428 S ROBERTSON BLVD 1-37 90048

Certificate Information: 428 S ROBERTSON BLVD 1-37 90048

Application / Permit
17010-10000-04994
Plan Check / Job No.
B17LA23269
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 6-story over basement 37 Unit apartment building; 5-story 36,872 sf Type III-A Apartment over on-grade Type I-A 8,388 sf garage, over 9,346 sub-terranean garage. Development is utilizing TOC Teir 1 guideilnes and incentives.
Permit Issued
Issued on 7/12/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2017 APPLICANT
Green Plans Picked Up 1/16/2018 APPLICANT
Assigned to Plan Check Engineer 1/18/2018 KRIKOR MANOUKIAN
Disabled Access Plans Picked Up 1/26/2018 APPLICANT
Corrections Issued 2/16/2018 KRIKOR MANOUKIAN
Quality Review Completed 3/8/2018 SHUNYU ZHANG
Building Plans Picked Up 3/15/2018 APPLICANT
Applicant returned to address corrections 4/24/2018 KRIKOR MANOUKIAN
Plan Check Approved 7/12/2018 KRIKOR MANOUKIAN
Issued 7/12/2018 LADBS
CofO in Progress 6/16/2020 DAVID BURKHEAD
CofO Issued 6/18/2020 DAVID TSAU
Permit Finaled 6/18/2020 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 3/19/2018 JAMES KHO
Highway dedication Cleared 4/27/2018 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 5/7/2018 JAMES KHO
Sewer availability Cleared 5/7/2018 JAMES KHO
"Q" conditions Cleared 6/13/2018 DIANA JIMENEZ
Green Code Cleared 6/13/2018 SARKIS HARABEDIAN
Permit Cleared 6/13/2018 JAMES KHO
ZA Case Cleared 6/13/2018 DIANA JIMENEZ
Density Bonus 12.22.A.31 Cleared 6/14/2018 MICHAEL ZIRBES
Low Impact Development Cleared 6/25/2018 SAM NAVID
Roof/Waste drainage to street Cleared 6/25/2018 JAMES KHO
Fire Marshall Fire Life Safety Cleared 6/28/2018 WILLIAM JOHNS
Hydrant and Access approval Cleared 6/28/2018 GEORGE SUCHAND
DAS Clearance Cleared 7/2/2018 WAI LAU
Driveway location Cleared 7/3/2018 JOHNATHAN YU
Frnt yard landscape/Water mgmt Cleared 7/3/2018 SEAN VEAL
Miscellaneous Cleared 7/3/2018 SEAN VEAL
Opn space landscape/Water mgmt Cleared 7/3/2018 SEAN VEAL
Prkng lot landscape/Water mgmt Cleared 7/3/2018 SEAN VEAL
Work Adjacent to Public Way Cleared 7/3/2018 ADRIAN SANCHEZ
Methane Ordinance Cleared 7/11/2018 WILLIAM JOHNS
Building over 3-story or 36-ft Cleared 7/12/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 7/12/2018 CALOSHA APPROVED

Contact Information

Architect Uriu, Giovanni; Lic. No.: C7487 830 SO GLENDALE AVENUE      GLENDALE, CA 91205
Contractor Owner-Builder       ,
Engineer Downey, Henry Ross; Lic. No.: S2628 7463 VARNA AVE      NORTH HOLLYWOOD, CA 916054011
Engineer Minas, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Geologist , ; Lic. No.: EG2607 566 RIVERDALE DRIVE      GLENDALE, CA 91204

Inspector Information

ALFREDO LOPEZ, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 7/17/2018 Conditional Approval GREGORY POMISH
Pre-Inspection 7/17/2018 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 7/23/2018 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 9/25/2018 Conditional Approval LARRY ARNICK
Deputy Methane Barrier 9/27/2018 Conditional Approval LARRY ARNICK
Deputy Methane Barrier 9/28/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 9/28/2018 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 9/28/2018 Not Ready for Inspection LARRY ARNICK
METHANE-Barrier 9/28/2018 Not Ready for Inspection LARRY ARNICK
METHANE-Subgrade 9/28/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 10/2/2018 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 10/2/2018 Partial Approval LARRY ARNICK
Deputy Methane Barrier 10/4/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 10/4/2018 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/4/2018 Approved LARRY ARNICK
Footing/Foundation/Slab 10/4/2018 Not Ready for Inspection LARRY ARNICK
METHANE-Barrier 10/4/2018 Not Ready for Inspection LARRY ARNICK
METHANE-Subgrade 10/4/2018 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/5/2018 Off-Hour Fees Due
Green Building Rough 10/5/2018 Off-Hour Fees Due
METHANE-Rough 10/5/2018 Off-Hour Fees Due
Reinforced Concrete Frame 10/5/2018 Off-Hour Fees Due
Verify Sprinkler Sign Off 10/5/2018 Off-Hour Fees Due
Deputy Methane Barrier 10/15/2018 Conditional Approval LARRY ARNICK
Deputy Methane Barrier 10/16/2018 Conditional Approval LARRY ARNICK
Deputy Methane Barrier 10/17/2018 Conditional Approval LARRY ARNICK
Deputy Methane Barrier 10/18/2018 Conditional Approval LARRY ARNICK
Deputy Methane Barrier 10/19/2018 Conditional Approval LARRY ARNICK
Deputy Methane Barrier 10/22/2018 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 10/23/2018 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 10/24/2018 Conditional Approval GREGORY POMISH
METHANE-Subgrade 10/24/2018 Partial Inspection GREGORY POMISH
Deputy Methane Barrier 10/25/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/8/2018 Approved GREGORY POMISH
Footing/Foundation/Slab 11/8/2018 Partial Approval GREGORY POMISH
METHANE-Barrier 11/8/2018 Approved GREGORY POMISH
METHANE-Subgrade 11/8/2018 Approved GREGORY POMISH
Deputy Methane Barrier 11/21/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 11/26/2018 Approved GREGORY POMISH
Deputy Reinf. Concrete 11/27/2018 Approved GREGORY POMISH
Deputy Shotcrete 11/28/2018 Approved GREGORY POMISH
Deputy Shotcrete 11/30/2018 Approved GREGORY POMISH
Green Building Rough 12/5/2018 Not Ready for Inspection JONATHAN QUACH
METHANE-Rough 12/5/2018 Not Ready for Inspection JONATHAN QUACH
Reinforced Concrete Frame 12/5/2018 Partial Approval JONATHAN QUACH
Verify Sprinkler Sign Off 12/5/2018 Not Ready for Inspection JONATHAN QUACH
Deputy Reinf. Concrete 12/7/2018 Conditional Approval LARRY ARNICK
Deputy Shotcrete 12/7/2018 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 12/11/2018 No Access for Inspection LARRY ARNICK
Deputy Reinf. Concrete 12/12/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 12/13/2018 Conditional Approval LARRY ARNICK
Green Building Rough 12/13/2018 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 12/13/2018 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 12/13/2018 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 12/13/2018 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 12/17/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/4/2019 Approved GREGORY POMISH
Deputy Reinf. Concrete 1/10/2019 Approved GREGORY POMISH
Footing/Foundation/Slab 1/10/2019 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 1/24/2019 Approved GREGORY POMISH
Deputy Reinf. Concrete 1/25/2019 Approved GREGORY POMISH
Footing/Foundation/Slab 1/25/2019 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/28/2019 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 1/28/2019 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 1/30/2019 Partial Approval GREGORY POMISH
Green Building Rough 1/31/2019 Not Ready for Inspection GREGORY POMISH
METHANE-Rough 1/31/2019 Approved GREGORY POMISH
Reinforced Concrete Frame 1/31/2019 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 1/31/2019 Not Ready for Inspection GREGORY POMISH
Deputy Shotcrete 2/1/2019 Approved GREGORY POMISH
Deputy Reinf. Concrete 2/25/2019 Approved GREGORY POMISH
Footing/Foundation/Slab 2/25/2019 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 2/26/2019 Approved GREGORY POMISH
Deputy Reinf. Concrete 2/28/2019 Approved GREGORY POMISH
Deputy Reinf. Concrete 3/1/2019 Approved GREGORY POMISH
Footing/Foundation/Slab 3/1/2019 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 3/4/2019 Approved GREGORY POMISH
Footing/Foundation/Slab 3/12/2019 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 3/22/2019 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 4/2/2019 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/9/2019 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 4/15/2019 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/25/2019 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/10/2019 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/28/2019 Corrections Issued LARRY ARNICK
Deputy Wood Construction 5/29/2019 Partial Approval JAMES POWERS
Green Building Rough 5/29/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 5/29/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 5/29/2019 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/31/2019 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 6/3/2019 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 6/3/2019 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 6/3/2019 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 6/4/2019 Partial Approval DAVID BURKHEAD
Insulation 6/5/2019 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 6/10/2019 Partial Approval LARRY ARNICK
Insulation 6/10/2019 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/11/2019 Partial Approval LARRY ARNICK
Drywall Nailing 6/14/2019 Partial Approval LARRY ARNICK
Green Building Rough 6/14/2019 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/26/2019 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 6/28/2019 Partial Inspection HAMID PISHEHVAR
Drywall Nailing 7/5/2019 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/5/2019 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 7/5/2019 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/8/2019 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 7/8/2019 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 7/9/2019 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/9/2019 Partial Approval DAVID BURKHEAD
Green Building Rough 7/9/2019 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 7/12/2019 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/12/2019 Partial Approval DAVID BURKHEAD
Green Building Rough 7/12/2019 Approved DAVID BURKHEAD
Insulation 7/12/2019 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 7/12/2019 Partial Approval DAVID BURKHEAD
Wood Frame 7/12/2019 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/16/2019 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/22/2019 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/23/2019 Not Ready for Inspection DAVID BURKHEAD
Insulation 7/23/2019 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/29/2019 Partial Approval DAVID BURKHEAD
Insulation 7/29/2019 Not Ready for Inspection DAVID BURKHEAD
Insulation 7/30/2019 Partial Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/7/2019 Partial Approval DAVID BURKHEAD
Insulation 8/20/2019 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/26/2019 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 9/6/2019 Partial Inspection DAVID BURKHEAD
Insulation 9/11/2019 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 9/11/2019 Not Ready for Inspection DAVID BURKHEAD
Insulation 9/13/2019 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 9/13/2019 Partial Approval DAVID BURKHEAD
Insulation 9/18/2019 Not Ready for Inspection DAVID BURKHEAD
Insulation 9/20/2019 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 9/20/2019 Approved DAVID BURKHEAD
Wood Frame 9/20/2019 Partial Approval DAVID BURKHEAD
Insulation 9/23/2019 Partial Approval DAVID BURKHEAD
Wood Frame 9/23/2019 Partial Approval DAVID BURKHEAD
Drywall Nailing 9/27/2019 Partial Approval DAVID BURKHEAD
Insulation 9/30/2019 Partial Approval DAVID BURKHEAD
Drywall Nailing 10/3/2019 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 10/3/2019 Partial Approval DAVID BURKHEAD
Drywall Nailing 10/8/2019 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 10/8/2019 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 10/10/2019 Partial Inspection DAVID BURKHEAD
Drywall Nailing 10/16/2019 Partial Approval RUSSELL BONVOULOIR
Insulation 10/16/2019 Partial Approval RUSSELL BONVOULOIR
Interior/Exterior Lathing 10/16/2019 Partial Approval RUSSELL BONVOULOIR
Interior/Exterior Lathing 10/18/2019 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 10/25/2019 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 10/25/2019 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 10/28/2019 Partial Approval DAVID BURKHEAD
Wood Frame 10/28/2019 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 11/1/2019 Approved DAVID BURKHEAD
Light Gage Steel Frame 12/20/2019 Partial Approval JAMES POWERS
Pre-Inspection 3/31/2020 Approved JONATHAN QUACH
Drywall Nailing 4/8/2020 Approved DAVID BURKHEAD
Final 4/8/2020 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 4/8/2020 Not Ready for Inspection JONATHAN QUACH
Green Building Final 4/8/2020 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 4/8/2020 Not Ready for Inspection JONATHAN QUACH
Reinforced Masonry Frame 4/8/2020 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 4/8/2020 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 4/8/2020 Not Ready for Inspection JONATHAN QUACH
Structural Steel Frame 4/8/2020 Not Ready for Inspection JONATHAN QUACH
Wood Frame 4/8/2020 Not Ready for Inspection JONATHAN QUACH
Final 5/11/2020 Partial Inspection JONATHAN QUACH
Footing/Foundation/Slab 5/11/2020 Approved JONATHAN QUACH
Green Building Final 5/11/2020 Not Ready for Inspection JONATHAN QUACH
Reinforced Concrete Frame 5/11/2020 Approved JONATHAN QUACH
Reinforced Masonry Frame 5/11/2020 Approved JONATHAN QUACH
Smoke Detectors 5/11/2020 Not Ready for Inspection JONATHAN QUACH
Structural Steel Frame 5/11/2020 Approved JONATHAN QUACH
Wood Frame 5/11/2020 Approved JONATHAN QUACH
Final 5/29/2020 Not Ready for Inspection LARRY ARNICK
Green Building Final 5/29/2020 Not Ready for Inspection LARRY ARNICK
Smoke Detectors 5/29/2020 Not Ready for Inspection LARRY ARNICK
Green Building Final 6/2/2020 Partial Approval JONATHAN QUACH
Final 6/3/2020 Not Ready for Inspection JONATHAN QUACH
Smoke Detectors 6/3/2020 Not Ready for Inspection JONATHAN QUACH
Special/Order Compliance 6/3/2020 Approved DAVID BURKHEAD
Final 6/8/2020 Conditional Approval JONATHAN QUACH
Green Building Final 6/8/2020 Approved JONATHAN QUACH
Smoke Detectors 6/8/2020 Approved JONATHAN QUACH
Pre-Inspection 6/12/2020 Partial Inspection JONATHAN QUACH
Special/Order Compliance 6/12/2020 Conditional Approval DAVID BURKHEAD
Final 6/16/2020 OK to Issue CofO DAVID BURKHEAD