8727 S BROADWAY 1-76 90003

Certificate Information: 8727 S BROADWAY 1-76 90003

Application / Permit
17010-10000-05023
Plan Check / Job No.
B17LA23434
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 4 story, type VA, 76 unit- apartment building over 1 story, type IA, parking garage. Transit Oriented Communities, 100% affordable project.
Permit Issued
Issued on 8/16/2023
Issuing Office
Metro
Current Status
Issued on 8/16/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/22/2017 APPLICANT
Assigned to Plan Check Engineer 12/28/2017 JOHN VASQUEZ
Corrections Issued 1/8/2018 JOHN VASQUEZ
Quality Review Completed 1/8/2018 JOHN VASQUEZ
Building Plans Picked Up 1/12/2018 APPLICANT
Disabled Access Plans Picked Up 1/12/2018 APPLICANT
Green Plans Picked Up 1/12/2018 APPLICANT
Applicant returned to address corrections 12/30/2019 JOHN VASQUEZ
Applicant returned to address corrections 9/22/2020 LARRY LEE
Applicant returned to address corrections 4/6/2021 LARRY LEE
Plan Check Approved 8/9/2023 KESETE HAREGOT
Plan Check Approved 8/9/2023 KESETE HAREGOT
Plan Check Approved 8/9/2023 KESETE HAREGOT
Issued 8/16/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/29/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 7/30/2020 ELAINE LEI
Driveway location Cleared 8/19/2020 COLLINS ALLAN
Internal circulation Cleared 8/19/2020 COLLINS ALLAN
Community Plan Implem. Overlay Cleared 12/29/2021 JEANETTE VONG
Sewer availability Cleared 4/13/2022 JEANETTE VONG
Highway dedication Cleared 4/19/2022 JEANETTE VONG
Permit Cleared 4/19/2022 JEANETTE VONG
Excavation more than 5-ft deep Cleared 6/1/2022 CALOSHA APPROVED
Hydrant and Access approval Cleared 10/4/2022 JOHN CONNEALLY
Bicycle Parking Cleared 4/18/2023 KATHERINE MENDOZA
Encroachment in public way Cleared 5/8/2023 KATHERINE MENDOZA
Project located in CRA area Cleared 5/18/2023 SUSAN WONG
Density Bonus 12.22.A.31 Cleared 5/23/2023 RICHARD TRUONG
Public Housing Cleared 5/23/2023 DANIEL COLLINS
Green Code Cleared 5/25/2023 AARON COSTA
Building over 3-story or 36-ft Cleared 5/30/2023 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 6/20/2023 DEAN RYAN REYES
Fire Marshall Fire Life Safety Cleared 6/21/2023 MENOA AGHAJANI
"Q" conditions Cleared 6/23/2023 STEVEN WECHSLER
DAS Clearance Cleared 6/23/2023 JOHN VASQUEZ
Miscellaneous Cleared 6/23/2023 STEVEN WECHSLER
Miscellaneous Cleared 6/23/2023 STEVEN WECHSLER
Opn space landscape/Water mgmt Cleared 6/23/2023 STEVEN WECHSLER
Prkng lot landscape/Water mgmt Cleared 6/23/2023 STEVEN WECHSLER
Site Plan review Cleared 6/25/2023 STEVEN WECHSLER
Low Impact Development Cleared 6/27/2023 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 6/27/2023 STEVE MELGAR
Stormwater Pollution Mitigatn Cleared 6/27/2023 AMMAR ELTAWIL

Contact Information

Architect Mutlow, John V; Lic. No.: C8816 2536 N VERMONT AVENUE      LOS ANGELES, CA 90027
Contractor Bernards Bros Inc; Lic. No.: 302007-B 555 FIRST STREET      SAN FERNANDO, CA 91340
Engineer Arca,, Perfecto; Lic. No.: C28918 23222 ROSANNA COURT      TORRANCE, CA 90502
Engineer Berliner,, Neal David; Lic. No.: GE2576 4913 MONUMENT ST      SIMI VALLEY, CA 93063
Engineer Yeh,, Ming Yang; Lic. No.: S2587 1613 CHELSEA ROAD   #233    SAN MARINO, CA 91108
Landscape Architect Spitz,, Katherine J.; Lic. No.: LA3846 4175 SUNSET LANE      PEBBLE BEACH, CA 93953

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/11/2023 Not Ready for Inspection JAMES POWERS
Grading Pre-Inspection 9/11/2023 Approved JAMES POWERS
Pre-Inspection 9/11/2023 Partial Approval JAMES POWERS
Pre-Inspection 10/16/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 4/8/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/25/2024 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/25/2024 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/29/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/2/2024 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/2/2024 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/3/2024 Pending Review
Footing/Foundation/Slab 5/8/2024 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/20/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/22/2024 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/22/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/23/2024 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 5/23/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/3/2024 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 6/3/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/21/2024 Conditional Approval ADAM BURGESS
Green Building Rough 6/26/2024 Not Ready for Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 6/26/2024 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 6/26/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/26/2024 Not Ready for Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 7/1/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 7/9/2024 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 7/10/2024 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 7/10/2024 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 7/11/2024 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 7/11/2024 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 7/19/2024 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 7/23/2024 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 7/24/2024 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 8/2/2024 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 8/9/2024 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 9/26/2024 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 9/26/2024 Partial Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 9/30/2024 Partial Approval RAFAEL CORTES
Special/Order Compliance 10/9/2024 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 10/16/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/28/2024 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 10/28/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 11/7/2024 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 11/7/2024 Not Ready for Inspection RAFAEL CORTES
Deputy Wood Construction 11/12/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Partial Approval RAFAEL ESPINOZA
Green Building Rough 11/12/2024 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/12/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 11/12/2024 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/14/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 11/14/2024 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/2/2024 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 12/2/2024 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/4/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/5/2024 Partial Approval RAFAEL ESPINOZA
Wall Anchors 12/5/2024 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 12/10/2024 Not Ready for Inspection RAFAEL CORTES
Wall Anchors 12/10/2024 Not Ready for Inspection RAFAEL CORTES
Insulation 12/11/2024 Partial Approval RAFAEL ESPINOZA
Wall Anchors 12/11/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Not Ready for Inspection RAFAEL CORTES
Insulation 12/13/2024 Partial Approval RAFAEL CORTES
Verify Sprinkler Sign Off 12/13/2024 Not Ready for Inspection RAFAEL CORTES
Wall Anchors 12/13/2024 Partial Approval RAFAEL CORTES
Wood Frame 12/13/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 12/16/2024 Partial Approval ALFREDO LOPEZ
Insulation 12/17/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 12/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wall Anchors 12/17/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 12/17/2024 Partial Approval RAFAEL ESPINOZA
Insulation 12/19/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 12/19/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wall Anchors 12/19/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 12/20/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/2/2025 Partial Approval RAFAEL CORTES
Insulation 1/6/2025 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Partial Approval RAFAEL CORTES
Verify Sprinkler Sign Off 1/7/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 1/7/2025 Partial Approval RAFAEL CORTES
Insulation 1/10/2025 Not Ready for Inspection JAMES POWERS
Wall Anchors 1/10/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/13/2025 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 1/13/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 1/13/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 1/15/2025 Not Ready for Inspection RAFAEL CORTES
Insulation 1/15/2025 Partial Approval RAFAEL CORTES
Structural Steel Frame 1/17/2025 No Access for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 1/17/2025 No Access for Inspection RAFAEL CORTES
Wood Frame 1/17/2025 No Access for Inspection RAFAEL CORTES
Deputy Wood Construction 1/22/2025 Conditional Approval RAFAEL ESPINOZA
Structural Steel Frame 1/22/2025 Partial Approval RAFAEL ESPINOZA
Wood Frame 1/22/2025 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Partial Approval RAFAEL CORTES
Insulation 1/27/2025 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/27/2025 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 1/27/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 2/4/2025 Partial Approval RAFAEL ESPINOZA
Insulation 2/4/2025 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 2/10/2025 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 2/12/2025 Partial Inspection RAFAEL ESPINOZA
Insulation 2/12/2025 Partial Approval RAFAEL ESPINOZA
Insulation 2/13/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 2/19/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 2/19/2025 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 2/21/2025 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/21/2025 Partial Inspection RAFAEL ESPINOZA
Wood Frame 2/21/2025 Partial Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/25/2025 No Access for Inspection RAFAEL CORTES
Wood Frame 2/25/2025 No Access for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/5/2025 Partial Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/17/2025 Partial Inspection RAFAEL ESPINOZA
Wood Frame 3/17/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/24/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 3/24/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 3/25/2025 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/27/2025 Partial Inspection RAFAEL ESPINOZA
Wood Frame 3/27/2025 Partial Inspection RAFAEL ESPINOZA
Insulation 4/9/2025 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/9/2025 Partial Inspection RAFAEL ESPINOZA
Wood Frame 4/9/2025 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 4/10/2025 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 4/10/2025 Partial Approval RAFAEL CORTES
Special/Order Compliance 4/10/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 4/11/2025 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/11/2025 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/11/2025 Partial Inspection RAFAEL ESPINOZA
Wood Frame 4/11/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/15/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/17/2025 Partial Approval RAFAEL ESPINOZA
Insulation 4/17/2025 Partial Approval RAFAEL ESPINOZA
Insulation 4/18/2025 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/25/2025 Partial Approval RAFAEL ESPINOZA
Wood Frame 4/25/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/28/2025 Partial Approval RAFAEL ESPINOZA
Insulation 4/28/2025 Partial Approval RAFAEL ESPINOZA
Insulation 4/29/2025 Partial Inspection RAFAEL ESPINOZA
Insulation 5/1/2025 Partial Approval RAFAEL ESPINOZA
Insulation 5/5/2025 Partial Approval RAFAEL CORTES
Special/Order Compliance 5/8/2025 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 5/8/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 5/8/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 5/12/2025 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 5/12/2025 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 5/14/2025 Partial Approval RAFAEL ESPINOZA
Insulation 5/19/2025 Partial Approval RAFAEL ESPINOZA
Insulation 5/21/2025 Partial Approval RAFAEL CORTES
Insulation 5/22/2025 Partial Inspection RAFAEL ESPINOZA
Insulation 5/27/2025 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 5/27/2025 Partial Approval RAFAEL ESPINOZA
Insulation 5/30/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 5/30/2025 Not Ready for Inspection RAFAEL CORTES
Insulation 6/2/2025 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 6/2/2025 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 6/3/2025 Partial Approval RAFAEL ESPINOZA
Insulation 6/3/2025 Partial Approval RAFAEL ESPINOZA
Insulation 6/4/2025 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 6/4/2025 Partial Approval RAFAEL ESPINOZA
Insulation 6/6/2025 Partial Approval RAFAEL ESPINOZA
Insulation 6/10/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/16/2025 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/17/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/20/2025 Partial Approval RAFAEL ESPINOZA
Insulation 6/20/2025 Partial Approval RAFAEL ESPINOZA
Insulation 6/24/2025 Partial Approval RAFAEL ESPINOZA
Insulation 6/26/2025 Partial Approval JAMES POWERS
Drywall Nailing 6/27/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 7/2/2025 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/10/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/1/2025 Corrections Issued RAFAEL CORTES
Light Gage Steel Frame 8/14/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 8/15/2025 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/20/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 8/22/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 8/27/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 8/27/2025 Not Ready for Inspection RAFAEL CORTES
Special/Order Compliance 8/27/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 8/29/2025 Approved RAFAEL CORTES
Drywall Nailing 9/24/2025 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 10/2/2025 Conditional Approval RAFAEL CORTES
Insulation 10/20/2025 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 10/20/2025 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 11/10/2025 Partial Approval JOEY BUCHANAN
Special/Order Compliance 12/4/2025 Not Ready for Inspection JOEY BUCHANAN