ |
| Applicant returned to address corrections | 11/7/2019 | JOHN VASQUEZ |
| Applicant returned to address corrections | 12/4/2019 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 12/13/2019 | JOHN VASQUEZ |
| Applicant returned to address corrections | 1/6/2020 | JOHN VASQUEZ |
| Applicant returned to address corrections | 1/16/2020 | JOHN VASQUEZ |
| Applicant returned to address corrections | 1/30/2020 | JOHN VASQUEZ |
| Applicant returned to address corrections | 2/13/2020 | JOHN VASQUEZ |
| Applicant returned to address corrections | 3/4/2020 | JOHN VASQUEZ |
| Applicant returned to address corrections | 3/16/2020 | JOHN VASQUEZ |
| Applicant returned to address corrections | 3/24/2020 | JOHN VASQUEZ |
| Applicant returned to address corrections | 4/13/2020 | JOHN VASQUEZ |
| Applicant returned to address corrections | 4/23/2020 | JOHN VASQUEZ |
| Applicant returned to address corrections | 4/29/2020 | JOHN VASQUEZ |
| Applicant returned to address corrections | 5/19/2020 | JOHN VASQUEZ |
| Plan Check Approved | 5/26/2020 | JOHN VASQUEZ |
| Plan Check Approved | 6/10/2020 | JOHN VASQUEZ |
| Issued | 6/10/2020 | LADBS |
| Permit Finaled | 2/10/2022 | DANIEL MC AULIFFE |
Permit Application Clearance Information
| Building over 3-story or 36-ft | Cleared | 9/18/2019 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 9/18/2019 | CALOSHA APPROVED |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2019 | THOMAS LANG |
| Permit | Cleared | 9/24/2019 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 9/24/2019 | THOMAS LANG |
| Construction near power lines | Cleared | 9/26/2019 | WALTER RAMIREZ |
| Construction within easement | Cleared | 9/26/2019 | WALTER RAMIREZ |
| Metro Rail approval | Cleared | 10/10/2019 | JOHN VASQUEZ |
| Green Code | Cleared | 10/11/2019 | JOHN VASQUEZ |
| Food Service Establishment | Cleared | 10/16/2019 | JASH PATEL |
| Sewer availability | Cleared | 11/20/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 12/27/2019 | JEREMY CARTER |
| Miscellaneous | Cleared | 2/4/2020 | TERRY PHAN |
| Fire Marshall Fire Life Safety | Cleared | 2/13/2020 | ANDREW KO |
| Low Impact Development | Cleared | 3/24/2020 | AMMAR ELTAWIL |
| Stormwater Pollution Mitigatn | Cleared | 3/24/2020 | AMMAR ELTAWIL |
| Green Code | Cleared | 4/1/2020 | NEGAR NEJAD |
| DAS Clearance | Cleared | 4/10/2020 | WAI LAU |
| Tract Map conditions | Cleared | 4/15/2020 | DANALYNN DOMINGUEZ |
| "D" conditions | Cleared | 4/29/2020 | DANALYNN DOMINGUEZ |
| "Q" conditions | Cleared | 4/29/2020 | DANALYNN DOMINGUEZ |
| "T" removal | Cleared | 4/29/2020 | DANALYNN DOMINGUEZ |
| CPC | Cleared | 4/29/2020 | DANALYNN DOMINGUEZ |
| Specific Plan | Cleared | 4/29/2020 | DANALYNN DOMINGUEZ |
| ZI | Cleared | 4/29/2020 | DANALYNN DOMINGUEZ |
| Hold | Not Cleared | 6/16/2020 | Department of Building and Safety |
Contact Information
| Architect | Takemori,, Tensho K; Lic. No.: C26283 | 12541 BEATRICE STREET LOS ANGELES, CA 90066 |
| Contractor | Tishman Construction Corporation Of California; Lic. No.: 322670-B | 300 S GRAND AVE LOS ANGELES, CA 90071 |
| Engineer | Heeringa,, Roger L; Lic. No.: S4536 | 818 STEWART ST #1000 SEATTLE, WA 98101 |
| Engineer | Hershberg,, Mark Aaron; Lic. No.: S5078 | 6080 CENTER DR STE 300 LOS ANGELES, CA 90045 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 2/10/2022 | Approved | DANIEL MC AULIFFE |
| Final | 2/10/2022 | Permit Finaled | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 2/10/2022 | Approved | DANIEL MC AULIFFE |
| Green Building Final | 2/10/2022 | Approved | DANIEL MC AULIFFE |
| Green Building Rough | 2/10/2022 | Approved | DANIEL MC AULIFFE |
| Reinforced Concrete Frame | 2/10/2022 | Approved | DANIEL MC AULIFFE |
| SWPPP-Const. Storm Water | 2/10/2022 | Completed | DANIEL MC AULIFFE |
| Smoke Detectors | 2/10/2022 | Approved | DANIEL MC AULIFFE |