4531 W HOLLYWOOD BLVD 1-202 90027

Certificate Information: 4531 W HOLLYWOOD BLVD 1-202 90027

Application / Permit
17010-10005-01773
Plan Check / Job No.
B18LA26249
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
Early start foundation only permit (up to street level ) for New 5-story mixed use building with mezzanine (202 dwelling units with core and shell only retail ) and one level of subterranean parking garage .
Permit Issued
Issued on 3/5/2019
Issuing Office
Metro
Current Status
Permit Finaled on 2/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 3/5/2019 SAI KHUM
Issued 3/5/2019 LADBS
Permit Finaled 2/10/2023 ERNESTO CORRAL

Permit Application Clearance Information

Building over 3-story or 36-ft Cleared 12/7/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/7/2018 CALOSHA APPROVED
DAS Clearance Cleared 12/10/2018 SAI KHUM
Hydrant and Access approval Cleared 12/10/2018 ROBERT DUFF
Fire Marshall Fire Life Safety Cleared 12/12/2018 MENOA AGHAJANI
Green Code Cleared 12/14/2018 DONALD CRICHLOW
Driveway location Cleared 12/27/2018 WESTON PRINGLE
Internal circulation Cleared 12/27/2018 WESTON PRINGLE
Low Impact Development Cleared 12/31/2018 MITESH PATEL
Address approval Cleared 1/3/2019 JEANETTE VONG
Highway dedication Cleared 1/3/2019 JEANETTE VONG
Roof/Waste drainage to street Cleared 1/3/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/7/2019 KAREN LE
Encroachment in public way Cleared 1/17/2019 KAREN LE
Miscellaneous Cleared 1/29/2019 ANNA VAN
Miscellaneous Cleared 1/29/2019 ANNA VAN
Opn space landscape/Water mgmt Cleared 1/29/2019 ANNA VAN
Site Plan review Cleared 1/29/2019 ANNA VAN
Specific Plan Cleared 1/29/2019 ANNA VAN
Tract Map conditions Cleared 1/29/2019 ANNA VAN
ZA Case Cleared 1/29/2019 ANNA VAN
ZA Case Cleared 1/29/2019 ANNA VAN
ZA Case Cleared 1/29/2019 ANNA VAN
ZI Cleared 1/29/2019 ANNA VAN
"D" conditions Cleared 1/30/2019 ANNA VAN
Grading in hillside Cleared 1/30/2019 ANNA VAN
Sewer availability Cleared 2/1/2019 JOHN LIN
Miscellaneous Cleared 2/27/2019 KAREN LE
Work Adjacent to Public Way Cleared 2/27/2019 BOK GOH
GPI Written Notices Cleared 3/5/2019 SAI KHUM

Contact Information

Architect Soderbergh,, Lars Gustaf; Lic. No.: C13554 1738 BERKELEY STREET      SANTA MONICA, CA 90404
Contractor Wpic Construction Llc; Lic. No.: 1029691-B 125 W MAPLE AVE      MONROVIA, CA 91016
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316
Engineer Tang,, Stanley Siu Kei; Lic. No.: C56178 1105 N AVON STREET      BURBANK, CA 91505

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/13/2019 Approved TED RIES
Pre-Inspection 4/11/2019 Approved TED RIES
Excavation/Setback/Form/Re-Bar 9/16/2019 Partial Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 9/18/2019 Partial Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 9/19/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 9/27/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 9/30/2019 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 9/30/2019 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 10/1/2019 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/2/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/2/2019 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 10/2/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/3/2019 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 10/3/2019 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/4/2019 Not Ready for Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/7/2019 Partial Inspection DANIEL MC AULIFFE
Deputy Shotcrete 10/8/2019 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 10/8/2019 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/9/2019 Partial Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 10/9/2019 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/10/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/10/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 10/15/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 10/15/2019 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 10/15/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 10/16/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/16/2019 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 10/16/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/17/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 10/17/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/18/2019 Approved DANIEL MC AULIFFE
Deputy Shotcrete 10/18/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/18/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/21/2019 Approved DANIEL MC AULIFFE
Deputy Shotcrete 10/21/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/21/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/22/2019 Approved DANIEL MC AULIFFE
Deputy Shotcrete 10/22/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/22/2019 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Masonry 10/23/2019 Conditional Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 10/23/2019 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Masonry 10/24/2019 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 10/24/2019 Partial Approval JEFF BYTHEWAY
Reinforced Masonry Frame 10/24/2019 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 10/25/2019 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 10/25/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/28/2019 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 10/28/2019 Approved DANIEL MC AULIFFE
Deputy Shotcrete 10/28/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/28/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/29/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/29/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/30/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 10/30/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/30/2019 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Shotcrete 10/31/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/31/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 11/13/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/13/2019 Partial Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 11/13/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/15/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/15/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/19/2019 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/19/2019 Partial Approval DANIEL MC AULIFFE
Deputy Shotcrete 11/21/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/21/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/22/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 11/22/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/22/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 12/18/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 12/18/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 12/19/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/3/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/10/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/13/2020 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 1/13/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/14/2020 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 1/14/2020 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 1/15/2020 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 1/15/2020 Partial Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 1/16/2020 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/23/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 1/24/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/27/2020 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 1/27/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/28/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/29/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/30/2020 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 1/30/2020 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/31/2020 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 1/31/2020 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 2/3/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/4/2020 Approved DANIEL MC AULIFFE
Deputy Shotcrete 2/4/2020 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 2/4/2020 Partial Approval DANIEL MC AULIFFE
Deputy Shotcrete 2/5/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/6/2020 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 2/6/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 2/10/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 2/11/2020 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 2/11/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 2/12/2020 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 2/13/2020 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 2/13/2020 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 2/14/2020 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 2/14/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 2/19/2020 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 2/19/2020 Partial Inspection DANIEL MC AULIFFE
Reinforced Masonry Frame 2/19/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/20/2020 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 2/20/2020 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 2/20/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/21/2020 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 2/21/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/3/2020 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/4/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/5/2020 Conditional Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 3/5/2020 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/6/2020 Conditional Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 3/6/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/9/2020 Conditional Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 3/9/2020 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/12/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/12/2020 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 3/12/2020 Conditional Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 3/12/2020 Not Ready for Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 3/13/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/16/2020 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 3/16/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/18/2020 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/18/2020 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 3/18/2020 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/19/2020 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/19/2020 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/20/2020 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/20/2020 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 3/20/2020 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 3/23/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/24/2020 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 3/24/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/25/2020 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 4/16/2020 Partial Approval DANIEL MC AULIFFE
Wood Frame 7/30/2020 Partial Inspection DANIEL MC AULIFFE
Wood Frame 8/12/2020 Partial Inspection DANIEL MC AULIFFE
Wood Frame 9/8/2020 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Partial Inspection DANIEL MC AULIFFE