9227 N TUJUNGA AVE 91352

Certificate Information: 9227 N TUJUNGA AVE 91352

Application / Permit
17010-10000-04979
Plan Check / Job No.
B17LA23170
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(15) Refuse Transfer Station
Work Description
NEW 228'X600', 3 STORY, SPECIAL INDUSTRIAL OCCUPANCY, TRANSFER STATION AND MATERIAL RECOVERY FACILITY METAL BUILDING WITH OFFICE AND MAINTENANCE.
Permit Issued
Issued on 8/28/2019
Issuing Office
Metro
Current Status
Issued on 8/28/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/31/2018 APPLICANT
Disabled Access Plans Picked Up 2/12/2018 APPLICANT
Assigned to Plan Check Engineer 3/1/2018 KESETE HAREGOT
Corrections Issued 3/5/2018 KESETE HAREGOT
Quality Review Completed 3/8/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 3/12/2018 APPLICANT
Green Plans Picked Up 3/14/2018 APPLICANT
Applicant returned to address corrections 4/17/2018 KESETE HAREGOT
Applicant returned to address corrections 12/5/2018 KESETE HAREGOT
Applicant returned to address corrections 1/24/2019 KESETE HAREGOT
Applicant returned to address corrections 3/7/2019 KESETE HAREGOT
Applicant returned to address corrections 8/23/2019 KESETE HAREGOT
Plan Check Approved 8/23/2019 KESETE HAREGOT
Issued 8/28/2019 LADBS
TCO Issued (Expire Date: 04-05-2021) 10/7/2020 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 3/16/2018 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 3/16/2018 JOHN LIN
Highway dedication Cleared 3/16/2018 JOHN LIN
Hydrant and Access approval Cleared 3/16/2018 JOHN DALLAS
Permit Cleared 3/16/2018 JOHN LIN
Building over 3-story or 36-ft Cleared 6/19/2018 CALOSHA APPROVED
Sewer availability Cleared 11/27/2018 LEE GUILBEAUX
Frnt yard landscape/Water mgmt Cleared 12/5/2018 IVORY CHAMBESHI
Miscellaneous Cleared 12/5/2018 IVORY CHAMBESHI
Miscellaneous Cleared 12/5/2018 IVORY CHAMBESHI
Prkng lot landscape/Water mgmt Cleared 12/5/2018 IVORY CHAMBESHI
ZI Cleared 12/5/2018 IVORY CHAMBESHI
ZI Cleared 12/5/2018 IVORY CHAMBESHI
Stormwater Pollution Mitigatn Cleared 12/11/2018 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 12/12/2018 JULIUS GARCIA
Low Impact Development Cleared 12/13/2018 AMMAR ELTAWIL
DAS Clearance Cleared 3/7/2019 KESETE HAREGOT
Flood clearance Cleared 3/14/2019 SYLVIA DHIMDIS
Green Code Cleared 4/24/2019 COLIN LOREDO
High storage rack Cleared 8/15/2019 OSCAR SALGADO JR
CPC Cleared 8/22/2019 BRIDGETTE WOOTEN
Site Plan review Cleared 8/22/2019 BRIDGETTE WOOTEN

Contact Information

Architect Kleiner,, Eric L; Lic. No.: C18874 1708 41ST STREET      SACRAMENTO, CA 95819
Contractor E T Environmental California Inc; Lic. No.: 921054-A 3424 PEACHTREE ROAD NE   SUITE 150    ATLANTA, GA 30326
Engineer Burkhart,, Thomas Alfred; Lic. No.: S4378 4080 PLAZA GOLDORADO CIRCLE SUITE B      CAMERON PARK, CA 95682
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384
Engineer Welschmeyer,, Jeremy Landrum; Lic. No.: C82293 2708 NW 86TH ST      KANSAS CITY, MO 64154

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/16/2019 Partial Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 9/18/2019 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 9/23/2019 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 9/26/2019 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 9/26/2019 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 9/26/2019 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/26/2019 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 10/9/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/10/2019 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/11/2019 Conditional Approval RICKEY JACKSON
Deputy Steel/Welding 10/23/2019 Conditional Approval DANNY RODRIGUEZ
METHANE-Barrier 10/28/2019 Partial Approval ROBERT COLE
Deputy Steel/Welding 11/20/2019 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/12/2019 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 12/12/2019 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/13/2019 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 12/13/2019 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 1/7/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/7/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/15/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/16/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/17/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 1/23/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/23/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/24/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 1/24/2020 Conditional Approval JAMES STEPHENS
Deputy Steel/Welding 1/29/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/30/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/30/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/6/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/10/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/11/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/12/2020 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/25/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 3/4/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 3/12/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 3/17/2020 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 3/17/2020 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 3/17/2020 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 3/17/2020 Partial Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/17/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 3/27/2020 Conditional Approval ROBERT COLE
Deputy Steel/Welding 3/27/2020 Conditional Approval ROBERT COLE
Deputy Steel/Welding 4/2/2020 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 4/3/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 4/8/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Partial Approval DANNY RODRIGUEZ
Insulation 4/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 4/16/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 4/20/2020 Approved HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 4/24/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 4/24/2020 Partial Approval JONATHAN QUACH
METHANE-Rough 4/24/2020 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 4/29/2020 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/29/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Fireproofing 4/30/2020 Approved DANNY RODRIGUEZ
Green Building Rough 4/30/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 4/30/2020 Partial Approval DANNY RODRIGUEZ
METHANE-Rough 4/30/2020 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/30/2020 Partial Inspection DANNY RODRIGUEZ
Deputy Fireproofing 5/1/2020 Conditional Approval JEFFREY DURAN
Insulation 5/4/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/6/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/8/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/11/2020 Partial Approval DANNY RODRIGUEZ
Insulation 5/11/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/13/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/15/2020 Approved JOE VELASQUEZ
Deputy Steel/Welding 5/19/2020 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/19/2020 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 5/19/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/21/2020 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/21/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 5/21/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/22/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 5/22/2020 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/27/2020 Partial Approval ROBERT COLE
Deputy Steel/Welding 6/2/2020 Approved DANNY RODRIGUEZ
Insulation 6/2/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 6/2/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/3/2020 Approved DANNY RODRIGUEZ
Deputy Drilled-In Anchors 6/4/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/4/2020 Approved DANNY RODRIGUEZ
Deputy Drilled-In Anchors 6/5/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/9/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/10/2020 Conditional Approval DANNY RODRIGUEZ
Drywall Nailing 6/10/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/11/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/12/2020 Approved HAMID PISHEHVAR
Footing/Foundation/Slab 6/12/2020 Partial Approval HAMID PISHEHVAR
Light Gage Steel Frame 6/12/2020 Approved HAMID PISHEHVAR
METHANE-Barrier 6/12/2020 Partial Approval HAMID PISHEHVAR
METHANE-Subgrade 6/12/2020 Partial Approval HAMID PISHEHVAR
Deputy Steel/Welding 6/16/2020 Approved DANNY RODRIGUEZ
Insulation 6/16/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 6/18/2020 Approved DANNY RODRIGUEZ
Drywall Nailing 6/18/2020 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/18/2020 Partial Approval DANNY RODRIGUEZ
Insulation 6/18/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/19/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/22/2020 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/22/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/23/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/24/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/25/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 6/25/2020 Approved DANNY RODRIGUEZ
Drywall Nailing 6/25/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 6/25/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/26/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 6/29/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 6/30/2020 Approved DANNY RODRIGUEZ
Drywall Nailing 7/1/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/2/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/7/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 7/7/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 7/9/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/13/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/13/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 7/13/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/14/2020 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/14/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/15/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/16/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/17/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 7/21/2020 Approved DANNY RODRIGUEZ
Drywall Nailing 7/21/2020 Partial Approval DANNY RODRIGUEZ
T-Bar Ceiling 7/21/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 7/22/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/24/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/27/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/29/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 7/29/2020 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/3/2020 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 8/3/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 8/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/7/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 8/7/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/11/2020 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/12/2020 Partial Approval JOHN KITCKO
Deputy Steel/Welding 8/14/2020 Approved DANNY RODRIGUEZ
Drywall Nailing 8/14/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/17/2020 Not Ready for Inspection HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 8/17/2020 Approved HAMID PISHEHVAR
Insulation 8/20/2020 Partial Approval SORIN CIRSTOIU
Deputy Steel/Welding 8/25/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/26/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/27/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/28/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/31/2020 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 9/1/2020 Partial Approval DANNY RODRIGUEZ
T-Bar Ceiling 9/1/2020 Partial Approval DANNY RODRIGUEZ
Insulation 9/2/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 9/3/2020 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 9/4/2020 Partial Approval JOE VELASQUEZ
Drywall Nailing 9/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 9/8/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/11/2020 Partial Approval DANNY RODRIGUEZ
T-Bar Ceiling 9/17/2020 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/21/2020 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 9/30/2020 Partial Inspection DANNY RODRIGUEZ
Final 10/6/2020 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 10/13/2020 Partial Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 10/27/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/28/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/29/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/30/2020 Conditional Approval DANNY RODRIGUEZ
Special/Order Compliance 11/9/2020 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/11/2021 Conditional Approval JEFFREY FULTON
Special/Order Compliance 2/3/2021 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 2/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 3/22/2021 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 5/2/2023 Partial Inspection DANNY RODRIGUEZ