3285 W LARGA AVE 90039

Certificate Information: 3285 W LARGA AVE 90039

Application / Permit
17010-10000-04996
Plan Check / Job No.
B17LA23284
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW RECREATION ROOM WITH ATTACHED CARPORT & SHOWER ROOM , WITH EXTERIOR ACCESS DOOR , FOR FUTURE SPA .
Permit Issued
Issued on 5/25/2018
Issuing Office
Metro
Current Status
CofO Issued on 5/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2017 APPLICANT
Assigned to Plan Check Engineer 1/16/2018 GEORGE BANNING
Corrections Issued 1/16/2018 GEORGE BANNING
Plan Check Approved 2/20/2018 GEORGE BANNING
Issued 5/25/2018 LADBS
CofO in Progress 8/1/2019 HAMIK HARTOUNIAN
No Progress 11/7/2019 HAMIK HARTOUNIAN
CofO in Progress 12/11/2019 HAMIK HARTOUNIAN
No Progress 12/31/2019 HAMIK HARTOUNIAN
CofO in Progress 5/28/2020 ELMER BLAND
Permit Finaled 5/29/2020 DEROLD HAUFF
CofO Issued 5/29/2020 DEROLD HAUFF
Permit Finaled 5/29/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/16/2018 STEVE MELGAR
Grading Pre-Inspection Cleared 1/16/2018 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 1/16/2018 STEVE MELGAR
Sewer availability Cleared 1/16/2018 STEVE MELGAR
ZI Cleared 1/16/2018 BRIAN CARR

Contact Information

Contractor Casa Vieja Contractors; Lic. No.: 841092-B 16357 TRIBUNE STREET      GRANADA HILLS, CA 91344
Engineer Parker, Leo Augustine; Lic. No.: S2829 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/13/2018 Approved LUIS ALVAREZ
Underground Mechanical 6/13/2018 Approved LUIS ALVAREZ
Footing/Foundation/Slab 7/11/2018 Not Ready for Inspection LUIS ALVAREZ
Footing/Foundation/Slab 7/12/2018 Approved LUIS ALVAREZ
Sewer 7/20/2018 Approved LUIS ALVAREZ
ELECTRICAL-Rough 9/24/2018 Not Ready for Inspection FRANCISCO MORADO
PLUMBING-Rough 9/24/2018 Not Ready for Inspection FRANCISCO MORADO
ELECTRICAL-Rough 10/2/2018 Approved FRANCISCO MORADO
Floor/Roof Diaphrgm/Shear Wall 10/2/2018 Partial Approval FRANCISCO MORADO
PLUMBING-Rough 10/22/2018 Approved FRANCISCO MORADO
Interior/Exterior Lathing 10/23/2018 Partial Inspection RUBEN SALAS
Green Building Rough 10/24/2018 Approved RUBEN SALAS
PLUMBING-Rough 10/24/2018 Approved RUBEN SALAS
Wood Frame 10/24/2018 Approved RUBEN SALAS
Insulation 10/25/2018 Approved CRAIG VAUGHAN
HVAC-Rough 11/19/2018 Not Ready for Inspection BRIAN SULLIVAN
Shower Pan 11/19/2018 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 11/21/2018 Approved RUBEN SALAS
Drywall Nailing 12/11/2018 Approved FRANCISCO MORADO
HVAC-Final 2/15/2019 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 2/15/2019 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 2/20/2019 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 2/22/2019 Approved HAMIK HARTOUNIAN
HVAC-Final 2/22/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 3/5/2019 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/18/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Final 7/18/2019 No Access for Inspection HAMIK HARTOUNIAN
Green Building Final 7/18/2019 No Access for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/18/2019 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 7/18/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 7/18/2019 No Access for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 7/18/2019 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/1/2019 Approved HAMIK HARTOUNIAN
Final 8/1/2019 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 8/1/2019 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/1/2019 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 8/1/2019 Approved HAMIK HARTOUNIAN
Smoke Detectors 8/1/2019 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 8/1/2019 Approved HAMIK HARTOUNIAN
Special/Order Compliance 12/4/2019 Corrections Issued HAMIK HARTOUNIAN