5221-5223 N CAMPO ROAD 91364

Certificate Information: 5221-5223 N CAMPO ROAD 91364

Application / Permit
17010-10002-02281
Plan Check / Job No.
B24LA03521
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO : 17010-20000-02281 CONVERT STORAGE/ PARKING SPACE / CRAWL SPACE TO Attached ADU per LAMC 12.22A.33(c) and (e)
Permit Issued
Issued on 11/13/2024
Issuing Office
Valley
Current Status
Permit Finaled on 4/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2024 APPLICANT
Assigned to Plan Check Engineer 2/29/2024 MARCELA FRANQUEZ
Corrections Issued 3/2/2024 MARCELA FRANQUEZ
Quality Review Completed 3/8/2024 KEN GILL
Building Plans Picked Up 3/12/2024 APPLICANT
Plan Check Approved 5/6/2024 MARCELA FRANQUEZ
Issued 11/13/2024 APPLICANT
Permit Finaled 4/24/2025 JOHN HAYES

Permit Application Clearance Information

Address approval Cleared 3/13/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 3/13/2024 CARLOS RAMIREZ
Sewer availability Cleared 3/13/2024 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 3/29/2024 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Abrahamian,, Zaven; Lic. No.: C41672 237 S LAMER ST      BURBANK, CA 91506
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/18/2024 Approved JOHN HAYES
Wood Frame 11/18/2024 Not Ready for Inspection JOHN HAYES
Deputy Drilled-In Anchors 11/19/2024 Conditional Approval JOHN HAYES
Footing/Foundation/Slab 11/20/2024 Approved JOHN HAYES
BUILDING-Rough-Frame 12/24/2024 Approved JOHN HAYES
ELECTRICAL-Rough 12/24/2024 Approved JOHN HAYES
HVAC-Rough 12/24/2024 Approved JOHN HAYES
PLUMBING-Rough 12/24/2024 Approved JOHN HAYES
Insulation 12/30/2024 Not Ready for Inspection JOHN HAYES
Insulation 1/3/2025 Approved SEAN WIRCH
Drywall Nailing 1/21/2025 Approved SEAN WIRCH
ELECTRICAL-Final 3/26/2025 Corrections Issued JOHN COLEMAN
Final 3/26/2025 Corrections Issued JOHN COLEMAN
HVAC-Final 3/26/2025 Approved JOHN COLEMAN
PLUMBING-Final 3/26/2025 Partial Inspection JOHN COLEMAN
Smoke Detectors 3/26/2025 Approved JOHN COLEMAN
Final 4/9/2025 Corrections Issued JOHN HAYES
Final 4/24/2025 Permit Finaled JOHN HAYES