944 S SERRANO AVE 1-32 90006
Certificate Information: 944 S SERRANO AVE 1-32 90006
- Application / Permit
- 17010-10000-04950
- Plan Check / Job No.
- B17LA23057
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- New 5 story, Type IIIA, 32 unit apartment over Type 1A, 1 story & 1 level subterranean parking garages. "Do not issue any permits for this address until AFTER April 14, 2019 per LADBS Scorched Earth Hearing. Contact Chief Inspector Frank Lara at (213)252-3310 if any questions. (Created: MONG / 04-05-17)"
- Permit Issued
- Issued on 5/2/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2018 | KESETE HAREGOT |
| Corrections Issued | 2/2/2018 | KESETE HAREGOT |
| Disabled Access Plans Picked Up | 2/7/2018 | APPLICANT |
| Quality Review Completed | 2/9/2018 | JOHN VASQUEZ |
| Green Plans Picked Up | 2/28/2018 | APPLICANT |
| Building Plans Picked Up | 3/1/2018 | APPLICANT |
| Applicant returned to address corrections | 4/27/2018 | KESETE HAREGOT |
| Applicant returned to address corrections | 5/4/2018 | KESETE HAREGOT |
| Applicant returned to address corrections | 5/17/2018 | KESETE HAREGOT |
| Applicant returned to address corrections | 4/25/2019 | KESETE HAREGOT |
| Plan Check Approved | 4/30/2019 | KESETE HAREGOT |
| Issued | 5/2/2019 | LADBS |
| TCO Issued (Expire Date: 07-05-2022) | 1/6/2022 | TED RIES |
| TCO Issued (Expire Date: 01-03-2023) | 7/7/2022 | ERNESTO CORRAL |
| TCO Issued (Expire Date: 07-08-2023) | 1/9/2023 | ERNESTO CORRAL |
| CofO in Progress | 1/24/2023 | RAFAEL ESPINOZA |
| CofO Issued | 2/22/2023 | ERNESTO CORRAL |
| Permit Finaled | 2/22/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 4/17/2018 | YOVANA PEREZ |
| Opn space landscape/Water mgmt | Cleared | 4/17/2018 | YOVANA PEREZ |
| Tract Map conditions | Cleared | 4/17/2018 | YOVANA PEREZ |
| Address approval | Cleared | 4/27/2018 | NAZILA NOORIFAR |
| Green Code | Cleared | 5/14/2018 | COLIN LOREDO |
| Internal circulation | Cleared | 6/13/2018 | MOHAMMAD HASAN |
| Historic monument | Cleared | 8/16/2018 | MELISSA JONES |
| Hydrant and Access approval | Cleared | 8/16/2018 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2018 | JEANETTE VONG |
| Fire Marshall Fire Life Safety | Cleared | 8/29/2018 | MENOA AGHAJANI |
| Low Impact Development | Cleared | 10/29/2018 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 10/29/2018 | STEVE MELGAR |
| DAS Clearance | Cleared | 11/30/2018 | EDDIE GARIN |
| Historical monument | Cleared | 12/18/2018 | JIM URQUHART |
| Project located in CRA area | Cleared | 12/18/2018 | JIM URQUHART |
| Highway dedication | Cleared | 1/31/2019 | LINDA MARGARET |
| Permit | Cleared | 1/31/2019 | LINDA MARGARET |
| Sewer availability | Cleared | 4/12/2019 | ELAINE LEI |
| Tract Map conditions | Cleared | 4/16/2019 | EDBER MACEDO |
| ZA Case | Cleared | 4/16/2019 | EDBER MACEDO |
| ZA Case | Cleared | 4/16/2019 | EDBER MACEDO |
| Building over 3-story or 36-ft | Cleared | 4/25/2019 | CALOSHA APPROVED |
Contact Information
| Architect | Kim,, Ik Poong; Lic. No.: C8449 | 1771 SUNNINGDALE RD #49G SEAL BEACH, CA 90740 |
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Taik Yul; Lic. No.: C40432 | 245 RENO ST 60 LOS ANGELES, CA 90057 |
| Engineer | Lee, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
| Engineer | Pukkanasut,, Jirayus; Lic. No.: C73728 | 15038 CLARK AVE HACIENDA HEIGHTS, CA 91745 |
| Landscape Architect | Kim,, David Dong-Sik; Lic. No.: LA2831 | 3000 W 6TH STREET SUITE 300 LOS ANGELES, CA 90020 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/31/2019 | Partial Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 11/6/2019 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 11/7/2019 | Conditional Approval | LESLIE TRUJILLO |
| Footing/Foundation/Slab | 11/7/2019 | Partial Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 11/8/2019 | Conditional Approval | LESLIE TRUJILLO |
| Green Building Rough | 11/8/2019 | Conditional Approval | LESLIE TRUJILLO |
| Reinforced Masonry Frame | 11/8/2019 | Partial Approval | LESLIE TRUJILLO |
| Verify Sprinkler Sign Off | 11/8/2019 | Conditional Approval | LESLIE TRUJILLO |
| Footing/Foundation/Slab | 11/14/2019 | Partial Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 11/15/2019 | Conditional Approval | LESLIE TRUJILLO |
| Footing/Foundation/Slab | 11/20/2019 | Not Ready for Inspection | LESLIE TRUJILLO |
| Green Building Rough | 11/22/2019 | Partial Approval | LESLIE TRUJILLO |
| Reinforced Masonry Frame | 11/22/2019 | Partial Approval | LESLIE TRUJILLO |
| Verify Sprinkler Sign Off | 11/22/2019 | Conditional Approval | LESLIE TRUJILLO |
| Green Building Rough | 11/26/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Reinforced Concrete Frame | 11/26/2019 | Partial Approval | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 11/26/2019 | Approved | DANIEL MC AULIFFE |
| Deputy Shotcrete | 12/5/2019 | Conditional Approval | LESLIE TRUJILLO |
| Green Building Rough | 12/5/2019 | Conditional Approval | LESLIE TRUJILLO |
| Reinforced Concrete Frame | 12/5/2019 | Partial Approval | LESLIE TRUJILLO |
| Deputy Shotcrete | 12/6/2019 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Shotcrete | 12/12/2019 | Conditional Approval | LESLIE TRUJILLO |
| Green Building Rough | 12/12/2019 | Conditional Approval | LESLIE TRUJILLO |
| Reinforced Concrete Frame | 12/12/2019 | Partial Approval | LESLIE TRUJILLO |
| Reinforced Masonry Frame | 12/17/2019 | Not Ready for Inspection | LESLIE TRUJILLO |
| Green Building Rough | 12/19/2019 | Conditional Approval | LESLIE TRUJILLO |
| Reinforced Concrete Frame | 12/19/2019 | Partial Approval | LESLIE TRUJILLO |
| Green Building Rough | 12/23/2019 | Conditional Approval | LESLIE TRUJILLO |
| Reinforced Masonry Frame | 12/23/2019 | Partial Inspection | LESLIE TRUJILLO |
| Green Building Rough | 12/30/2019 | Conditional Approval | LESLIE TRUJILLO |
| Reinforced Masonry Frame | 12/30/2019 | Partial Approval | LESLIE TRUJILLO |
| Reinforced Concrete Frame | 1/4/2020 | Conditional Approval | LESLIE TRUJILLO |
| Footing/Foundation/Slab | 1/24/2020 | Partial Approval | LESLIE TRUJILLO |
| Footing/Foundation/Slab | 2/20/2020 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 3/3/2020 | Partial Approval | RAFAEL ESPINOZA |
| Reinforced Concrete Frame | 3/5/2020 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 3/6/2020 | Partial Approval | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 3/12/2020 | Partial Approval | LESLIE TRUJILLO |
| Green Building Rough | 3/18/2020 | No Access for Inspection | RAFAEL ESPINOZA |
| Reinforced Masonry Frame | 3/18/2020 | Partial Approval | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 3/20/2020 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 4/20/2020 | Partial Inspection | RAFAEL ESPINOZA |
| Reinforced Concrete Frame | 4/22/2020 | Partial Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 5/5/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Wood Construction | 5/21/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Wood Construction | 5/27/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Wood Frame | 5/29/2020 | Corrections Issued | RAFAEL ESPINOZA |
| Special/Order Compliance | 6/2/2020 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 6/2/2020 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Wood Construction | 6/10/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Wood Frame | 6/11/2020 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Wood Construction | 6/23/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2020 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Wood Construction | 7/7/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2020 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Wood Construction | 7/13/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Wood Frame | 7/14/2020 | Corrections Issued | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 7/22/2020 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 7/24/2020 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 7/30/2020 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 8/21/2020 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 8/24/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 9/8/2020 | Not Ready for Inspection | DAVID BURKHEAD |
| Wood Frame | 9/9/2020 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 9/16/2020 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 9/18/2020 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 9/25/2020 | Corrections Issued | RAFAEL ESPINOZA |
| Drywall Nailing | 10/8/2020 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 10/8/2020 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 10/13/2020 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 10/22/2020 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 11/5/2020 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 11/16/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 11/20/2020 | Approved | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 11/24/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 11/25/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 12/9/2020 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 12/11/2020 | Partial Approval | NICK DANERI |
| Drywall Nailing | 12/23/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 12/23/2020 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 12/29/2020 | No Access for Inspection | RAFAEL ESPINOZA |
| Insulation | 12/29/2020 | Corrections Issued | RAFAEL ESPINOZA |
| Drywall Nailing | 1/4/2021 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 1/4/2021 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 1/19/2021 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 1/22/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 2/8/2021 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 2/9/2021 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 2/9/2021 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 2/12/2021 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 2/18/2021 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 3/1/2021 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 3/19/2021 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 4/8/2021 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 4/16/2021 | Partial Inspection | DAVID BURKHEAD |
| Light Gage Steel Frame | 4/23/2021 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 5/7/2021 | Partial Approval | NICK DANERI |
| Pre-Inspection | 5/14/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Special/Order Compliance | 5/18/2021 | Approved | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 6/8/2021 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 6/29/2021 | Partial Approval | RAFAEL ESPINOZA |
| T-Bar Ceiling | 7/14/2021 | Approved | RAFAEL ESPINOZA |
| Pre-Inspection | 7/16/2021 | Corrections Issued | RAFAEL ESPINOZA |
| T-Bar Ceiling | 7/16/2021 | Corrections Issued | RAFAEL ESPINOZA |
| Special/Order Compliance | 8/5/2021 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 9/24/2021 | Partial Inspection | DANIEL MC AULIFFE |
| Green Building Final | 9/24/2021 | Partial Inspection | DANIEL MC AULIFFE |
| Green Building Rough | 9/24/2021 | Approved | DANIEL MC AULIFFE |
| Reinforced Concrete Frame | 9/24/2021 | Approved | DANIEL MC AULIFFE |
| Reinforced Masonry Frame | 9/24/2021 | Approved | DANIEL MC AULIFFE |
| SGSOV-Seismic Gas S/O Valve | 9/24/2021 | SGSOV Approved | DANIEL MC AULIFFE |
| Smoke Detectors | 9/24/2021 | Approved | DANIEL MC AULIFFE |
| Final | 10/20/2021 | Partial Inspection | RAFAEL ESPINOZA |
| Special/Order Compliance | 6/8/2022 | Conditional Approval | NICK DANERI |
| Special/Order Compliance | 12/12/2022 | Approved | RAFAEL ESPINOZA |
| Final | 1/24/2023 | OK to Issue CofO | RAFAEL ESPINOZA |
| Green Building Final | 1/24/2023 | Approved | RAFAEL ESPINOZA |